|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To be submitted by Grantee with each grant drawdown application, or at intervals no greater than 3 months) |
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the Monitoring Documents referred to in your Grant Contract, you are required to submit to NHMF a Progress Report with each grant drawdown application, or at maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing towards meeting the Approved Purposes. The headings and format of the Report, addressing the principal monitoring criteria, are shown below. These headings and format must be followed, but you may prepare your Report using computer software incorporating spreadsheets as appropriate. All sections (expanded in size as necessary) are to be completed fully on each monthly report. (Use supplementary sheets if necessary). PM
forms should be returned in hardcopy and must be completed fully. Failure to
do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
18 |
|
Report Date: |
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
August 2000 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general
progress towards achievement of the Approved Purposes identifying any problems
or issues to which NHMF’s attention should be drawn. Note any actions proposed
in response to problems or particular areas of risk.
The project is within budget and is scheduled to be
completed on time. |
See annex 1 for detailed progress and throughput reports. |
See annex 2 for Project Board Minutes ( |
|
|
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing
partnership funds
Source of
Funding |
Amount
expected (A) |
Amount
received to date (B) |
Balance
to come A-B) |
Date
balance expected |
NAS |
£425,967 |
£52,165 |
£373,802 |
Aug 2002 |
GSU |
£703,785 |
£47,914 |
£655,871 |
Aug 2002 |
|
|
|
|
|
|
1,129,752 |
100,079 |
1,029,673 |
Aug 2002 |
Totals |
|
|
|
|
Explain
any changes to sources of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material
change to the Approved Purposes which
have been approved by NHMF since the last Report and advise of any potential
requests for such change in the future.
Description of Change Item |
Date of request to NHMF |
Date of NHMF
response |
Effect on
achievement of Approved Purposes |
Effect on Programme |
Effect on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any material change to the Approved Purposes
Report on any effect to delivery
of the Approved Purposes of any cost transfer between the principal cost
elements stated in your “Notification of Grant”. (Note: no such transfer is to
be made between capital and revenue elements, or between VAT and any other cost
element, without NHMF prior consent ).
Amount of cost transfer (£’000) |
Cost transfer from (cost element): |
Cost transfer to (cost element): |
Effect on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or
comments received from NHMF or its Project Monitors since your last report
Work element for which Design/Document review has been
carried out |
Date reviewed |
NHMF/Project Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the
agreed Timetable/Programme for key activities
Grant Expiry Date:
Key
Activity or milestone |
Planned
completion date |
Actual
(or currently forecast)
completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a)
Cost Control
Enter expenditure to date against
the key items of Approved Cost (i.e. the
costs on which NHMF has agreed to pay the Payment Percentage) compared with
that detailed in the pre-commencement documentation. (VAT and Contingencies to
be separately identified).
Items
of Approved Cost (Principal
cost elements) |
Approved Costs to completion as agreed at award |
Out-turn
Costs as currently forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual
costs to Date (C) |
Variance (C-B) |
Balance
of costs (A- C) |
Staff |
£2,170,889 |
£668,184 |
£668,184 |
£450,514 |
£-217,670 |
£217,670 |
Internet Server |
£449,700 |
£374,750 |
£374,750 |
|
£374,750 |
£374,750 |
Communication |
£51,222 |
£21,518 |
£21,518 |
£2,460 |
£-19,058 |
£19,058 |
Digitisation |
£349,191 |
£180,000 |
£180,000 |
£104,511 |
£-75,489 |
£75,489 |
Other |
£543,500 |
£235,200 |
£235,200 |
£115,807 |
£-119,393 |
£119,393 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£73,984 |
£73,984 |
|
£73,984 |
£73,984 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
£6,196,307 |
£1,553,636 |
£1,553,636 |
£673,292 |
£17,124 |
£880,344 |
Note any significant changes to
the apportionment of costs between the principal cost elements prior to their
commitment. Note the effect of any such changes and confirm that they will not
affect the Approved Purposes including expected quality.
Cost transfer from : |
Cost transfer to: |
Amount (£) |
Effect of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of
expenditure of the total Balance (A-C) calculated above and the funding sources
to cover the expenditure
|
To date |
Next Qtr |
2nd Qtr |
3rd Qtr |
4th Qtr |
5th Qtr |
Later |
Total to Completion |
Expenditure
of Approved Cost |
Enter Total of C above |
|
|
|
|
|
|
Enter Total of
A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£673,292 |
|
|
|
|
|
|
£1,553,636 |
Other source (1) |
|
|
|
|
|
|
|
|
Other source (2) |
|
|
|
|
|
|
|
|
Other source (3) |
|
|
|
|
|
|
|
|
Total Funding (to equal Expenditure of Approved Cost) |
£673,292 |
|
|
|
|
|
|
£1,553,636 |
7. Procurement
Enter the current procurement
status of any significant goods, works, or services currently being procured
for the project, or awarded since the last Report.
Goods/Works/ Services
: brief description |
Approx
Value |
EU
procurement Applies? Yes./No |
No of
tenderers |
Date of
tender return |
Date of
award |
Selected
Contractor/supplier/ consultant |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services
not awarded to the lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note
any evidence provided at the request of NHMF or the Project Monitor.
Property
Description and evidence provided |
Date
evidence provided to NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have
effected:
Cover |
Effective
From Date |
Expiry
Date |
Employer Liability Insurance |
21/10/99 |
20/10/00 |
Computer Insurance |
21/10/99 |
21/10/00 |
Office Insurance: Including Goods In Transit &
Officers Liability Insurance. |
21/10/99 |
21/10/00 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried
Staff (Note: applicable only to staff whose salaries are included as Eligible
Costs in the Approved project.
Position |
Date
Appointed |
Job
Description sent to NHMF (Yes/No) |
Media in
which advert placed |
Employment Contract
to NHMF (Yes/No) |
Digital Imager |
07/08/00 |
Yes |
Scottish Exec News |
No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer
Staff
The total number of Volunteer
staff employed at present is …………4……
(Details are provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal
statutory consents required to complete the project
Consent
Required |
Granting
Authority |
Actual or
expected date of consent |
Planning |
N/A |
|
Listed Building |
|
|
Scheduled Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement,
press releases, or other publicity issued since the last report:
Description |
Date
Issued |
Approved
by NHMF (Yes/No) |
Displayed acknowledgement |
N/A |
|
Press Releases issued |
|
|
Publicity issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making
photographic records of the project Y
14. Special Conditions
Indicate progress towards
satisfying the Special Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See
pages 10-16 inclusive of HLF/ SCAN contract 6 July 1999 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Grantee: Scottish Archive Network
Address: Thomas Thomson House, 99 Bankhead Crossway North,
Edinburgh, EH11 4DX
Signed for Grantee: …Ishbel Barnes……………………………………………………..
Date: …………19/09/00……………….
Visits, either formal or informal, were
paid to: Royal College of Surgeons, Edinburgh; Heriot-Watt University Archives;
Stirling University Library; and Stirling Council Archives. Only in the latter is there any hope of TLFA
creation work occurring this calendar year, as we have already made sufficient
commitments in general for the rest of 2000.
TLFA creation
continued for most of the current archives, including Jordanhill Library, NAS,
Highland Council Archives, Aberdeen University Library Special Collections, and
Orkney Archives. Work on the latter two
mostly comprised shell-entry creation using basic guides to the archives, which
will then need to be fleshed out during visits to the archives, which are
expected to take place shortly. Jo
Peattie more or less completed some very important work on devising TLFA
entries for fonds commonly encountered at local authority archives, eg
commissioners of supply records. When
complete they will be sent out to relevant archives for comment. The hope is that these entries will be used
as the basis for the Admin/Biog History element wherever the appropriate
records are found, but leaving room for local variants if required.
The TLFA for the
Royal College of Physicians and Surgeons of Glasgow was quality checked during
the month, and some minor final adjustments required to be made before it could
be sent out for local comment. Further
TLFA entries for Angus and Perth and Kinross Archives were read, and some
comments began to be received for sections of their TLFAs already sent out. We were pleased to note that on the whole the
archives involved were content with what they had seen.
All the staff
were involved in the formal SCAN Strategy Review in mid-August. Rachael Third and Jo Peattie each had over a
week’s leave during the month.
The advert for
John MacKenzie’s post appeared in mid-August.
Because the post will not be filled for perhaps a couple of months yet,
there will be a spell of some weeks while the project cannot proceed as swiftly
as expected. The performance measures
for the next month or two will be adjusted to take account of the
shortfall. Furthermore, we learned in
the course of August that Rachael Third had been offered a post in another
archive network project, which she accepted.
She is likely to leave SCAN at the end of September. This will unfortunately make life worse in
the short term, although it will be possible (all being well) to recruit her replacement off the same board used for the other
current vacancy.
Special
Archive Services Project
Gary
Clelland, the new digital imaging technician for the Special Archive Services
team, started in post on 7 August. Gary was given training in handling
documents and photographs by both Peter Dickson and Dagmar Hinz from the
Conservation team. Joanna Baird and Gary Clelland visited the Scottish Newspapers
Microfilming Unit on 16 August. Gary attended a training course in Photoshop
5.5 on Thursday 24 August. Joanna and Gary visited General Register House on 29
August as part of an informal staff induction process.
Robin Urquhart visited the National Railway Museum in York on 1 and 29
August to discuss and research for the ‘North by Northwest exhibition’. Robin also held a meeting with John Burnett
from the National Museums of Scotland regarding the exhibition and possible
links to the Scottish Life Archive.
Both
Joanna Baird and Robin Urquhart attended the SCAN strategy review days from 10
to 11 August.
Joanna and Robin compiled images and text to give to the web design
company, Multimedia, for the development of the exhibition ‘North by
Northwest’. Joanna created a booklet to
publicise the exhibition in advance of the exhibition sponsors’ open day to be
held on 4 September.
Robin Urquhart has been liaising with
The Kodak Megaplus 6.3i camera ordered in July was delivered to site,
together with lenses, frame grabber board and foot switch. This now awaits
assembly once the copy stands and book cradles arrive. Meanwhile, preparations for
the next round of camera procurement are well in hand. The camera identified as
meeting our requirements most closely is the new Atmel Camelia 8M, a single
shot camera with higher resolution than the Kodak Megaplus 6.3i (at a much
lower price). The camera is fully software compliant and has been rigorously
tested in trials at the GSU Europe technical laboratories, from whom
In
consultation with Hazel Rob Mildren has been developing a quality control
programme for the digital images, which will randomly select a required
percentage of images for inspection after the initial capture stage
On the curatorial side, work has continued on checking indexes and
preparing the Aberdeen warrants (CC1/6) for conservation. The index to St
Andrews testaments up to 1800 has been transposed from alphabetical into
chronological order and
Work on the conservation of the Edinburgh registers has been progressing
well and is currently ahead of schedule. Proposals for conservation of the
Aberdeen warrants are also progressing well. In light of the failure to recruit
a third conservator arrangements have gone ahead to recruit a preservation
assistant from within the Scottish Executive and the post was advertised on 30
August. Peter Dickson and Dagmar Hinz both gave archive handling training to
Gary Clelland, the new digital imager for SAS.
The GSU volunteers completed work on the post-1823 registers for
Aberdeen, Perth and Cupar and began work on the Dundee registers. Mr and Mrs
McLaws finished their tour of duty and left at the end of the month. Their
replacements and a further two volunteers are due to arrive in the second week
of September.
All
the Testaments team took part in two days of review and planning of the SCAN
project. As a result, revised performance measures were agreed and compilation
of statistics for these new measures is ongoing. Milestones relating to digital
capture await agreement with the HLF on image resolution.
Throughput Reports
|
August 2000 – predicted |
August - achieved |
September 2000 - Predicted |
Cumulative Totals |
Topic Pages - drafted |
6 |
5 |
11 |
63 |
FAQ’s - drafted |
5 |
1 |
0 |
84 |
Topic Pages – quality controlled |
5 |
0 |
0 |
15 |
FAQ’s – quality controlled |
0 |
0 |
0 |
41 |
Palaeography texts and transcripts added |
1 |
1 |
2 |
13 |
Palaeography tips added |
1 |
1 |
2 |
10 |
‘Featured Documents’ added |
4 |
4 |
5 |
60 |
Images created |
- |
250 |
300 |
250 |
The
amount of completed work on the Knowledge Base was less than expected during
August. However, resources were redirected to assimilating data sent by Glasgow
& West of Scotland Family History Society (a member of the user’s group),
which will enhance and speed up work on the places section of the Knowledge
Base. In addition, more work than expected was required on the North by
Northwest exhibition, in order to provide the designers with enough material to
compile a prototype of the exhibition in preparation for the sponsors’ open day
on 5 September.
As Gary Clelland only started in his post as digital imaging technician
for Special Archive Services team on 7 August we have no imaging predictions
for August 2000. The prediction for September is tentative and it is assumed
that the correct equipment is in place and working.
|
August 2000- Predicted |
August 2000 - Achieved |
September 2000 - Predicted |
Totals achieved |
TLFA initial draft entries –drafted |
300
|
400
|
300
|
3740
|
TLFA initial draft entries - quality controlled |
150
|
70
|
150
|
1360
|
TLFA entries - revised within SCAN |
150
|
390
|
150
|
950
|
TLFA entries –agreed by SCAN and
part. archive |
200
|
0
|
200
|
169
|
Testaments Editorial
|
August 2000Predicted |
August 2000Achieved |
September 2000
Predicted |
Testaments registers SC1/37/44-70
SC20/50/10-27 SC45/31/1-26 SC49/31/27-69 |
|
|
|
Index entries created
|
9000
|
11771
|
5000
|
Vols/Pages numbered
|
10/11000
|
26/28358
|
35/37500
|
Testaments Conservation |
August 2000 Predicted |
August 2000 Achieved |
September 2000 Predicted |
Vols. assessed |
0 |
0 |
0 |
Folios cleaned |
2500 |
10441 |
10000 |
Vols. paginated |
10 |
30 |
30 |
Folios conserved |
500 |
650 |
500 |
Vols.rebound |
0 |
0 |
0 |
Vols. completed |
10 |
15 |
15 |
At 31 August there were 462 volumes of the total of 2033
volumes ready for digital capture = 22.7% of the total.
These figures break down as follows:
Pre-1823 volumes: 83 completed (including conservation) out of 567
= 14.6%
Post-1823 volumes: 379 completed out of 1466 = 25.9%
Notes of Project Board Meeting
8 August 2000 10.00am
Attendees: Ishbel Barnes
(Chair), Rob Mildren, George Mackenzie, Stuart Low (Minute Secretary).
1. Review
of Work Plans
1.1 It
was agreed that the existing format for Project Board reports would continue
until after the strategy review meeting on 10/11th August.
1. 2 Special
Archive Services sub-Project
1.2.1 It was noted that Joanna would liase with the NAS regarding the award of the NAS website design contract to MMI. It was agreed that SCAN would place the order with MMI, on behalf of the NAS, and that a reasonable administration charge would be levied as a way of formalising the business transaction.
1.2.2 It was noted that agreement needs to be reached between SCAN and the NAS as to how digital images will eventually be linked to the electronic catalogues. As an interim solution it was proposed to use a system of reference numbers to keep track of any digital images made. It was also agreed that it might be best to organise imaging schedules around complete runs and Ishbel agreed to discuss this with both Joanna and Rosemary.
The sub-project work plans for both July and August were agreed and approved.
1.3 Testaments
1.3.1 It was agreed that the throughput estimates
and milestones for the Testaments sub-project should be recast at the strategy
review on 10/11th August.
The sub-project work plans for both July and August were agreed and approved.
1.4 Top
Level Finding Aids sub-Project
1.4.1 It was agreed to discuss the construction of
specific timetables for work carried out in each of the participating archives
at the strategy review on 10/11th August.
The sub-project works plan for both July and August were agreed and approved.
2. Procurement
2.2.1 It was confirmed that one complete camera
station had been procured from Edit Ltd, although it was noted that the GSU
were still discussing the issue of their software licence. It is expected to
have a fully functioning camera station in place by the end of September.
2.2.2 It was noted that the ICT Internet
connections would be in place by 22nd August and that Morse would
install the Server and associated equipment after this date.
2.2.3 It was noted that Arkis 2 was still seen to
be the best technical solution to SCAN’s needs, although a few problems had
been identified. This mainly concerned translating the language used by both
the labelling system and the core programming from Swedish to English.
3.1.1 It was noted that the Digital Imager, Mr Garry Clelland had taken up post on 7th August.
3.1.2 It was noted that it had now been agreed between SCAN and the NAS to appoint a Conservator Technician and that steps had been taken to progress this.
3.1.3 It was noted that SCAN had now requested a third archivist to appointed from the posts due to be advertised in the SoA Journal on 15th August.
4. Finance
4.1.1 A written report was tabled, of which an
extract is attached.
5. User
Group Meeting
5.1 It was noted that the next meeting of
the User Group would take place on Saturday 7th October at TTH
between 10.45 and 3.00. It was confirmed that Agenda items had been requested.
It was also noted that it was expected that the users would have the chance to
test out some aspects of the website.
6. Participating
Archives Working Group Meeting
6.1 It was noted that the next meeting of
the participating archives working group would take place on Tuesday 29th
August at the NLS (Lawn market) at 10.00.
7. SCAN
Launch & Dissemination Campaign
7.1.1 A draft copy of the proposed dissemination
campaign plan was tabled for discussion and approval. It was agreed that the
campaign plan should be discussed at the HLF Monitoring meeting to gauge
reaction. It was also agreed that monthly reports on dissemination activity
should be tabled at future project boards. [Extract Attached].
The next Project Board meeting will be held on Wednesday 6th September at 10.00 in Thomas Thomson House, Bankhead Crossway North, Edinburgh.
SL
8 August 2000
[EXTRACT]
1. HLF Drawdowns
1.1 The July
drawdown for £27,489.05 submitted on 19 July is currently being assessed.
1.2 The advance
request for £62,000 submitted to the HLF on 19 July with regard to the
procurement of 1 digital camera and 3 bookcradles and associated equipment is
currently being assessed.
1.3 The August drawdown is under preparation and
should be submitted on 17 August with the monthly report for July.
Scottish Archive Network
[Extract]
Step 1: The objectives of the campaign are:
·
To raise the profile of the Scottish Archive Network
(SCAN) amongst its relevant publics.
·
To present Archives in a fresh and appealing way,
which promotes the accessibility and uniqueness of SCAN’s services and products
to its targeted publics.
·
To promote SCAN’s Internet website as the first
point of contact for those who might be interested in researching Scotland’s
history.
·
To attract commercial sponsorship and advertising to
ensure the continuation of the project after 2002.
·
To assist in the sales and marketing of SCAN’s
services and products using a co-ordinated and consistent promotional theme.
Step 2: Budget:
The budget allocation for
dissemination activities has been fixed at TBA
Step 3: Targeted Publics:
·
Archive Users – Public & Professional
·
Archivists
·
Genealogists
·
Tourists
·
Paleographers
·
Family & Local History Internet Users
·
Record Agents
·
Social Historians
·
Media Journalists
Targeted User Organizations:
·
Academic & Educational Institutions
·
Information Providers
·
Digitization Agencies
·
Scottish Local History Forums
·
Scottish History Societies
·
Scottish Records Association
·
Society of Archivists
·
Society of Genealogists
·
NRA
·
Scottish Tourist Information Board
·
Media Organizations
Targeted
On-Line Organizations:
·
Internet Search Engines
·
GENUKI
·
NewsGroups
·
BBC Online
·
Digitizing websites
·
Conservation News
·
Journal of Online Genealogy
·
Genealogical websites
·
Scotland.org
·
Conservation News
Locality:
·
Scottish market
·
U.K. market
·
North American market
· Australasian Market
Step 4: Research:
·
Investigate the needs and requirements of targeted
users.
·
Evaluate the competition.
·
Identify superior aspects of SCAN products and
services against market competition.
·
Identify marketing strategies and priorities.
·
Identify advertising and publicity strategies and
priorities.
·
Identify potential sponsors and fundraising
opportunities.
Step 5: Strategies:
1. Direct
Marketing: - Advertising & promotion of products services.
·
CD-Rom based marketing/promotional media.
·
Customizing website to suit corporate clients
specific requirements.
·
Participating Archives.
·
Mail shots & Flyer Inserts.
·
Internet advertising.
2. Publicity: - Press
Releases, Press Conferences and Interviews.
·
Print Media Radio Media TV Media
·
Press Agencies National Terrestrial
·
International Regional
Cable/Satellite
·
National Daily Local
·
National Sunday
·
Regional Daily
·
Regional Sunday
·
Local
·
Magazines/Journals
·
Historical & Genealogical Guides
·
Internet Media Other
·
Search Engines Participant
Archives
·
Websites
3. Promotion: - Design
& Produce Promotional Material.
·
Publicity & Promotion Packs
·
Merchandise
·
Competitions
4. Sponsorship &
Fundraising:
·
Corporate Events
·
Exhibition Launches
·
Networking
·
Corporate Presentations
·
Grant Applications
Step 7: Produce necessary material
Step 8: Implementation
Step 9: Campaign Supervision
·
Maintain and monitor press cutting portfolio to show
amount of editorial coverage gained.
·
Evaluate effectiveness of marketing and advertising
strategies in terms of sales figures and website hits.
·
Evaluate effectiveness of sponsorship and
fundraising activities in terms of revenue generation.
·
Evaluate campaign budget in relation to manpower,
time and materials against product sales, web site hits and revenue generated.