|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To be submitted by Grantee with each grant drawdown application, or at intervals no greater than 3 months) |
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the Monitoring Documents referred to in your Grant Contract, you are required to submit to NHMF a Progress Report with each grant drawdown application, or at maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing towards meeting the Approved Purposes. The headings and format of the Report, addressing the principal monitoring criteria, are shown below. These headings and format must be followed, but you may prepare your Report using computer software incorporating spreadsheets as appropriate. All sections (expanded in size as necessary) are to be completed fully on each monthly report. (Use supplementary sheets if necessary). PM
forms should be returned in hardcopy and must be completed fully. Failure to
do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
19 |
|
Report Date: |
19 Oct 2000 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Sept 2000 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general
progress towards achievement of the Approved Purposes identifying any problems
or issues to which NHMF’s attention should be drawn. Note any actions proposed
in response to problems or particular areas of risk.
The project is within budget and is scheduled to be
completed on time. |
See annex 1 for detailed progress and throughput reports. |
See annex 2 for Project Board Minutes (11/10/00) |
Detailed Response to HLF Correspondence of 08/09/00 To Follow |
|
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing
partnership funds
Source of
Funding |
Amount
expected (A) |
Amount
received to date (B) |
Balance
to come A-B) |
Date
balance expected |
NAS |
£425,967 |
£55,930 |
£370,037 |
Aug 2002 |
GSU |
£703,785 |
£54,711 |
£649,074 |
Aug 2002 |
|
|
|
|
|
|
1,129,752 |
110,641 |
1,019,111 |
Aug 2002 |
Totals |
|
|
|
|
Explain
any changes to sources of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material
change to the Approved Purposes which
have been approved by NHMF since the last Report and advise of any potential
requests for such change in the future.
Description of Change Item |
Date of request to NHMF |
Date of NHMF
response |
Effect on
achievement of Approved Purposes |
Effect on Programme |
Effect on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any material change to the Approved Purposes
Report on any effect to delivery
of the Approved Purposes of any cost transfer between the principal cost
elements stated in your “Notification of Grant”. (Note: no such transfer is to
be made between capital and revenue elements, or between VAT and any other cost
element, without NHMF prior consent ).
Amount of cost transfer (£’000) |
Cost transfer from (cost element): |
Cost transfer to (cost element): |
Effect on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or
comments received from NHMF or its Project Monitors since your last report
Work element for which Design/Document review has been
carried out |
Date reviewed |
NHMF/Project Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the
agreed Timetable/Programme for key activities
Grant Expiry Date:
Key
Activity or milestone |
Planned
completion date |
Actual
(or currently forecast)
completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a)
Cost Control
Enter expenditure to date against
the key items of Approved Cost (i.e. the
costs on which NHMF has agreed to pay the Payment Percentage) compared with
that detailed in the pre-commencement documentation. (VAT and Contingencies to
be separately identified).
Items
of Approved Cost (Principal
cost elements) |
Approved Costs to completion as agreed at award |
Out-turn
Costs as currently forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual
costs to Date (C) |
Variance (C-B) |
Balance
of costs (A- C) |
Staff |
£2,170,889 |
£851,441 |
£851,441 |
£492,400 |
£-359,041 |
£359,041 |
Internet Server |
£449,700 |
£374,750 |
£374,750 |
|
£374,750 |
£374,750 |
Communication |
£51,222 |
£24,768 |
£24,768 |
£2,460 |
£-22,308 |
£22,308 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£104,511 |
£-94,239 |
£94,239 |
Other |
£543,500 |
£298,925 |
£298,925 |
£127,878 |
£-171,047 |
£171,047 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£87,433 |
£87,433 |
|
£73,984 |
£73,984 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
£6,196,307 |
£1,836,067 |
£1,836,067 |
£727,249 |
£-197,901 |
£1,095,369 |
Note any significant changes to
the apportionment of costs between the principal cost elements prior to their
commitment. Note the effect of any such changes and confirm that they will not
affect the Approved Purposes including expected quality.
Cost transfer from : |
Cost transfer to: |
Amount (£) |
Effect of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of
expenditure of the total Balance (A-C) calculated above and the funding sources
to cover the expenditure
|
To date |
Next Qtr |
2nd Qtr |
3rd Qtr |
4th Qtr |
5th Qtr |
Later |
Total to Completion |
Expenditure
of Approved Cost |
Enter Total of C above |
|
|
|
|
|
|
Enter Total of
A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£727,249 |
|
|
|
|
|
|
£1,836,067 |
Other source (1) |
|
|
|
|
|
|
|
|
Other source (2) |
|
|
|
|
|
|
|
|
Other source (3) |
|
|
|
|
|
|
|
|
Total Funding (to equal Expenditure of Approved Cost) |
£727,249 |
|
|
|
|
|
|
£1,836,067 |
7. Procurement
Enter the current procurement
status of any significant goods, works, or services currently being procured
for the project, or awarded since the last Report.
Goods/Works/ Services
: brief description |
Approx
Value |
EU
procurement Applies? Yes./No |
No of
tenderers |
Date of
tender return |
Date of
award |
Selected
Contractor/supplier/ consultant |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services
not awarded to the lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note
any evidence provided at the request of NHMF or the Project Monitor.
Property
Description and evidence provided |
Date
evidence provided to NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have
effected:
Cover |
Effective
From Date |
Expiry
Date |
Employer Liability Insurance |
21/10/00 |
20/10/01 |
Computer Insurance |
21/10/00 |
21/10/01 |
Office Insurance: Including Goods In Transit &
Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried
Staff (Note: applicable only to staff whose salaries are included as Eligible
Costs in the Approved project.
Position |
Date Appointed |
Job
Description sent to NHMF (Yes/No) |
Media in
which advert placed |
Employment Contract
to NHMF (Yes/No) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer
Staff
The total number of Volunteer
staff employed at present is …………6……
(Details are provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal
statutory consents required to complete the project
Consent
Required |
Granting
Authority |
Actual or
expected date of consent |
Planning |
N/A |
|
Listed Building |
|
|
Scheduled Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement,
press releases, or other publicity issued since the last report:
Description |
Date
Issued |
Approved
by NHMF (Yes/No) |
Displayed acknowledgement |
N/A |
|
Press Releases issued |
|
|
Publicity issued |
See Article Attached |
|
|
|
|
13. Photographic Records
Y
Confirm that you are making
photographic records of the project Y
14. Special Conditions
Indicate progress towards
satisfying the Special Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See
pages 10-16 inclusive of HLF/ SCAN contract 6 July 1999 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Grantee: Scottish Archive Network
Address: Thomas Thomson House, 99 Bankhead Crossway North,
Edinburgh, EH11 4DX
Signed for Grantee: …Ishbel Barnes……………………………………………………..
Date: …………19/10/00……………….
Preliminary
assessment visits were undertaken at the National Trust for Scotland Archives,
Midlothian Council Archives, Edinburgh University Library Special Collections
& Archives, and North Lanarkshire Council Archives. In the last two cases, all being well the participating
archive will be providing SCAN with the data it requires, subject to (we hope)
only minor amendments. In the case of
the first two mentioned, no TLFA creation work is expected to take place in
even 2001, as in neither case is the archive in a strong enough position at
present to be able to cope with the additional duties required.
TLFA creation
work continued for Orkney Archives, both by Alan Borthwick (who paid a further
week’s visit mid-month), and Jo Peattie, who began to fill in some of the gaps
in basic shell entries for the small, deposited collections held there. Some
work was also done on NAS collections, covering British Railways, County
Council and District Council records.
Some revision of entries was undertaken for Perth and Kinross Council
Archives.
Jo Peattie
completed a draft of some “common fonds” entries, which are Administrative
Histories for collections of records commonly found in local authority archives
(only those so far tackled). We hope
that these standard entries will be used wherever such collections are found
within the participating archives, with the addition of local variants as
required. The entries were sent off to
appropriate participating archives for comment.
Few comments have been received so far, but those which have arrived
have complimentary.
Comments on
TLFAs circulated for consideration were received back from Angus Council
Archives, and Falkirk Museums History Research Centre. Changes suggested by the first of those were
incorporated, but it was no possible to consider the comments submitted by the
second before the end of the month.
All of the team
assisted with preparations for the 5 September exhibition launch reported on
fully by the SAS project, and Alan had prepared some TLFA entries for some of
the pre-nationalisation independent railway operating companies for handouts.
John MacKenzie’s
vacant post will not be filled for some weeks yet, although interviews will be
held in mid-October. Rachael Third left
SCAN at the end of September to take up a post in another archive network project,
and if practicable her post will also be filled by the October interviews. There will be a spell of some weeks while the
project cannot proceed as swiftly as expected because of the staff shortage. The performance measures for the next month
or two will be adjusted to take account of the shortfall.
The Special
Archive Services team of Joanna Baird, Robin Urquhart and Gary Clelland were
all involved in the preparation and organisation of the ‘North by Northwest’
exhibition sponsors’ day which was held on 5 September. This event was arranged
to thank the sponsors for their contributions and to give them an insight into
SCAN. Despite a low turnout, the feedback was very positive.
Joanna and Robin
held a meeting with Multimedia Incorporated on Friday to discuss progress on
the website design. Much of September was spent in compiling and revising copy
to appear on the site for the 30 November launch.
Robin made
several visits during the course of September, including a visit to Dumfries
Archive Centre and members of the Users Group in Dumfries, and a visit to the
National Library of Scotland.
Due to a series
of camera malfunctions, only 132 out of the predicted 350 images were created
by Gary Clelland in September. Gary’s new PC arrived at the beginning of
September but initially the digital camera would not work in conjunction with
Windows NT. It was initially thought this was due to a problem with an outdated
plug-in, but extensive testing suggested this was not the case. Also, the
digital camera itself was producing very mixed results and Gary borrowed an
identical camera from the National Library of Scotland. Tests with this camera
proved that the fault was not in fact with the camera but with either the cable
or the PC. Gary tested his camera on a set-up at the British Geological Survey
and this conclusively proved that the problem lay with the cable – which showed
signs of damage. The failure of the cable may also explain the inability of the
camera to function alongside the plug-in. This testing process took up the
whole of September.
Throughput Reports
|
September 2000 - predicted |
September 2000- achieved |
October 2000 - Predicted |
Cumulative Totals |
Knowledge Base entries - drafted |
11 |
12 |
14 |
159 |
Knowledge Base entries - quality-controlled |
0 |
0 |
0 |
56 |
Knowledge Base entries – added to site (figures begin from November 2000) |
0 |
0 |
0 |
0 |
Palaeography texts, tips and transcripts added |
4 |
6 |
3 |
23 |
Bookshop entries added |
0 |
0 |
0 |
10 |
Virtual Strongroom and Research Tools entries added |
0 |
3 |
1 |
3 |
‘Featured Documents’ added |
4 |
4 |
5 |
60 |
Images created |
300 |
132 |
350 |
382 |
What’s New entries added (figures to begin from December 2000) |
N/A |
N/A |
N/A |
|
Exhibition entries added (caption and image) |
8 |
2 |
2 |
36 |
Directory entries added (figures begin from November 2000) |
0 |
0 |
0 |
|
Visits made/talks given |
4 |
6 |
20 |
The amount of completed work on the Knowledge Base was about what was expected. In addition, two new parts of the Scottish Handwriting pages were created (one hour basic tutorial and a palaeography coach), and a new part of the website: the Virtual Strongroom was created, with images to back up entries in the Knowledge Base.
Due to the malfunction of the digital camera, only 132 images out of the predicted 300 were created by Gary Clelland in the course of September.
|
September 2000- Predicted |
September 2000 - Achieved |
October 2000 – Predicted |
Totals achieved |
TLFA initial draft entries –drafted |
300
|
200
|
150
|
3940
|
TLFA initial draft entries - quality controlled |
150
|
0
|
50
|
1360
|
TLFA entries - revised within SCAN |
150
|
40
|
100
|
990
|
TLFA entries –agreed by SCAN and
part. archive |
200
|
100
|
100
|
269
|
Further shell TLFA entries exist, but they have mostly not been entered
in the stats as yet as further work on them is required
The stats for September/October reflect the shortage of staff, and the
requirement to undertake TLFA Compilation Guidelines, which makes quality
checking hard to fit in.
Testaments Editorial
|
August 2000Predicted |
August 2000Achieved |
September 2000
Predicted |
Testaments registers SC1/37/44-70
SC20/50/10-27 SC45/31/1-26 SC49/31/27-69 |
|
|
|
Index entries created
|
9000
|
11771
|
5000
|
Vols/Pages numbered
|
10/11000
|
26/28358
|
35/37500
|
Testaments Conservation |
August 2000 Predicted |
August 2000 Achieved |
September 2000 Predicted |
Vols. assessed |
0 |
0 |
0 |
Folios cleaned |
2500 |
10441 |
10000 |
Vols. paginated |
10 |
30 |
30 |
Folios conserved |
500 |
650 |
500 |
Vols.rebound |
0 |
0 |
0 |
Vols. completed |
10 |
15 |
15 |
Minutes
Present:
Mr Mildren, Mr MacKenzie, Dr Barnes.
1. The
minutes of the previous project board were agreed.
2. Review of Work Plans
The
monthly work plans and throughput figures for the three sub projects were
agreed.
3.
Procurement.
3.1 Digital cameras
It was noted that there had been very considerable problems with the
installation of the new camera. The problems had not been solved by Edit but by
the staff of SCAN and the GSU. Edit’s performance had been fairly dismal. The
next task was the assessment of the Atmel Camelia camera. The board asked Mr
Mildren to carry this assessment forward as expeditiously as possible.
3.2 ICT equipment
Mr
Mildren reported that if Edit’s performance was fairly dismal that of Morse was
deeply dismal. They were now in the seventh week of a four week contract. He
had now written to them stating his dissatisfaction with their work and warning
them about the consequences. The board agreed to keep the matter under constant
revue.
3.3 Cataloguing software
Dr Barnes reported on the series of meetings Mr Cadell and herself had
had with Mr Norberg, the head of the Swedish National Archive and his
colleagues. It had been agreed in principal that Scotland and Sweden will form
a consortium to develop ARKIS and that profits of future sales will be returned
to the consortium. The consortium will hold the copyright of the system.
Scotland will pay Sweden a sum to be agreed to help pay for past development
costs. Dr Barnes said that she was now working with the Swedes to draft this
agreement.
4. Staffing
4.1 Conservator post. Dr Barnes reported that the board for this post
would be held within the next two weeks.
4.2 Curatorial posts. Dr Barnes reported that by the end of November the
TLFA project would have three vacancies. There would be a joint NAS/SCAN board
on 12 October but there seemed little doubt that not all the vacant posts would
be filled. This would have the obvious result of delaying the TLFA sub project.
She would continue to try and find suitable candidates to fill the vacant posts
5. Finance
In Mr
Low’s absence no detailed financial statement was produced for the board but Dr
Barnes confirmed that the finances were in order.
6. User Group
Dr
Barnes reported that the meeting of the Users Group held on 7 October had been
most successful. The trials of the digital images of the testaments had been
most instructive and the users had been most surprised at the high quality of
the images. They had also been most complementary about the web site design.
7. Participating Archives Working Group
Dr
Barnes reported that she was waiting for further written proposals from Dr
O’Brien.
8. SCAN
launch strategy.
It was
agreed that this would be looked at again following the sad news of Mr Dewar’s
death. It had been hoped that Mr Dewar would officially launch the network on 30 November. It was agreed however
that 30 November would remain the launch date.
9.
A.O.C.B.
9.1 It
was agreed that the English version of the ICA Dictionary of Archival
Terminology would be incorporated in the SCAN site and that further IT work
would be carried out on it as soon as practicable.
9.2 It was agreed that Dr Barnes would write to Tods Murray WS about the
copyright statement needed for the SCAN web pages.
10. Date
of next meeting.