Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To be submitted by Grantee with each grant drawdown application, or at intervals no greater than 3 months) |
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the Monitoring Documents referred to in your Grant Contract, you are required to submit to NHMF a Progress Report with each grant drawdown application, or at maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing towards meeting the Approved Purposes. The headings and format of the Report, addressing the principal monitoring criteria, are shown below. These headings and format must be followed, but you may prepare your Report using computer software incorporating spreadsheets as appropriate. All sections (expanded in size as necessary) are to be completed fully on each monthly report. (Use supplementary sheets if necessary). PM
forms should be returned in hardcopy and must be completed fully. Failure to
do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
20 |
|
Report Date: |
14 Nov 2000 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Oct 2000 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general
progress towards achievement of the Approved Purposes identifying any problems
or issues to which NHMFs attention should be drawn. Note any actions proposed
in response to problems or particular areas of risk.
The project is within budget and is scheduled to be
completed on time. |
See annex 1 for detailed progress and throughput reports. |
See annex 2 for Project Board Minutes (11/10/00) |
|
|
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing
partnership funds
Source of
Funding |
Amount
expected (A) |
Amount
received to date (B) |
Balance
to come A-B) |
Date
balance expected |
NAS |
£425,967 |
£59,695 |
£366,272 |
Aug 2002 |
GSU |
£703,785 |
£69,564 |
£634,221 |
Aug 2002 |
|
|
|
|
|
|
1,129,752 |
129,259 |
1,000,493 |
Aug 2002 |
Totals |
|
|
|
|
Explain
any changes to sources of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material
change to the Approved Purposes which
have been approved by NHMF since the last Report and advise of any potential
requests for such change in the future.
Description of Change Item |
Date of request to NHMF |
Date of NHMF
response |
Effect on
achievement of Approved Purposes |
Effect on Programme |
Effect on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any material change to the Approved Purposes
Report on any effect to delivery
of the Approved Purposes of any cost transfer between the principal cost
elements stated in your Notification of Grant. (Note: no such transfer is to
be made between capital and revenue elements, or between VAT and any other cost
element, without NHMF prior consent ).
Amount of cost transfer (£000) |
Cost transfer from (cost element): |
Cost transfer to (cost element): |
Effect on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or
comments received from NHMF or its Project Monitors since your last report
Work element for which Design/Document review has been
carried out |
Date reviewed |
NHMF/Project Monitors comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the
agreed Timetable/Programme for key activities
Grant Expiry Date:
Key
Activity or milestone |
Planned
completion date |
Actual
(or currently forecast)
completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a)
Cost Control
Enter expenditure to date against
the key items of Approved Cost (i.e. the
costs on which NHMF has agreed to pay the Payment Percentage) compared with
that detailed in the pre-commencement documentation. (VAT and Contingencies to
be separately identified).
Items
of Approved Cost (Principal
cost elements) |
Approved Costs to completion as agreed at award |
Out-turn
Costs as currently forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual
costs to Date (C) |
Variance (C-B) |
Balance
of costs (A- C) |
Staff |
£2,170,889 |
£851,441 |
£851,441 |
£536,113 |
£-315,328 |
£315,328 |
Internet Server |
£449,700 |
£374,750 |
£374,750 |
|
£374,750 |
£374,750 |
Communication |
£51,222 |
£24,768 |
£24,768 |
£2,460 |
£-22,308 |
£22,308 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£111,195 |
£-87,555 |
£87,555 |
Other |
£543,500 |
£298,925 |
£298,925 |
£142,999 |
£-155,926 |
£155,926 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£87,433 |
£87,433 |
|
£73,984 |
£73,984 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
£6,196,307 |
£1,836,067 |
£1,836,067 |
£792,767 |
£-132,383 |
£1,029,851 |
Note any significant changes to
the apportionment of costs between the principal cost elements prior to their
commitment. Note the effect of any such changes and confirm that they will not
affect the Approved Purposes including expected quality.
Cost transfer from : |
Cost transfer to: |
Amount (£) |
Effect of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of
expenditure of the total Balance (A-C) calculated above and the funding sources
to cover the expenditure
|
To date |
Next Qtr |
2nd Qtr |
3rd Qtr |
4th Qtr |
5th Qtr |
Later |
Total to Completion |
Expenditure
of Approved Cost |
Enter Total of C above |
|
|
|
|
|
|
Enter Total of
A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£792,767 |
|
|
|
|
|
|
£1,836,067 |
Other source (1) |
|
|
|
|
|
|
|
|
Other source (2) |
|
|
|
|
|
|
|
|
Other source (3) |
|
|
|
|
|
|
|
|
Total Funding (to equal Expenditure of Approved Cost) |
£792,767 |
|
|
|
|
|
|
£1,836,067 |
7. Procurement
Enter the current procurement
status of any significant goods, works, or services currently being procured
for the project, or awarded since the last Report.
Goods/Works/ Services
: brief description |
Approx
Value |
EU
procurement Applies? Yes./No |
No of
tenderers |
Date of
tender return |
Date of
award |
Selected
Contractor/supplier/ consultant |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services
not awarded to the lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note
any evidence provided at the request of NHMF or the Project Monitor.
Property
Description and evidence provided |
Date
evidence provided to NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have
effected:
Cover |
Effective
From Date |
Expiry
Date |
Employer Liability Insurance |
21/10/00 |
20/10/01 |
Computer Insurance |
21/10/00 |
21/10/01 |
Office Insurance: Including Goods In Transit &
Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to Revenue elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried
Staff (Note: applicable only to staff whose salaries are included as Eligible
Costs in the Approved project.
Position |
Date
Appointed |
Job
Description sent to NHMF (Yes/No) |
Media in
which advert placed |
Employment Contract
to NHMF (Yes/No) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer
Staff
The total number of Volunteer
staff employed at present is
9
(Details are provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal
statutory consents required to complete the project
Consent
Required |
Granting
Authority |
Actual or
expected date of consent |
Planning |
N/A |
|
Listed Building |
|
|
Scheduled Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement,
press releases, or other publicity issued since the last report:
Description |
Date
Issued |
Approved
by NHMF (Yes/No) |
Displayed acknowledgement |
N/A |
|
Press Releases issued |
|
|
Publicity issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making
photographic records of the project Y
14. Special Conditions
Indicate progress towards
satisfying the Special Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See
pages 10-16 inclusive of HLF/ SCAN contract 6 July 1999 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Grantee: Scottish Archive Network
Address: Thomas Thomson House, 99 Bankhead Crossway North,
Edinburgh, EH11 4DX
Signed for Grantee:
Ishbel Barnes
..
Date:
.