Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To be submitted by Grantee with each grant drawdown application, or at intervals no greater than 3 months) |
|
||||||||||
|
Form PM3(Part
2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the Monitoring Documents referred to in your Grant Contract, you are required to submit to NHMF a Progress Report with each grant drawdown application, or at maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing towards meeting the Approved Purposes. The headings and format of the Report, addressing the principal monitoring criteria, are shown below. These headings and format must be followed, but you may prepare your Report using computer software incorporating spreadsheets as appropriate. All sections (expanded in size as necessary) are to be completed fully on each monthly report. (Use supplementary sheets if necessary). PM
forms should be returned in hardcopy and must be completed fully. Failure to
do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
23 |
|
Report Date: |
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Feb 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general
progress towards achievement of the Approved Purposes identifying any problems
or issues to which NHMF’s attention should be drawn. Note any actions proposed
in response to problems or particular areas of risk.
The project remains within budget and is scheduled to be
completed on time. |
See annex 1 for detailed progress and throughput reports. |
A Project Board was not convened in February as it proved
impossible to arrange a convenient meeting date to secure a quorum. A board
was held in March. |
See annex 2 for update on special conditions |
|
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing
partnership funds
Source of
Funding |
Amount
expected (A) |
Amount
received to date (B) |
Balance
to come A-B) |
Date
balance expected |
NAS |
Ł425,967 |
Ł76,875 |
Ł349,092 |
Aug 2002 |
GSU |
Ł703,785 |
Ł136,700 |
Ł567,085 |
Aug 2002 |
|
|
|
|
|
|
1,129,752 |
213,575 |
916,177 |
Aug 2002 |
Totals |
|
|
|
|
Explain
any changes to sources of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material
change to the Approved Purposes which have been approved by NHMF since
the last Report and advise of any potential requests for such change in the
future.
Description of Change Item |
Date of request to NHMF |
Date of NHMF
response |
Effect on
achievement of Approved Purposes |
Effect on Programme |
Effect on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any material change to the Approved Purposes
Report on any effect to delivery
of the Approved Purposes of any cost transfer between the principal cost
elements stated in your “Notification of Grant”. (Note: no such transfer is to
be made between capital and revenue elements, or between VAT and any other cost
element, without NHMF prior consent ).
Amount of cost transfer (Ł’000) |
Cost transfer from (cost element): |
Cost transfer to (cost element): |
Effect on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or
comments received from NHMF or its Project Monitors since your last report
Work element for which Design/Document review has been
carried out |
Date reviewed |
NHMF/Project Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the
agreed Timetable/Programme for key activities
Grant Expiry Date:
Key
Activity or milestone |
Planned
completion date |
Actual
(or currently forecast)
completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a)
Cost Control
Enter expenditure to date against
the key items of
Approved Cost (i.e. the costs on which NHMF has agreed to pay the
Payment Percentage) compared with that detailed in the pre-commencement
documentation. (VAT and Contingencies to be separately
identified).
Items
of Approved Cost (Principal
cost elements) |
Approved Costs to completion as agreed at award |
Out-turn
Costs as currently forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual
costs to Date (C) |
Variance (C-B) |
Balance
of costs (A- C) |
Staff |
Ł2,170,889 |
Ł1,217,955 |
Ł1,217,955 |
Ł728,419 |
Ł-489,536 |
Ł489,536 |
Internet Server |
Ł449,700 |
Ł412,225 |
Ł412,225 |
Ł142,848 |
Ł-269,377 |
Ł269,377 |
Communication |
Ł51,222 |
Ł31,268 |
Ł31,268 |
Ł15,902 |
Ł- 15,366 |
Ł15,366 |
Digitisation |
Ł349,191 |
Ł198,750 |
Ł198,750 |
Ł154,595 |
Ł- 44,155 |
Ł44,155 |
Other |
Ł543,500 |
Ł383,950 |
Ł383,950 |
Ł186,805 |
Ł-197,145 |
Ł197,145 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
Ł2,631,805 |
Ł112,209 |
Ł112,209 |
|
Ł-112,209 |
Ł112,209 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
Ł6,196,307 |
Ł2,356,357 |
Ł2,356,357 |
Ł1,228,569 |
Ł-1,127,788 |
Ł1,127,788 |
Note any significant changes to
the apportionment of costs between the principal cost elements prior to their
commitment. Note the effect of any such changes and confirm that they will not
affect the Approved Purposes including expected quality.
Cost transfer from : |
Cost transfer to: |
Amount (Ł) |
Effect of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of
expenditure of the total Balance (A-C) calculated above and the funding sources
to cover the expenditure
|
To date |
Next Qtr |
2nd Qtr |
3rd Qtr |
4th Qtr |
5th Qtr |
Later |
Total to Completion |
Expenditure
of Approved Cost |
Enter Total of C above |
|
|
|
|
|
|
Enter Total of
A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
Ł1,228,569 |
|
|
|
|
|
|
Ł2,356,357 |
Other source (1) |
|
|
|
|
|
|
|
|
Other source (2) |
|
|
|
|
|
|
|
|
Other source (3) |
|
|
|
|
|
|
|
|
Total Funding (to equal Expenditure of Approved Cost) |
Ł1,228,569 |
|
|
|
|
|
|
Ł2,356,357 |
|
|
|
|
|
|
|
|
|
7. Procurement
Enter the current procurement
status of any significant goods, works, or services currently being procured
for the project, or awarded since the last Report.
Goods/Works/ Services
: brief description |
Approx
Value |
EU
procurement Applies? Yes./No |
No of
tenderers |
Date of
tender return |
Date of
award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services
not awarded to the lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note
any evidence provided at the request of NHMF or the Project Monitor.
Property
Description and evidence provided |
Date
evidence provided to NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective
From Date |
Expiry
Date |
Employer Liability Insurance |
|
|
Computer Insurance |
|
|
Office Insurance: Including Goods In Transit &
Officers Liability Insurance. |
|
|
10. Appointment of Staff
(Revenue Elements only, if any)
List the salaried staff appointed
(applicable to “Revenue” elements of project only) since your last Report and
the total number of volunteers currently employed (if any).
a) Salaried
Staff (Note: applicable only to staff whose salaries are included as Eligible
Costs in the Approved project.
Position |
Date
Appointed |
Job
Description sent to NHMF (Yes/No) |
Media in
which advert placed |
Employment Contract
to NHMF (Yes/No) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer
Staff
The total number of Volunteer staff employed at
present is …………11…… (Details are provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal
statutory consents required to complete the project
Consent
Required |
Granting
Authority |
Actual or
expected date of consent |
Planning |
N/A |
|
Listed Building |
|
|
Scheduled Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement,
press releases, or other publicity issued since the last report:
Description |
Date
Issued |
Approved
by NHMF (Yes/No) |
Displayed acknowledgement |
N/A |
|
Press Releases issued |
|
|
Publicity issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making
photographic records of the project Y
14. Special Conditions
Indicate progress towards
satisfying the Special Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See
Annex 3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Grantee: Scottish Archive Network
Address: Thomas Thomson House, 99
Bankhead Crossway North,
Signed for Grantee: …
Date:
Initial visits were paid to Northern Health Services
Archive,
Work was formally started on the collections
description for Northern Health Services Archive, and continued at Dundee City
Archives and Aberdeen University Library Special Collections/Archives.
The checking of the reviewed data from the Royal College of Physicians
and Surgeons, Glasgow, was completed, and some suggestions as to the best means
of compiling the data in some awkward cases were made. The College’s archivist visited on 26
February to discuss the work, and will further consider how best to close off
work on this archive very soon. A visit
was paid to the Scottish Theatre Archive in an effort to bring the conclusion
of its work closer.
Meetings with the recently appointed Fife Council
Archivist and the head of a Scottish place-names studies institute were
attended.
Three students were interviewed with a view to their
undertaking some transfer of data from our old MS Word-based collection
description entries to the in-house “Wee Arkis” Access database, which will
allow simple transfer in the long run to the ARKIS II system. It is hoped that we shall be able to start
the students on the work in early April.
The general staffing position eased further during
the month when a 12 March start-date was confirmed for another casual
(part-time) member of staff. As a very
experienced archivist it is unlikely that he will require much training before
he becomes effective.
An important set of comments on the “Collections Description Guidelines”
was received on 13 February, which will allow revised “Guidelines” to be
issued, perhaps during April.
Internet
Resources project
It was still not
possible to link the SCAN knowledge base to a database/searchable mechanism in
February. It is hoped that this will be made available in early March in time
for the meeting of the Users Group/Participating Archives working group.
The registration
process was automated by the designers, but something in the way our server is
set up is preventing this information from being automatically added to a
database as planned. Therefore registration requests were manually added by
Joanna. This should be resolved in March.
More enquiries/points were posted to the Forum. In some cases either Joanna or Robin posted answers to queries. Joanna will ask Bill to look into threading the Forum into a series of themed discussion areas in March. 7 Enquiries were received via the email form and Joanna answered them or forwarded them within a few days of receipt.
Joanna added a
‘property’ section to the ‘Virtual Strongroom’ and a ‘GRO(S)’ section to the
SCAN ‘Bookshop’.
Joanna met with
Robin Prior of ADS data services on 28 February to discuss some potential data
capture work. Joanna also met with the design company Evolution Design on 27
February, to discuss some redesign work for SCAN publicity material as the
existing material is out of date/irrelevant. Joanna drafted new
leaflets/publicity material in preparation for the meeting.
Joanna emailed
all the participating archives on Thursday 15th February to ask for
information for various parts of the website. 2 responses were received in
February.
Joanna liaised with Alec Murdoch to try
and agree a schedule for the Users/PAWG meeting on 10 March in the absence of
Joanna Baird
continued to attend the Scottish Enteprise ‘Marketing Advance Programme’ with
Technical
problems continued to trouble the Kontron camera and therefore Joanna
asked the National Library if they could
borrow their Kontron camera until the new SCAN one arrives at the end of March.
They agreed to this and the NLS camera was in place on Friday 9th
February.
Modifications to
the 120° book cradle were carried out by IKM at the beginning of February.
These enabled the single page capture programme to be started with St Andrews
testaments (CC20/7) and a number of Aberdeen warrants (CC1/6)
Two requests were received from the public search rooms for Aberdeen
warrants (CC1/6) out to SCAN. As a result, 182 images were captured and CD Roms
produced for readers. It was decided not to undertake any further ad hoc
capture of the warrants, but to start a programme for their capture in April,
after the installation of the second 120° book cradle.
Publications and Education Branch requested images of 11 pages of
Edinburgh testaments.
The work of identification, conservation, digitisation and general
administration for all these requests took 45 hours.
Hazel also attended a meeting of the Electronic Access for Readers
Working Group on 21 February at West Register House.
Throughput Report
|
February 2001 - predicted
|
February 2001 |
March 2001 - predicted |
Cumulative Totals |
Knowledge Base entries – added to site (figures begin from December 2000) |
12 |
20 |
15 |
50 |
Palaeography texts, tips and transcripts added |
2 |
2 |
2 |
8 |
Bookshop entries added |
1 |
1 |
0 |
10 |
Virtual Strongroom Research Tools entries added |
0 |
1 |
|
4 |
‘Featured Documents’ added |
2 |
2 |
3 |
64 |
Images created (inc JPEG copies made for web) |
300 |
225 |
300 |
1583 |
What’s New entries added (figures to begin from December 2000) |
1 |
2 |
2 |
N/A |
Exhibition entries added (caption and image) |
0 |
0 |
0 |
38 |
Directory entries added (figures begin from November 2000) |
1 |
2 |
||
Press Box content added |
0 |
0 |
||
Visits made/talks given |
0 |
4 |
37 |
|
Microsites added/linked |
1 |
1 |
||
Registered users |
- |
243 |
||
Enquiries received |
|
22 |
||
Forum postings |
|
54 |
||
Articles written |
0 |
|
1 |
|
Web statistics |
|
|
|
|
Requests
|
63057 |
|
252054 |
|
Pages |
30359 |
|
124506 |
Online
Catalogues
All figures contained within separate Excel
spreadsheet.
Editorial
|
February 2001 predicted |
February 2001 achieved |
March 2001 predicted |
Cumulative total |
Index entries created |
17500 |
18671 |
18500 |
137731 |
Vols/pages numbered |
100/70000 |
166/134622 |
150/125000 |
1012/912809 |
Index/image linking ß |
|
|
|
|
Vols |
- |
1 |
3 |
1 |
Images |
- |
479 |
1400 |
479 |
Index entries |
- |
118 |
345 |
118 |
Conservation |
February 2001 predicted |
February 2001 achieved |
March 2001 predicted |
Cumulative total assessed |
Volumes Assessed/ Paginated |
20/20 |
20/10 |
20/15 |
222 |
Volume pages cleaned repaired |
2500 + 200 |
3790 + 380 |
2500 + 200 |
55797 + 5477 = 61274 |
Volumes completed |
10 |
6 |
10 |
121 |
Loose documents assessed |
0 |
0 |
0 |
26075 |
Loose documents cleaned/ repaired |
500pp (= 250ff) |
482 pp (= 241 ff) |
1100 pp (= 550 ff) |
2704 pp (= 1352 ff) |
At 28 February there were 1133 volumes of the total of 2033
volumes ready for digital capture = 55% of the total.
These figures break down as follows:
Pre-1823 volumes: 121 completed (including conservation) out of 567
= 21%
Post-1823 volumes: 1012 completed out of 1466 = 69%
Digital
capture
|
February
predicted |
February achieved |
March predicted |
Cumulative
total |
Vols
captured |
20 |
36 |
40 |
94 |
Double
pages |
8000 |
19199 |
20000 |
36847 |
Single
pages |
3000 |
5878 |
7500 |
5878 |
Vols
quality checked |
15 |
31 |
35 |
74 |
HLF Contract Special
Conditions
11.1 |
A |
Schedule of Requirements for the Supply of Digital Cameras |
October 1999 |
|
|
Information and Communications Technology Requirements |
March 1999 |
|
|
Information and Communications Technology Tender Document |
February 2000 |
|
|
Test plan submitted for installation of ICT equipment |
October 2000 |
|
|
Data Capture Specification for Indexes |
November 1999 |
|
|
Website design specification |
November 1999 |
|
b) |
Evaluation and selection criteria for ICT equipment submitted in
evaluation report “SCAN ICT Requirements Tender Report” |
April 2000 |
|
|
Book Cradle Evaluation |
July 2000 |
|
|
Web Site Tender Evaluation |
January 2000 |
|
|
Camera Evaluation for HLF |
May 2000 |
|
|
Resolution Requirements for Testaments |
May 2000 |
|
|
Data Capture Tender Evaluation |
December 2000 |
|
c) |
Weekly backups and daily incremental backups take place for all SCAN
information (excluding images) Uncompressed TIFF images are written to DLT and stored locally Compressed JPEG images are written to the Internet Server where a
backup is taken weekly |
|
|
d) |
|
|
|
e) |
|
|
|
f) |
|
|
|
g) |
All manuals received for ICT equipment and standard operation of
digital cameras Additional operator manual developed with GSU for the use of the
digital camera |
|
12.1 |
|
A presentation and report covering the entire ICT requirements for the
project was given |
May 2000 |
|
|
Information and Communications Technology Requirements |
March 1999 |
|
|
Information and Communications Technology Tender Document |
February 2000 |
|
|
Test plan submitted for installation of ICT equipment |
October 2000 |
|
|
Data Capture Specification for Indexes |
November 1999 |
13 |
|
Escrow discussed for deposit of digital images. SCAN has a contract
clause with GSU to provide mutual restore and backup of digital images |
|
14 |
|
Not done but there are all such applications to date have been
developed, and belong to, Scottish Archive Network |
|