|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To be submitted by Grantee with each grant drawdown application, or at intervals no greater than 3 months) |
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the Monitoring Documents referred to in your Grant Contract, you are required to submit to NHMF a Progress Report with each grant drawdown application, or at maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing towards meeting the Approved Purposes. The headings and format of the Report, addressing the principal monitoring criteria, are shown below. These headings and format must be followed, but you may prepare your Report using computer software incorporating spreadsheets as appropriate. All sections (expanded in size as necessary) are to be completed fully on each monthly report. (Use supplementary sheets if necessary). PM
forms should be returned in hardcopy and must be completed fully. Failure to
do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
24 |
|
Report Date: |
19 Apr 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Mar 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general
progress towards achievement of the Approved Purposes identifying any problems
or issues to which NHMF’s attention should be drawn. Note any actions proposed
in response to problems or particular areas of risk.
The project remains within budget and is scheduled to be
completed on time. |
See annex 1 for detailed progress and throughput reports. |
See annex 2 for update on special conditions |
See annex 3 for performance data |
The minutes of the Project Board held on 14 March are
attached at Annex 4 |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing
partnership funds
Source of
Funding |
Amount
expected (A) |
Amount
received to date (B) |
Balance
to come A-B) |
Date
balance expected |
NAS |
£425,967 |
£80,905 |
£345,062 |
Dec 2002 |
GSU |
£703,785 |
£152,650 |
£551,135 |
Dec 2002 |
|
|
|
|
|
|
£1,129,752 |
£233,555 |
£896,197 |
Dec 2002 |
Totals |
|
|
|
|
Explain
any changes to sources of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material
change to the Approved Purposes which
have been approved by NHMF since the last Report and advise of any potential
requests for such change in the future.
Description of Change Item |
Date of request to NHMF |
Date of NHMF
response |
Effect on
achievement of Approved Purposes |
Effect on Programme |
Effect on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any material change to the Approved Purposes
Report on any effect to delivery
of the Approved Purposes of any cost transfer between the principal cost
elements stated in your “Notification of Grant”. (Note: no such transfer is to
be made between capital and revenue elements, or between VAT and any other cost
element, without NHMF prior consent ).
Amount of cost transfer (£’000) |
Cost transfer from (cost element): |
Cost transfer to (cost element): |
Effect on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or
comments received from NHMF or its Project Monitors since your last report
Work element for which Design/Document review has been
carried out |
Date reviewed |
NHMF/Project Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the
agreed Timetable/Programme for key activities
Grant Expiry Date:
Key
Activity or milestone |
Planned
completion date |
Actual
(or currently forecast)
completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a)
Cost Control
Enter expenditure to date against
the key items of Approved Cost (i.e. the
costs on which NHMF has agreed to pay the Payment Percentage) compared with
that detailed in the pre-commencement documentation. (VAT and Contingencies to
be separately identified).
Items
of Approved Cost (Principal
cost elements) |
Approved Costs to completion as agreed at award |
Out-turn
Costs as currently forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual
costs to Date (C) |
Variance (C-B) |
Balance
of costs (A- C) |
Staff |
£2,170,889 |
£1,217,955 |
£1,217,955 |
£776,647 |
£-441,308 |
£441,308 |
Internet Server |
£449,700 |
£412,225 |
£412,225 |
£139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£31,268 |
£31,268 |
£24,571 |
£- 6,697 |
£ 6,697 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£155,224 |
£- 43,526 |
£43,526 |
Other |
£543,500 |
£383,950 |
£383,950 |
£205,271 |
£-178,679 |
£178,679 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£112,209 |
£112,209 |
|
£-112,209 |
£112,209 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals |
£6,196,307 |
£2,356,357 |
£2,356,357 |
£1,301,561 |
£-1,054,796 |
£1,054,796 |
Note any significant changes to
the apportionment of costs between the principal cost elements prior to their
commitment. Note the effect of any such changes and confirm that they will not
affect the Approved Purposes including expected quality.
Cost transfer from : |
Cost transfer to: |
Amount (£) |
Effect of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of
expenditure of the total Balance (A-C) calculated above and the funding sources
to cover the expenditure
|
To date |
Next Qtr |
2nd Qtr |
3rd Qtr |
4th Qtr |
5th Qtr |
Later |
Total to Completion |
Expenditure
of Approved Cost |
Enter Total of C above |
|
|
|
|
|
|
Enter Total of
A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,301,561 |
|
|
|
|
|
|
£2,356,357 |
Other source (1) |
|
|
|
|
|
|
|
|
Other source (2) |
|
|
|
|
|
|
|
|
Other source (3) |
|
|
|
|
|
|
|
|
Total Funding (to equal Expenditure of Approved Cost) |
£1,301,561 |
|
|
|
|
|
|
£2,356,357 |
|
|
|
|
|
|
|
|
|
7. Procurement
Enter the current procurement
status of any significant goods, works, or services currently being procured
for the project, or awarded since the last Report.
Goods/Works/ Services
: brief description |
Approx
Value |
EU
procurement Applies? Yes./No |
No of
tenderers |
Date of
tender return |
Date of
award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services
not awarded to the lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note
any evidence provided at the request of NHMF or the Project Monitor.
Property
Description and evidence provided |
Date
evidence provided to NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have
effected:
Cover |
Effective
From Date |
Expiry
Date |
Employer Liability Insurance |
21/10/00 |
20/10/01 |
Computer Insurance |
21/10/00 |
21/10/01 |
Office Insurance: Including Goods In Transit &
Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried
Staff (Note: applicable only to staff whose salaries are included as Eligible
Costs in the Approved project.
Position |
Date
Appointed |
Job
Description sent to NHMF (Yes/No) |
Media in
which advert placed |
Employment Contract
to NHMF (Yes/No) |
Curatorial (Casual) |
12/03/01 |
Yes |
Scottish Exec Recruitment |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer
Staff
The total number of Volunteer
staff employed at present is …………11……
(Details are provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal
statutory consents required to complete the project
Consent
Required |
Granting
Authority |
Actual or
expected date of consent |
Planning |
N/A |
|
Listed Building |
|
|
Scheduled Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement,
press releases, or other publicity issued since the last report:
Description |
Date
Issued |
Approved
by NHMF (Yes/No) |
Displayed acknowledgement |
N/A |
|
Press Releases issued |
|
|
Publicity issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making
photographic records of the project Y
14. Special Conditions
Indicate progress towards
satisfying the Special Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See
Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name of Grantee: Scottish Archive Network
Address: Thomas Thomson House, 99 Bankhead Crossway North,
Edinburgh, EH11 4DX
Signed for Grantee: …Rob Mildren……………………………………………………..
Date: 19/04/01………………………….
Progress
An initial visit was made to one Archive during the
month: the Clan Donald Centre, Skye, where the visit was combined with the
start of collection description work. In
the course of the visit there a good part of the work required was completed, and
we hope that no return visit will be needed.
Collection description work also began on another new Archive: Glasgow
City Archives. This is the largest
Archive outside the two main national bodies, the National Archives and the
National Library. The work is being done
at present by a casual member of staff who began work with us on 12 March, but
who (as the former head of the Archive) has extensive knowledge of its
collections.
The appointment of this casual member of staff
brings the staffing complement nearly back to normal; and even though we have
two people on casual (short-term) contracts we hope now to be able to make good
progress again in collection description creation. (Adverts for general staff recruitment on a
fixed-term basis appeared at the start of April.) To ensure that the staff in the team knew
what the current state of play was with various issues we had a team meeting on
7 March, which was also the chance for staff working remotely to meet the
others for the first time.
Jenny Cutts continued her
collection description work at Dundee City Archives, completing the bulk of the
work needed on the deposited collections by the end of the month. Nicola Mills continued work on both the
Aberdeen University Library Special Collections Dept and Northern Health
Services Archive collection descriptions.
Alan Borthwick interviewed
two further people as potential recruits for the task of converting the older
collection description data into the “WeeArkis”
access database. Personnel were asked to
start their procedures for formally recruiting these staff, the final terms and
conditions more or less being worked out by the end of the month.
Members of staff from the Riksarkivet, Sweden,
visited TTH on 26 and 27 March to talk about progress with ARKIS II, and SCAN
now has a version of ARKIS loaded on to its server which will be able to host
our collection description data and eventually be used to provide general
public access.
Training and Outreach
Alan Borthwick spent some
time at the end of the month preparing for a lecture (about SCAN and collection
description work) to be given at a Conference in Lund, Sweden, called “Access
to Official Document and Archives”, on 6 April.
He also gave a general talk about SCAN’s work
to the Central Scotland Family History Society in Stirling, 28 March; and spoke
on 6 March to Valerie Adams, Public Record Office of Northern Ireland, about
Online Catalogues. He attended the joint
meeting of the Users’ Group and the Participating Archives Working Group,
Glasgow, 10 March, and gave a brief update on Online Catalogues.
Alan Borthwick attended a
training course given by the Scottish Executive on 27 March about their new
performance appraisal system which is to be effective from April 2001. He also attended a presentation given by a
member of the “Picture Australia” project, which presents digitised images of
photos and paintings of works held by Australian libraries and museums, 5
March. Jenny Cutts
attended a Scottish Executive new staff induction day session, 16 March.
A search
mechanism was made to function in the Knowledge Base in time for the Users/PAWG
meeting on 10th March however the group found it too complicated for
the amount of information that was then available. They did not find it user-friendly to have a
quantity of search results pages when one or two
would have done.They also preferred to carry out a
simple cross-site search for keywords rather than a search within a specific
website area – something they could already do on the SCAN site. It was agreed
to institute something simpler for the time being for the people, subjects and
record types areas. The ‘places’ section may require something more
sophisticated in the near future. Joanna therefore added 4 drop-down menus to
the Knowledge Base home page which link to the relevant pages.
It was still not
possible to automate registrations to the SCAN website during the course of
March and therefore they were manually added by Joanna.
Joanna asked
Bill to look at threading the discussions posted to the ‘Forum’ – essentially
creating several different ‘Fora’. This was a
response to the volume of usage and type of enquries
that the Forum is currently receiving but it was also highlighted as a priority
by the Users and Participating Archives during the meeting at the beginning of
March. The Forum was out of action for approximately 2-3 weeks in March due to
a technical problem which was resolved in late March.
Robin
demonstrated the SCAN website to East Ayrshire Family
History Society on 8 March, to a meeting of the Highland local history
societies in Nairn on 19 March and to Troon & South Ayrshire Family
History Society on 20 March. He visited Highland Council Archive for research
on 19 March.
Joanna added pages for the Scottish Text Society and also for the Stair Society to the SCAN site. The former were available immediately after creation but the latter require some further text to be added before they can be made publicly available.
Joanna also met with the design company Evolution Design several times during the course of March to finalise the design of our new publicity material. Joanna drafted 1 leaflet and 1 insert - both containing captions and images - and liaised with Margaret Fox to design 1 insert for the Wills project.
Joanna Baird attended the meeting of the Users Group and the PAWG on
Saturday 10 March in Glasgow. Joanna attended a meeting of the Secondment Network Group held by the Scottish Executive on
Thursday 29th March.
Joanna Baird continued to attend the Scottish Enteprise
‘Marketing Advance Programme’ with Stuart Low.
Joanna and Stuart drafted an interim report of their findings so far for
circulation and discussion with the rest of SCAN and the business manager.
The team were still using the Kontron camera
borrowed from the National Library of Scotland in February. However, the green
glass on the book cradle and lack of corrective software currently available
meant that the images taken were kept to a minimum because the quality was not
really acceptable. Much effort was expended on printing out some 1500 images in
colour in preparation for both the retiral of Dr Barnes and Tartan Day on 6 April. As the only
existing colour printer was on the 2nd floor,
this involved a considerable amount of time on Gary’s part. Fortunately, a new colour printer was ordered in March for Gary Clelland’s specific use. This should arrive in early
April. The new digital camera for the
Internet Resources team is expected to arrive in the first or second week of
April. It is expected that the team can enter full ‘production mode’ in mid to
late April.
During the month
the HLF monitors confirmed that the SCAN criteria for single and double page
capture of the testaments were acceptable. The GSU volunteers made good
progress with the double page capture of the post-1823 Aberdeen Inventories
(SC1/36) and the single page capture of the pre-1823 St Andrews testaments
(CC20/4 & 7).
Hazel Anderson
was in regular contact with IKM, suppliers of the Atmel
cameras and the book cradles in the second round of procurement, to facilitate
the delivery and installation of the equipment exactly to specification in
April.
Valerie Adams, Public Record Office of Northern Ireland, visited SCAN for
two days to inform herself about the digitisation
equipment and workflow in the Testaments project.
Hazel attended the Users’ Group meeting at Glasgow University on Saturday
10 March, where she gave a presentation on progress in the project and showed
examples of digital images, which were well received.
Hazel also attended a training session on the Scottish Executive’s new
Performance Management system at General Register House on 27 March.
|
March
2001 – predicted
|
March 2001 |
April 2001 - predicted |
Cumulative Totals |
Knowledge Base entries – added to site (figures begin from December 2000) |
15 |
33 |
226 |
83 |
Palaeography texts, tips and transcripts added |
2 |
4 |
2 |
12 |
Bookshop entries added |
0 |
0 |
0 |
10 |
Virtual Strongroom Research Tools entries added |
0 |
0 |
2 |
4 |
‘Featured Documents’ added |
3 |
3 |
3 |
67 |
Images created (inc JPEG copies made for web) |
300 |
96 |
300 |
1808 |
What’s New entries added (figures to begin from December 2000) |
2 |
5 |
2 |
N/A |
Exhibition entries added (caption and image) |
0 |
0 |
0 |
38 |
Directory entries added (figures begin from November 2000) |
2 |
2 |
||
Press Box content added |
0 |
0 |
||
Visits made/talks given |
5 |
2 |
42 |
|
Microsites added/linked |
0 |
3 |
||
Registered users |
- |
292 |
||
Enquiries received |
|
25 |
||
Forum postings |
|
60 |
||
Articles written |
1 |
0 |
2 |
|
Web statistics |
|
|
|
|
Requests
|
77645 |
|
329699 |
|
Pages |
37496 |
|
162002 |
2. Online Catalogues
All
figures contained within separate Excel spreadsheet.
Editorial
|
March 2001
predicted |
March 2001
achieved |
April 2001 predicted |
Cumulative total |
Index entries created |
18500 |
22402 |
20000 |
160133 |
Vols/pages numbered |
150/125000 |
162/144958 |
155/130000 |
1178/1047431 |
Index/image linking ß |
|
|
|
|
Vols |
3 |
5 |
5 |
5 |
Images |
1400 |
2560 |
2600 |
2560 |
Index entries |
345 |
517 |
500 |
517 |
Conservation
|
March 2001 predicted |
March 2001
achieved |
April 2001 predicted |
Cumulative total assessed |
Volumes Assessed/ Paginated |
20/15 |
0/7 |
35/15 |
222 |
Volume pages Cleaned & repaired |
2700 |
2765 |
2700 |
64039 |
Volumes completed |
10 |
6 |
15 |
127 |
Loose documents assessed |
0 |
0 |
0 |
0 |
Loose documents cleaned/ repaired |
1130 pp (= 565 ff) |
1510 pp (= 755 ff) |
550 pp (= 275 ff) |
4214 pp (= 2107 ff) |
At 30 March there were 1305 volumes of the total of 2033
volumes ready for digital capture = 64%% of the total.
These figures break down as follows:
Pre-1823 volumes: 127 completed (including conservation) out of 567
= 22 %
Post-1823 volumes: 1178 completed out of 1466 = 80 %
Digital capture
|
March predicted |
March achieved |
April predicted |
Cumulative
total |
Vols
captured |
40 |
35 |
35 |
129 |
Double
pages |
20000 |
22453 |
22000 |
59300 |
Single
pages |
7500 |
9262 |
9000 |
15140 |
Vols
quality checked |
35 |
26 |
30 |
100 |
11.1 |
A |
Schedule of Requirements for the Supply of Digital Cameras |
October 1999 |
|
|
Information and Communications Technology Requirements |
March 1999 |
|
|
Information and Communications Technology Tender Document |
February 2000 |
|
|
Test plan submitted for installation of ICT equipment |
October 2000 |
|
|
Data Capture Specification for Indexes |
November 1999 |
|
|
Website design specification |
November 1999 |
|
b) |
Evaluation and selection criteria for ICT equipment submitted in
evaluation report “SCAN ICT Requirements Tender Report” |
April 2000 |
|
|
Book Cradle Evaluation |
July 2000 |
|
|
Web Site Tender Evaluation |
January 2000 |
|
|
Camera Evaluation for HLF |
May 2000 |
|
|
Resolution Requirements for Testaments |
May 2000 |
|
|
Data Capture Tender Evaluation |
December 2000 |
|
c) |
Weekly backups and daily incremental backups take place for all SCAN
information (excluding images) Uncompressed TIFF images are written to DLT and stored locally Compressed JPEG images are written to the Internet Server where a
backup is taken weekly |
April 2001 November 2000 (and ongoing) November 2000 (and ongoing) |
|
d) |
|
|
|
e) |
|
|
|
f) |
|
|
|
g) |
All manuals received for ICT equipment and standard operation of
digital cameras Additional operator manual developed with GSU for the use of the
digital camera |
|
12.1 |
|
A presentation and report covering the entire ICT requirements for the
project was given |
May 2000 |
|
|
Information and Communications Technology Requirements |
March 1999 |
|
|
Information and Communications Technology Tender Document |
February 2000 |
|
|
Test plan submitted for installation of ICT equipment |
October 2000 |
|
|
Data Capture Specification for Indexes |
November 1999 |
13 |
|
Escrow discussed for deposit of digital images. SCAN has a contract
clause with GSU to provide mutual restore and backup of digital images |
Early discussions held with NCC Follow Up Required |
14 |
|
Escrow discussed for deposit of any software packages |
Early discussions held with NCC Follow Up Required |
Annex 3
Internet Resources performance spreadsheet |
|
March |
|
CUMULATIVE
TOTAL |
2000-2001 |
|
|
|
|
|
|
|
|
|
Images Created |
|
|
|
|
Documents |
|
|
|
|
|
TIFF's |
41 |
|
|
|
JPEG's |
55 |
|
|
DOCUMENTS TOTAL |
|
96 |
|
765 |
Glass Plate Negatives |
|
|
|
|
|
TIFF's |
0 |
|
|
|
JPEG's |
0 |
|
|
GLASS PLATE NEG TOTAL |
|
0 |
|
18 |
Other |
|
|
|
|
|
TIFF's |
20 |
|
|
|
JPEG's |
109 |
|
|
OTHER TOTAL |
|
129 |
|
|
TOTAL |
|
225 |
|
1808 |
|
|
|
|
|
Knowledge Base Entries added to
website |
|
|
|
|
People |
|
0 |
|
|
Places |
|
1 |
|
|
Subjects |
|
11 |
|
|
Types of Record |
|
21 |
|
|
Family History |
|
0 |
|
|
TOTAL |
|
33 |
|
88 |
|
|
|
|
|
Palaeography pages added to website |
|
|
|
|
Tips |
|
2 |
|
|
Posers |
|
2 |
|
|
Other Pages |
|
0 |
|
|
TOTAL |
|
4 |
|
18 |
|
|
|
|
|
Research Tools added to website |
|
|
|
|
Virtual Strongroom
entries |
|
0 |
|
|
Other Research tools |
|
|
|
|
TOTAL |
|
0 |
|
4 |
|
|
|
|
|
Featured Documents added to
website |
|
|
|
|
Featured Docs added |
|
3 |
|
10 |
|
|
|
|
|
What's New entries added to
website |
|
4 |
|
10 |
|
|
|
|
|
|
|
|
|
|
Directory entries added to
website |
|
|
|
4 |
|
|
|
|
|
Microsites created/linked to |
|
2 |
|
3 |
|
|
|
|
|
Exhibition added to website |
|
|
|
0 |
Entries added |
|
|
|
|
|
|
|
|
|
PR |
|
|
|
|
Press Releases added to site |
|
0 |
|
2 |
Visits made/talks given |
|
5 |
|
44 |
Talks given |
|
|
|
0 |
TOTAL |
|
5 |
|
11 |
|
|
|
|
|
|
|
|
|
|
Bookshop |
|
|
|
|
Entries added |
|
|
|
1 |
|
|
|
|
|
Enquiries received |
|
3 |
|
25 |
Users registered |
|
49 |
|
292 |
Forum postings |
|
6 |
|
60 |
|
|
|
|
|
Web statistics |
|
|
|
|
Requests |
|
77645 |
|
329699 |
Pages |
|
37496 |
|
162002 |
Notes of Project Board Meeting
14 March 2001 16.00
Attendees: Ishbel Barnes (Chair), Rob Mildren,
Peter Anderson, Stuart Low (Minute Secretary).
Apologies: George
Mackenzie
1. Minutes of Last
Meeting and Matters Arising
1.1 The minutes of
the last meeting were approved and there were no matters arising.
2. HLF Review
It was noted
that correspondence had been sent to the HLF on 19 February estimating the
project completion times based on a comparative evaluation of both double and
single paged digital imaging. It was further noted that a response from the HLF
was currently awaited.
3. Review
of Workplan
3.1 Internet Resources
3.1.1 It was noted that work was continuing
satisfactorily and that the website had attracted over 250,000 hits over the
period Dec 2000 to Feb 2001.
The
sub-project work plans for both March and April were agreed and approved.
3.2 Testaments
3.2.1 It was noted that work was continuing
satisfactorily and that the index process was proceeding smoothly
The
sub-project work plans for both March and April were agreed and approved.
3.3 Catalogues
3.3.1 It was noted that Aberdeen University was
being worked on at the moment and work was about to begin in Stirling Council Archives.
3.3.2 It was noted that Andrew Jackson would be
working for SCAN in Glasgow City Archives from 12 March.
3.3.3 It was confirmed that Goran
from the National Archives of Sweden would be visiting SCAN between 26th
–28th March to discuss the development of the Arkis
software.
The
sub-project works plan for both March and April were agreed and approved.
4 Procurement
4.1 It was noted that the next 3 digital
cameras should arrive in April and that the next phase of digital camera
procurement would now be assessed.
4.2 It was confirmed that the second phase of
PC equipment ordered for the participating archives had now been delivered to
Glasgow School of Art and the RCSE. It was also noted that Stirling
Council had now procured their own PC under this programme.
5.1 It was noted that the recruitment
advertisement for curatorial staff was now with Personnel for their action.
6. Finance
6.1 A written report was tabled. [Extract
Attached]
6.2 It was noted that the budget variance
report would be sent to the HLF along with the next drawdown
submission on 16th March.
6.3 It was noted that the Year End Accounts
had been received from McCabe’s and that a copy had been lodged with Companies
House.
6.4 It was noted that the Royal Bank of
Scotland were to be notified of Ishbel’s forthcoming
retirement in respect of her position as cheque signatory and credit card
holder. It was agreed that Alan Borthwick take over
this function and that the bank should be notified accordingly.
7. Directors
7.1 It was noted that Mrs Webster would like
to continue in her position as a SCAN Director.
8. User
Group/Participating Archives Working Group Meeting
8.1 It was noted that the Users Group and
the PAWG had convened for a joint meeting on 10th March. A full
report will be compiled recording the day’s events and discussions. It was
noted that it was proposed to hold the next meeting of the Users Group in
October 2001.
9. Launch
Event & Dissemination Campaign
9.1 It was noted that Hazel and Joanna would
be representing SCAN at the St Andrews Day Society Tartan Day Festival in
Washington D.C during the period 3 – 8 April. It was hoped that this would
raise the profile of the SCAN project to a key target audience.
9.2 It was noted that the Marketing Advance programme was at its halfway stage and that it was proving
useful in developing SCAN’s commercial focus. It was
further noted that Rob, in his new capacity as Project Director, should now
become more involved in this aspect of the projects activities.
The next Project Board meeting will be held on Thursday 12 April at 16.00 in Thomas Thomson House, Bankhead Crossway North, Edinburgh.
SL
03/04/01
Scottish
Archive Network
Finance
Report as at 8 March 2001
1.
HLF Drawdowns
1.1 The February drawdown
(20) of £46,212.33 has been assessed as £46,212.33 and should have been
credited to SCAN’s account by 8 March.
1.3 The March drawdown (21) is currently under preparation and will be
submitted on 16 March
1.4 The advance drawdown
(19) for the procurement of a further 3 cameras and associated equipment for
£55,000 has been assessed as £55,000 and was credited to SCAN’s
account on 19 February. This has reduced our payment percentage to 73.23%.