Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To
be submitted by Grantee with each grant drawdown application, or at intervals
no greater than 3 months)
|
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the
Monitoring Documents referred to in your Grant Contract, you are required to
submit to NHMF a Progress Report with each grant drawdown application, or at
maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing
towards meeting the Approved Purposes. The headings and format
of the Report, addressing the principal monitoring criteria, are shown below.
These headings and format must be followed, but you may prepare your Report
using computer software incorporating spreadsheets as appropriate. All
sections (expanded in size as
necessary) are to be completed fully on each monthly report. (Use
supplementary sheets if necessary). PM forms should be returned in hardcopy and must be
completed fully. Failure to do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
26 |
|
Report Date: |
20 June 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
May 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general progress towards
achievement of the Approved Purposes identifying any problems or issues to
which NHMF’s attention should be drawn. Note any actions proposed in response
to problems or particular areas of risk.
The
project remains within budget and is scheduled to be completed on time. |
See
annex 1 for detailed progress. |
See
annex 2 for update on special conditions. |
The
minutes of the Project Board held in May are attached at Annex 3. |
The
Project Performance Information is now held on the accompanying spreadsheet. |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing partnership funds
Source of Funding |
Amount expected (A) |
Amount received to date (B) |
Balance to come A-B) |
Date balance expected |
NAS |
£425,967 |
£87,571 |
£338,396 |
Dec
2002 |
GSU |
£703,785 |
£195,712 |
£508,073 |
Dec
2002 |
|
|
|
|
|
|
£1,129,752 |
£283,283 |
£846,469 |
Dec
2002 |
Totals
|
|
|
|
|
Explain any changes to sources
of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material change to the Approved
Purposes which have been approved by
NHMF since the last Report and advise of any potential requests for such change
in the future.
Description
of Change Item |
Date
of request to NHMF |
Date
of NHMF response |
Effect
on achievement of Approved Purposes |
Effect
on Programme |
Effect
on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any
material change to the Approved Purposes
Report on any effect to delivery of the Approved
Purposes of any cost transfer between the principal cost elements stated in
your “Notification of Grant”. (Note: no such transfer is to be made between
capital and revenue elements, or between VAT and any other cost element,
without NHMF prior consent ).
Amount
of cost transfer (£’000) |
Cost
transfer from (cost element): |
Cost
transfer to (cost element): |
Effect
on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or comments received from
NHMF or its Project Monitors since your last report
Work
element for which Design/Document review has been carried out |
Date
reviewed |
NHMF/Project
Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the agreed
Timetable/Programme for key activities
Grant Expiry Date:
Key Activity or milestone |
Planned completion date |
Actual (or currently forecast) completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall
Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a) Cost Control
Enter expenditure to date against the key items
of Approved Cost (i.e. the costs on
which NHMF has agreed to pay the Payment Percentage) compared with that
detailed in the pre-commencement documentation. (VAT and Contingencies to be
separately identified).
Items of Approved Cost (Principal cost elements) |
Approved Costs to completion as agreed at award |
Out-turn Costs as currently
forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual costs to Date (C) |
Variance (C-B) |
Balance of costs (A- C) |
Staff
|
£2,170,889 |
£1,217,955 |
£1,217,955 |
£881,630 |
£-336,325 |
£336,325 |
Internet
Server |
£449,700 |
£412,225 |
£412,225 |
£139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£31,268 |
£31,268 |
£24,771 |
£- 6,497 |
£ 6,497 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£155,756 |
£-
42,994 |
£42,994 |
Other |
£543,500 |
£383,950 |
£383,950 |
£255,658 |
£-128,292 |
£128,292 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£112,209 |
£112,209 |
|
£-112,209 |
£112,209 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals
|
£6,196,307 |
£2,356,357 |
£2,356,357 |
£1,457,663 |
£-898,694 |
£898,694 |
Note any significant changes to the apportionment of
costs between the principal cost elements prior to their commitment. Note the
effect of any such changes and confirm that they will not affect the Approved
Purposes including expected quality.
Cost
transfer from : |
Cost
transfer to: |
Amount
(£) |
Effect
of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of expenditure of the total
Balance (A-C) calculated above and the funding sources to cover the expenditure
|
To
date |
Next Qtr |
2nd
Qtr |
3rd
Qtr |
4th
Qtr |
5th
Qtr |
Later |
Total
to Completion |
Expenditure
of Approved Cost |
Enter Total
of C above |
|
|
|
|
|
|
Enter Total of A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,457,663 |
|
|
|
|
|
|
£2,356,357 |
Other
source (1) |
|
|
|
|
|
|
|
|
Other
source (2) |
|
|
|
|
|
|
|
|
Other
source (3) |
|
|
|
|
|
|
|
|
Total
Funding (to equal Expenditure of Approved Cost) |
£1,457,663 |
|
|
|
|
|
|
£2,356,357 |
|
|
|
|
|
|
|
|
|
7. Procurement
Enter the current procurement status of any
significant goods, works, or services currently being procured for the project,
or awarded since the last Report.
Goods/Works/ Services : brief description |
Approx Value |
EU procurement Applies? Yes./No |
No of tenderers |
Date of tender return |
Date of award |
Selected
Contractor/supplier/ consultant |
Two
Atmel Digital Cams |
£22,100 |
No |
|
|
|
|
Bookcradles & Copystands |
£22,200 |
No |
|
|
|
|
Supporting
Computers |
£11,000 |
No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services not awarded to the
lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note any evidence provided at
the request of NHMF or the Project Monitor.
Property Description and
evidence provided |
Date evidence provided to
NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective From Date |
Expiry Date |
Employer
Liability Insurance |
21/10/00 |
20/10/01 |
Computer
Insurance |
21/10/00 |
21/10/01 |
Office
Insurance: Including Goods In Transit & Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried Staff (Note:
applicable only to staff whose salaries are included as Eligible Costs in the
Approved project.
Position |
Date Appointed |
Job Description sent to NHMF
(Yes/No) |
Media in which advert placed |
Employment Contract to NHMF (Yes/No) |
Curatorial |
May
01 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer Staff
The total number of Volunteer staff employed at present is …………9…… (Details are
provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal statutory consents
required to complete the project
Consent Required |
Granting Authority |
Actual or expected date of
consent |
Planning |
N/A |
|
Listed
Building |
|
|
Scheduled
Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement, press releases, or
other publicity issued since the last report:
Description |
Date Issued |
Approved by NHMF (Yes/No) |
Displayed
acknowledgement |
N/A |
|
Press
Releases issued |
|
|
Publicity
issued |
Shetland
Times – Visit to Shetland Archive. Inverness
Press & Journal – North by North West Exhibition. |
No No |
|
|
|
13. Photographic Records
Y
Confirm that you are making photographic records of
the project Y
14. Special Conditions
Indicate progress towards satisfying the Special
Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Grantee: Scottish Archive Network
Address:
Thomas Thomson House, 99 Bankhead Crossway North, Edinburgh, EH11 4DX
Signed
for Grantee: …Rob Mildren……………………………………………………..
Date: 20/06/01………………………….
One initial visit
occurred, again combined with the start of formal collection description work,
to Shetland Archives. Two of our staff
made the journey in the hope that we would make good inroads in the course of
effectively 3 weeks’ work, which we did.
At least one further week’s work will be required, however, in situ as
well as a fair bit of other work back home.
Continued progress on
collection description was reported at Aberdeen University Special
Collections/Archives, Stirling Council Archives, Glasgow City Archives and
Dundee City Archives. Some of the work
here was revision of entries which had already been formally logged, but there
was also produced some good quality entries for the record series of Glasgow
Corporation.
There was further
preparation for the of 4 casual student employees who will be migrating data
from our old Word-based documents to the Wee Arkis
access database, from which we can readily load the data into ARKIS II. They started work week commencing 14 May, and
are contracted to do 100 hours work each in an 8-week period.
Our IT staff produced
guidance as to the best means of capturing data within Access databases for the
48 archives we shall be covering. There
are some technically difficult, but interesting, problems, particularly how
best to give us all access to the index of name authorities which we have
created to avoid the creation of duplicate entries, but ensuring that there is
only one master version, when we are not necessarily based in a central office.
The interviews in the
NAS/SCAN curatorial staff recruitment will be held for about 20 candidates in
late June, and should produce some extra staff for this part of SCAN to bring
us back closer to the correct staffing level for the team.
Jenny Cutts attended a 2-day course, “Seminars for recently-qualified
archive professionals (part 1)”, arranged by the Society of Archivists.
Alan Borthwick gave a lecture on 15 May about SCAN’s work to a gathering in Shetland Museum, Lerwick, arranged by the local Archives and Museum staff.
Robin Urquart spent most of May preparing for the launch of the next exhibition in the series ‘North by Northwest’ on June 5th in Inverness. Bill Paton assisted with the creation and amendment of the relevant databases in preparation for this event. Joanna Baird assisted with new design for the exhibition.
Several additional pages were added to the Family History part of the website and this involved the creation of 4 additional submenus for this part of the site. 2 publications were added to the bookshop and ‘Northern Health Services Archive’ was added to the bookshop submenu.
A large format camera produced by ‘Betterlight’ was demonstrated to the team in May.
Joanna Baird held a meeting with Maureen Sprott and Cameron Taylor from the Scottish Tourist Board to discuss their ‘Genealogy Tourism Strategy’. Robin and Joanna demonstrated the SCAN website. As a result, it was agreed that SCAN should be represented on the Steering Group for the project due to the relevance of the SCAN project to prospective genealogy tourists.
One end-year staff review was carried out in May.
Joanna Baird drafted the SCAN Marketing Plan for submission to Scottish Enterprise on 15th May.
The newly-designed SCAN leaflets were received back from Evolution Design at the beginning of May. A note of this was posted on the online ‘News Roundup’ and consequently a few requests for leaflets were received from participating archives.
Little digitisation work was carried out in the course of May despite the arrival of the new camera towards the end of April. There were continued problems with the set-up of the new camera and much of Gary Clelland’s time was taken up assisting IKM with the installation, modification and testing of the new Atmel camera. 1 week of May constituted annual leave.
These problems were almost all resolved by the end of May and we hope that we will achieve a much higher rate of production in the course of June. Additionally, the environmental conditions in the small camera room have improved and this should allow work on imaging the glass plate negatives to begin in June.
Digital capture of the St Andrews Testaments, 1549-1823, (CC20/4/1-31) was completed. The post-1823 registers currently being captured are: Aberdeen wills (SC1/37/1-76), Orkney inventories and confirmations (SC11/38/1-8 & 41/1) and Alloa inventories and wills (SC64/42/1-15). Digital capture of the Edinburgh Testaments, 1514-1829, CC8/8/1-152 was started.
Ralf Ihrig, of IKM Micrographic GmbH, returned on 10 May to complete installation of the three Atmel cameras and book cradles. All three cameras are now operating, although there are still some software problems to be ironed out. The final two Atmel cameras, copy stands and book cradles were ordered during the month.
Two of our GSU volunteers, Bob and LouAnn Blakely, left us at the beginning of the month, having completed their tour of duty with SCAN. They were the first of the volunteers to join the project (in November 1999) and they will be much missed. A replacement couple is expected when the next two cameras are delivered at the beginning of August.
For detailed figure
breakdown please see Project Performance Monitor Spreadsheet.
At 30 April there were 1551 volumes of the total of 2033 volumes ready for digital capture =76% of the total.
These figures break down as follows:
At 31
May 162
volumes of the total of 2033 volumes had been captured = 8% of
the total
1.1 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
Fulfilled. The Scottish Archive Network
follows all Scottish Executive procurement rules. This has been verified by Mr J Grady, Chief Procurement Officer NAS. |
|
1.2 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
|
|
1.3 |
NHMF may reduce the Grant by such amount
as it thinks fit up to an amount which bears the same proportion to the
difference between the lowest tender price and the price of the tender
accepted by the Grantee as the Grant bore to the original cost of the
Approved Purposes if NHMF, in its absolute discretion, disagrees with the
reason given by the Grantee for not accepting the lowest tender. |
|
|
1.4 |
The Grantee agrees that it shall only
accept tenders that it believes in good faith will result in the Approved
Purposes being carried out to the standard prescribed by Special Conditions 2
and 9 of this Contract. |
|
|
2. |
The Grantee shall carry out the Works or
shall procure that the Works are carried out in a professional manner in
accordance with currently accepted best practice in the Information
Technology industry. The Grantee will
ensure that best practice or proven and widely adopted standards are applied
especially in the areas of project management, requirements analysis, system
or application, design, testing, documentation, installation and maintenance
and in the area of the preservation of digital materials. |
SCAN believes that it is carrying out the
Works and procuring the Works in a professional manner in accordance with
currently accepted best practice in the Information Technology industry |
|
3. |
Prior to commencing the Works the Grantee
shall secure to NHMF’s satisfaction all necessary
planning permissions building consents and statutory approvals. |
Fulfilled |
|
4. |
Prior to commencing the Works the Grantee
shall prepare a detailed cost plan for carrying out the Approved Purposes in
a format which has been agreed in advance by NHMF and shall submit the same
to NHMF for Approval. Thereafter the
Grantee shall spend the Grant and other funds provided for the Approved
Purposes only in accordance with the Approved cost plan (“the Cost
Plan”). The Grantee must obtain prior
written Approval for any changes in expenditure which are not in accordance
with the details of the Cost Plan and in particular for movement of funds
between the various elements of the Cost Plan. |
Detailed cost plan submitted and agreed with the HLF. No changes in expenditure have been made
without prior written approval. The budget has been updated following the PID
review and a report detailing the variations form the original budget
estimates has also been submitted for discussion with the HLF at our next
quarterly meeting |
|
5. |
Prior to commencing the Works the Grantee
shall prepare a draft monthly project report form and a draft monthly cash
flow report form and shall submit the same to NHME for Approval. Thereafter the Grantee shall submit signed
monthly reports in the Approved forms to NHMF until the Approved Purposes
have been fulfilled. |
Signed monthly project reports and
monthly cash flows are submitted to the HLF |
|
6. |
Prior to commencing the Works the Grantee
shall submit to NHMF for Approval a revised and updated programme
for the Project. For the avoidance of
doubt the Programme shall contain details of the
works to be carried out at the development stage. The Grantee shall only carry out the Works
in accordance with the Approved programme (“the Programme”) or any modification thereof Approved by NHMF. |
The Project Initiation Document (PID) was
submitted to the HLF as requested. The revised PID has also been submitted
and discussed with the HLF |
|
7. |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance of the project on terms which note the interest of and
are Approved by NHMF. |
Insurance has been obtained and full
details given to the HLF. Any renewal notices will automatically be dealt
with by SCAN |
|
8. |
Prior to issuing invitations to tender
the grantee shall prepare a report on the information and communication
technology to be installed at the Property pursuant to the Approved Purposes
and without prejudice to the generality of the foregoing the report shall
include:- |
An ICT report was prepared and the
tendering process undertaken as agreed. The ICT infrastructure is now in
place and has been paid in full. The next requirement will be to increase the
data storage capacity as the digital imaging workflow increases |
|
8.1 |
a feasibility report |
|
|
8.2 |
the specification for the Digital
Deliverables |
|
|
8.3 |
the design of the system which shall in
particular include details of all interactives |
|
|
8.4 |
the proposals for the purchase of network
infrastructure. |
|
|
|
On receipt of Approval for the report
(“the ICT Report”) the Grantee shall prepare invitations to tender and tender
evaluation criteria for such works and shall submit the same to NHMF for
Approval. Thereafter the Grantee shall
issue invitations to tender in accordance with the Approved tender
invitations and evaluation criteria. |
|
|
9. |
The Grantee shall carry out the
information and communication technology works in accordance with currently
accepted best practice in the Information Technology industry. The Grantee will ensure that best practice
or proven and widely adopted standards are applied especially in the areas of
project management, requirements analysis, system or application
specification, design testing, user and system documentation, installation
and maintenance and in the areas of the preservation of digital materials. |
SCAN believes it has fulfilled and is
fulfilling this condition |
|
10. |
The Grantee shall submit to NHMF for
Approval details of the standards that the Grantee intends to implement. |
SCAN has submitted to the HLF its draft
cataloguing standards |
|
11.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report for the safeguarding and enhancement of, and public
access to, the Property including without limitation its proposals for: |
|
|
|
a) such
testing as may be necessary to demonstrate that the Digital Deliverables and
capable of fulfilling the Approved Purposes |
Schedule of Requirements for the Supply
of Digital Cameras |
October 1999 |
Information and Communications Technology
Requirements |
March 1999 |
||
Information and Communications Technology
Tender Document |
February 2000 |
||
Test plan submitted for installation of
ICT equipment |
October 2000 |
||
Data Capture Specification for Indexes |
November 1999 |
||
Website design specification |
November 1999 |
||
|
b) such
evaluation as may be necessary to demonstrate that the Digital Deliverables
are capable of fulfilling the Approved Purposes |
Evaluation and
selection criteria for ICT equipment submitted in evaluation report “SCAN ICT
Requirements Tender Report” |
April 2000 |
Book Cradle
Evaluation |
July 2000 |
||
Web Site Tender
Evaluation |
January 2000 |
||
Camera
Evaluation for HLF |
May 2000 |
||
Resolution
Requirements for Testaments |
May 2000 |
||
Data Capture
Tender Evaluation |
December 2000 |
||
|
c) the
preservation and security of all data and other material collected or
created in the course of carrying out
the Approved Purposes by the keeping of back-up copies of the Digital Deliverables and
otherwise; |
Weekly backups
and daily incremental backups take place for all SCAN information (excluding
images) |
April 2001 |
Uncompressed TIFF images are written to
DLT and stored locally |
November 2000 (and ongoing) |
||
Compressed JPEG images are written to the
Internet Server where a backup is taken weekly |
November 2000 (and ongoing) |
||
|
d) the
form of licence(s) to be used by the Grantee
permitting third party exploitation of the Intellectual Property; |
This was included as part of the contract
negotiations with the Genealogical Society of Utah. The HLF have a copy of
this document July 1999 |
|
|
e) the
form(s) of assignment(s) consent(s) waiver(s) licence(s)
or permission(s) to be used by the Grantee for the securing of third party
rights in the Intellectual Property; |
|
|
|
f) error
correction, maintenance and updating of the Digital Deliverables |
Data flow diagram of the digitisation process available May 2001 Proposed data flow for the maintenance of
distributed data for the online catalogues available from May 2001 |
|
|
g) user
manuals or instructions and interfaces for the Digital Deliverables and its
use. |
All manuals
received for ICT equipment and standard operation of digital cameras Additional operator manual developed with
GSU for the use of the digital camera. ser manual produced in association
with the GSU for the installation, maintenance and delivery of digital
imaging in June 2000 Guidelines for capture of fonds level descriptions produced by SCAN in September
2000 |
|
|
Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. The Grantee must obtain prior written
Approval for any changes in the proposals which are not in accordance with
the Approved reports |
|
|
11.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
12.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report on the hardware technology to be used with the Digital
Deliverables (“the Hardware”) including without limitation its proposals for: (a) such
testing as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved Purposes; (b) such
evaluation as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved
Purposes; (c) error
correction, maintenance and updating of the Hardware; and (d) user
manuals and instructions for the Hardware and its use. Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. On receipt of Approval of the said monthly
reports the Grantee shall implement the reports in carrying out the Approved
Purposes. The Grantee must obtain
prior written Approval for any changes in the proposals which are not in
accordance with the Approved reports. |
A presentation
and report covering the entire ICT requirements for the project was given |
May 2000 |
Information and
Communications Technology Requirements |
March 1999 |
||
Information and
Communications Technology Tender Document |
February 2000 |
||
Test plan
submitted for installation of ICT equipment |
October 2000 |
||
Data Capture
Specification for Indexes |
November 1999 |
||
12.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
13. |
The Grantee shall enter into a deposit
agreement with a third party Approved by NHMF for all Digital Deliverables
and any associated or necessary software and applications and shall
thereafter deposit escrow copies of the said Digital Deliverables on a basis
to be agreed with NHMF. |
Escrow discussed
for deposit of digital images. SCAN has a contract clause with GSU to provide
mutual restore and backup of digital images |
Early
discussions held with NCC Follow Up
Required |
14. |
The Grantee shall ensure that all
applications and software necessary to access use or present the digital
deliverables are transferable to a third party. |
Escrow discussed
for deposit of any software packages |
Early
discussions held with NCC Follow Up
Required |
15 |
The Grantee agrees that it shall take all
reasonable steps to mitigate to NHMF’s satisfaction
the amount of VAT payable upon, or to recover the VAT payable upon, or to
recover the VAT attributable to, the cost of fulfilling the Approved
Purposes. The Grant shall be reduced
by an amount which bears the same proportion to the VAT not payable or
recovered as the Grant, prior to such decrease, bore to the original costs of
the Approved Purposes. |
SCAN has fulfilled this condition: VAT is fully recovered. |
|
16 |
At the end of Year 1 the Grantee is to produce a policy statement to support the extensibility of membership of Scottish Archive Network Limited with no financial implications. |
SCAN supports the extensibility of
membership of the Scottish Archive Network with no financial implications.
Currently there is an interest shown by the Roman Catholic Archdiocese of
Glasgow Archives for inclusion |
|
17 |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance for the Project on terms which note the interest of and
are Approved by NHMF. |
SCAN has fulfilled this condition |
|
18 |
The documents required to be submitted or
provided to NHMF under these special conditions, are required to be submitted
or provided by the Grantee only for NHMF’s own
purposes in connection with the Grant and NHMF’s
approval or acceptance of such documents cannot be taken as approval or
acceptance for any other purpose. |
This is accepted by SCAN |
|
|
19. [Clause
to go in here annexing contracts between a Scottish Archive Network Ltd and
others] |
|
|
20 |
The Grantee shall take account of any
representations which NHMF may make with regard to the carrying out of the
Approved Purposes in accordance with the Programme,
Design, specification, Cost Plan, ICT Report and the contracts referred to in
special conditions 1.1. In particular
the Grantee shall take account of any representations which NHMF may make
prior to the issue of a certificate of practical completion of the Works and
shall pass such representations on to the person authorised
to sign a certificate of practical completion. |
This is accepted by SCAN |
|
21 |
Without prejudice to the generality of
Clause 13.2 of this Contract NHMF may at any time appoint by notice in
writing to the Grantee a third party (“the Lead Monitor”) to monitor the
progress of the Approved Purposes and additional monitors to advise on
specialist matters arising from the implementations regarding the Approved
Purposes the Grantee shall take such reasonable steps as may be necessary to
comply with the recommendations. |
This is accepted by SCAN |
|
22 |
Prior to commencing the Works the Grantee
shall secure to the satisfaction of NHMF all the additional funding required
to complete the Approved Purposes. |
The additional funding required by the
HLF was secured. Budget projections supplied to HLF in March 2001 indicate
that the project will complete within budget and with the agreed percentage
of partnership funding |
Notes of Project Board Meeting
18 May 2001 16.00
Attendees:
Rob Mildren (Chair/Secretary), George Mackenzie, Peter
Anderson
Apologies:
Stuart Low (Minute Secretary)
1 |
Minutes of Last Meeting and Matters Arising |
Action |
1.1 |
The minutes of the last meeting were approved and there were no matters arising. |
|
2 |
HLF Correspondence |
|
2.1 |
No correspondence had been received from the Heritage Lottery Fund. Due to a misunderstanding over dates, the scheduled Quarterly Monitoring Meeting had been postponed until 4 June 2001 |
|
2.2 |
The response to the previous communication from HLF on digital imaging and new budget headings had been prepared but was awaiting the finalising of the agreement between SCAN and Riksarkivet over the use of Arkis for the finding aids project |
RM |
2.3 |
The post of Project Manager was discussed. It was agreed to raise this with the HLF monitors at the next meeting for their views on progressing the recruitment of a permanent project manager and the issue of costs involved in advertising the post. |
RM |
3 |
Review of Workplans |
|
|
Stuart will be working on the composite spreadsheet with the aim of completing it for the next drawdown. |
SL/RM |
3.1 |
Internet Resources |
|
3.1.1 |
RM reported that the team now had their Atmel camera installed and working along with the book cradle. The camera was operating satisfactorily but there was a question mark over the number of defective pixels. RM will devise a means of highlighting the number and location of defective pixels. It may then prove possible to derive more accurate settings from surrounding pixel values. |
RM |
3.1.2 |
RM advised the
project board that Internet Resources team had identified a number of “stock”
jobs that would be carried out. These were aimed to produce material that
could be incorporated into knowledge base and other web resources for the
SCAN website. |
RM/GM |
3.1.3 |
RM reported that a workshop teaching palaeographic skills had been held at TTH in conjunction with the Scottish Records Association. It had been a very successful day with more than 20 participants. GM asked if this could be made available for NAS staff. SCAN will highlight the avaialablitity of training materials to NAS staff. |
JB/HA |
3.1.4 |
The sub-project work plans for both May and June were agreed and approved. |
|
3.2 |
Testaments |
|
3.2.1 |
Hazel Anderson and RM had met with staff from the Search room. The meeting was very positive and it was agreed to make a version of the current composite index to the Sherrif Court resords available for staff use and evaluation by the end of June. In addition digital images of completed volumes would be released as early as possible to relieve pressure on search room staff to provide access for the public. |
HA/RM |
3.2.2 |
The index linking operation was proceeding satisfactorily. Testaments staff will evaluate the need and usefulness of the requirement to examine each image for index entries, particularly for the post 1800 material. Once this is well underway an accurate assessment of any additional resources that may be required for this step can be made. |
HA |
3.2.3 |
The sub-project work plans for both May and June were agreed and approved. |
|
3.3 |
Catalogues |
|
3.3.1 |
RM reported that the casual staff had started work on transferring existing entries to the database structure |
|
3.3.2 |
The sub-project work plans for both May and June were agreed and approved. |
|
4 |
Procurement |
|
4.1 |
Digital Cameras |
|
4.1.1 |
The 3 Atmels had now been installed and are working successfully. We will now request advance from HLF to place an order for the final 2 camera needed for the Testaments project |
SL |
4.2 |
Cataloguing Software |
|
|
RM will meet with Goran Krisitanson during the forthcoming European ICA meeting to finalise the arrangements for SCAN to use Arkis database. NAS has drawn up a document detailing its requirements for its own cataloguing system. The need to interface with SCAN finding aid entries has been included. |
|
5. |
Staffing |
|
|
GM reported that the joint board for NAS/SCAN curatorial recruitment will take place June 18-21 20 candidates will be interviewed |
|
6. |
Finance |
|
|
SL will cover any relevant issues in the next project board meeting |
|
7. |
User
Group |
|
|
No report was received |
|
8. |
Participating
Archives Working Group |
|
|
No report was received |
|
9. |
Marketing
Events & Publicity Dissemination |
|
|
RM reported that the course programme had now been completed but there will be continuing contact with Cathy Black, SCAN’s marketing advisor, particularly with a view to furthering the business plan |
|
10 |
AOCB |
|
|
There were no additional items |
|
11 |
Date
of Next Meeting |
|
|
The next Project Board meeting will be held on Wednesday 27th June at 15.30 in Thomas Thomson House, Bankhead Crossway North, Edinburgh. |
|
RM