Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To
be submitted by Grantee with each grant drawdown application, or at intervals
no greater than 3 months)
|
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the
Monitoring Documents referred to in your Grant Contract, you are required to
submit to NHMF a Progress Report with each grant drawdown application, or at
maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing
towards meeting the Approved Purposes. The headings and format
of the Report, addressing the principal monitoring criteria, are shown below.
These headings and format must be followed, but you may prepare your Report
using computer software incorporating spreadsheets as appropriate. All
sections (expanded in size as
necessary) are to be completed fully on each monthly report. (Use
supplementary sheets if necessary). PM forms should be returned in hardcopy and must be
completed fully. Failure to do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
27 |
|
Report Date: |
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
June 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general progress towards
achievement of the Approved Purposes identifying any problems or issues to
which NHMF’s attention should be drawn. Note any actions proposed in response
to problems or particular areas of risk.
The
project remains within budget and is scheduled to be completed on time. |
See
annex 1 for detailed progress. |
See
annex 2 for update on special conditions. |
The
minutes of the Project Board held in June are attached at Annex 3. |
The
Project Performance Information is now held on the accompanying spreadsheet. |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing partnership funds
Source of Funding |
Amount expected (A) |
Amount received to date (B) |
Balance to come A-B) |
Date balance expected |
NAS |
£425,967 |
£ 90,904 |
£335,063 |
Dec
2002 |
GSU |
£703,785 |
£211,312 |
£492,473 |
Dec
2002 |
|
|
|
|
|
|
£1,129,752 |
£302,216 |
£827,536 |
Dec
2002 |
Totals
|
|
|
|
|
Explain any changes to sources
of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material change to the Approved
Purposes which have been approved by
NHMF since the last Report and advise of any potential requests for such change
in the future.
Description
of Change Item |
Date
of request to NHMF |
Date
of NHMF response |
Effect
on achievement of Approved Purposes |
Effect
on Programme |
Effect
on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any
material change to the Approved Purposes
Report on any effect to delivery of the Approved
Purposes of any cost transfer between the principal cost elements stated in
your “Notification of Grant”. (Note: no such transfer is to be made between
capital and revenue elements, or between VAT and any other cost element,
without NHMF prior consent ).
Amount
of cost transfer (£’000) |
Cost
transfer from (cost element): |
Cost
transfer to (cost element): |
Effect
on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or comments received from
NHMF or its Project Monitors since your last report
Work
element for which Design/Document review has been carried out |
Date
reviewed |
NHMF/Project
Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the agreed
Timetable/Programme for key activities
Grant Expiry Date:
Key Activity or milestone |
Planned completion date |
Actual (or currently forecast) completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall
Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a) Cost Control
Enter expenditure to date against the key items
of Approved Cost (i.e. the costs on
which NHMF has agreed to pay the Payment Percentage) compared with that
detailed in the pre-commencement documentation. (VAT and Contingencies to be
separately identified).
Items of Approved Cost (Principal cost elements) |
Approved Costs to completion as agreed at award |
Out-turn Costs as currently
forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual costs to Date (C) |
Variance (C-B) |
Balance of costs (A- C) |
Staff
|
£2,170,889 |
£1,401,212 |
£1,401,212 |
£928,088 |
£-473,124 |
£473,124 |
Internet
Server |
£449,700 |
£ 412,225 |
£ 412,225 |
£139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£ 34,518 |
£ 34,518 |
£24,832 |
£ -
9,686 |
£ 9,686 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£159,848 |
£-
38,902 |
£38,902 |
Other |
£543,500 |
£421,750 |
£421,750 |
£297,320 |
£
-124,430 |
£124,430 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£112,209 |
£112,209 |
|
£-112,209 |
£112,209 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals
|
£6,196,307 |
£2,580,664 |
£2,580,664 |
£1,549,936 |
£-1,030,728 |
£1,030,728 |
Note any significant changes to the apportionment of
costs between the principal cost elements prior to their commitment. Note the
effect of any such changes and confirm that they will not affect the Approved
Purposes including expected quality.
Cost
transfer from : |
Cost
transfer to: |
Amount
(£) |
Effect
of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of expenditure of the total
Balance (A-C) calculated above and the funding sources to cover the expenditure
|
To
date |
Next Qtr |
2nd
Qtr |
3rd
Qtr |
4th
Qtr |
5th
Qtr |
Later |
Total
to Completion |
Expenditure
of Approved Cost |
Enter Total
of C above |
|
|
|
|
|
|
Enter Total of A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,549,936 |
|
|
|
|
|
|
£2,580,664 |
Other
source (1) |
|
|
|
|
|
|
|
|
Other
source (2) |
|
|
|
|
|
|
|
|
Other
source (3) |
|
|
|
|
|
|
|
|
Total
Funding (to equal Expenditure of Approved Cost) |
£1,549,936 |
|
|
|
|
|
|
£2,580,664 |
7. Procurement
Enter the current procurement status of any
significant goods, works, or services currently being procured for the project,
or awarded since the last Report.
Goods/Works/ Services : brief description |
Approx Value |
EU procurement Applies? Yes./No |
No of tenderers |
Date of tender return |
Date of award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services not awarded to the
lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note any evidence provided at
the request of NHMF or the Project Monitor.
Property Description and
evidence provided |
Date evidence provided to
NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective From Date |
Expiry Date |
Employer
Liability Insurance |
21/10/00 |
20/10/01 |
Computer
Insurance |
21/10/00 |
21/10/01 |
Office
Insurance: Including Goods In Transit & Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of Staff (Revenue Elements only, if any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried Staff (Note:
applicable only to staff whose salaries are included as Eligible Costs in the
Approved project.
Position |
Date Appointed |
Job Description sent to NHMF
(Yes/No) |
Media in which advert placed |
Employment Contract to NHMF (Yes/No) |
Curatorial
(Casual) |
04/06/01 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer Staff
The total number of Volunteer staff employed at present is …………9…… (Details are
provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal statutory consents
required to complete the project
Consent Required |
Granting Authority |
Actual or expected date of
consent |
Planning |
N/A |
|
Listed
Building |
|
|
Scheduled
Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement, press releases, or
other publicity issued since the last report:
Description |
Date Issued |
Approved by NHMF (Yes/No) |
Displayed
acknowledgement |
N/A |
|
Press
Releases issued |
|
|
Publicity
issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making photographic records of
the project Y
14. Special Conditions
Indicate progress towards satisfying the Special
Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Grantee: Scottish Archive Network
Address:
Thomas Thomson House, 99 Bankhead Crossway North, Edinburgh, EH11 4DX
Signed
for Grantee: …Rob Mildren……………………………………………………..
Date: 25/07/01………………………….
Nicola Mills revised
some Orkney Archives collection descriptions in the course of a week’s visit
there; and also continued with her work on Aberdeen University Library Special
Collections Dept.
Andrew Jackson
continued work in Glasgow City Archives, and provided some entries for local
authority records, as well as a re-draft of our standard entries for local
authority records, which at the end of the month was almost complete.
Alison Diamond, who is
able to work on an occasional basis for us, continued work on Stirling Council
Archives collection descriptions.
Our casual students employed
to convert our older data into our current WeeArkis access databases provided a
good quantity of data during the month, most of which was checked over by
The NAS/SCAN
recruitment board met towards the end of the month, and it is believed that
some suitable candidates have been identified, although it may be late in July
before we can establish who might join SCAN.
Niall Taylor and
Joanna Baird met with
Fiona Edgar from Edinburgh Chamber of Commerce on 1st June regarding
a possible student placement within SCAN during July and August. Fiona agreed
that SCAN was suitable to supply such a placement and Joanna then met with a
candidate for the placement – Victoria Miller – who was subsequently offered
the temporary post. Victoria is a 3rd year business studies student
at Edinburgh University and she will working on a marketing project with
specific relevance to Scottish Wills. She will begin her placement on July 2nd
and a workplan was drawn up for her in June.
Joanna Baird attended
a meeting with Rob Mildren, Stuart Low and Cathy Black – the SCAN business
manager on Friday 29th June.
John Malden began
working for the Internet Resources team on Monday 4th June on a
casual contract. John will be working on Knowledge Base entries and Research
Tools for the website for 6 months.
7 days from June constituted annual leave for Joanna Baird.
The official launch of
‘North by Northwest’ took place in Inverness on 5 June. Robin Urquhart and
Digitisation
The new digital camera functioned well during June
and initial predictions re quantity of images captured were exceeded.
No glass plate negatives were imaged during June due to the high levels of relative humidity prevailing in the camera room, although several test images were made using non archival negatives to test colour balance etc.
Digital capture of the Orkney inventories and confirmations (SC11/38/1-8 & 41/1) and Alloa inventories and wills (SC64/42/1-15) was completed. The post-1823 registers currently being captured are: Aberdeen wills (SC1/37/1-76) and Ayr Inventories (SC6/44/1-38). Digital capture of the Edinburgh Testaments, 1514-1829 (CC8/8/1-152) continues.
Jane attended a training session on the new Scottish Executive performance management system at GRH, and all members of the Testaments team (except Peter Dickson, who was on sick leave) attended one of the two NAS staff Away Days on 19th and 21st June.
Two archive students, one from France and one from Turkey, visited the Testaments project during the month, and Hazel answered an enquiry about digital capture from the Notarial Archives of Malta. Digital images of an Aberdeen warrant (CC1/6/7439-7443) were produced for a reader by special request.
Hazel gave two presentations during the month. The first, on SCAN and the testaments, was to the AGM of the Scottish Law Agents Society in Aberdeen. The second, on the management of a digitising project, was given at the annual conference of the Higher Education Digitising Service (HEDS) in London.
1.1 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
Fulfilled. The Scottish Archive Network
follows all Scottish Executive procurement rules. This has been verified by
Mr J Grady, Chief Procurement Officer NAS. |
|
1.2 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
|
|
1.3 |
NHMF may reduce the Grant by such amount
as it thinks fit up to an amount which bears the same proportion to the
difference between the lowest tender price and the price of the tender
accepted by the Grantee as the Grant bore to the original cost of the
Approved Purposes if NHMF, in its absolute discretion, disagrees with the
reason given by the Grantee for not accepting the lowest tender. |
|
|
1.4 |
The Grantee agrees that it shall only
accept tenders that it believes in good faith will result in the Approved
Purposes being carried out to the standard prescribed by Special Conditions 2
and 9 of this Contract. |
|
|
2. |
The Grantee shall carry out the Works or
shall procure that the Works are carried out in a professional manner in
accordance with currently accepted best practice in the Information
Technology industry. The Grantee will
ensure that best practice or proven and widely adopted standards are applied
especially in the areas of project management, requirements analysis, system
or application, design, testing, documentation, installation and maintenance
and in the area of the preservation of digital materials. |
SCAN believes that it is carrying out the
Works and procuring the Works in a professional manner in accordance with
currently accepted best practice in the Information Technology industry |
|
3. |
Prior to commencing the Works the Grantee
shall secure to NHMF’s satisfaction all necessary planning permissions
building consents and statutory approvals. |
Fulfilled |
|
4. |
Prior to commencing the Works the Grantee
shall prepare a detailed cost plan for carrying out the Approved Purposes in
a format which has been agreed in advance by NHMF and shall submit the same
to NHMF for Approval. Thereafter the
Grantee shall spend the Grant and other funds provided for the Approved
Purposes only in accordance with the Approved cost plan (“the Cost
Plan”). The Grantee must obtain prior
written Approval for any changes in expenditure which are not in accordance
with the details of the Cost Plan and in particular for movement of funds
between the various elements of the Cost Plan. |
Detailed cost plan submitted and agreed with the HLF. No changes in expenditure have been made
without prior written approval. The budget has been updated following the PID
review and a report detailing the variations form the original budget
estimates has also been submitted for discussion with the HLF at our next
quarterly meeting |
|
5. |
Prior to commencing the Works the Grantee
shall prepare a draft monthly project report form and a draft monthly cash
flow report form and shall submit the same to NHME for Approval. Thereafter the Grantee shall submit signed
monthly reports in the Approved forms to NHMF until the Approved Purposes
have been fulfilled. |
Signed monthly project reports and
monthly cash flows are submitted to the HLF |
|
6. |
Prior to commencing the Works the Grantee
shall submit to NHMF for Approval a revised and updated programme for the
Project. For the avoidance of doubt
the Programme shall contain details of the works to be carried out at the
development stage. The Grantee shall
only carry out the Works in accordance with the Approved programme (“the
Programme”) or any modification thereof Approved by NHMF. |
The Project Initiation Document (PID) was
submitted to the HLF as requested. The revised PID has also been submitted
and discussed with the HLF |
|
7. |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance of the project on terms which note the interest of and
are Approved by NHMF. |
Insurance has been obtained and full
details given to the HLF. Any renewal notices will automatically be dealt
with by SCAN |
|
8. |
Prior to issuing invitations to tender
the grantee shall prepare a report on the information and communication
technology to be installed at the Property pursuant to the Approved Purposes
and without prejudice to the generality of the foregoing the report shall
include:- |
An ICT report was prepared and the tendering
process undertaken as agreed. The ICT infrastructure is now in place and has
been paid in full. The next requirement will be to increase the data storage
capacity as the digital imaging workflow increases |
|
8.1 |
a feasibility report |
|
|
8.2 |
the specification for the Digital
Deliverables |
|
|
8.3 |
the design of the system which shall in
particular include details of all interactives |
|
|
8.4 |
the proposals for the purchase of network
infrastructure. |
|
|
|
On receipt of Approval for the report
(“the ICT Report”) the Grantee shall prepare invitations to tender and tender
evaluation criteria for such works and shall submit the same to NHMF for
Approval. Thereafter the Grantee shall
issue invitations to tender in accordance with the Approved tender
invitations and evaluation criteria. |
|
|
9. |
The Grantee shall carry out the
information and communication technology works in accordance with currently
accepted best practice in the Information Technology industry. The Grantee will ensure that best practice
or proven and widely adopted standards are applied especially in the areas of
project management, requirements analysis, system or application
specification, design testing, user and system documentation, installation
and maintenance and in the areas of the preservation of digital materials. |
SCAN believes it has fulfilled and is
fulfilling this condition |
|
10. |
The Grantee shall submit to NHMF for
Approval details of the standards that the Grantee intends to implement. |
SCAN has submitted to the HLF its draft
cataloguing standards |
|
11.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report for the safeguarding and enhancement of, and public
access to, the Property including without limitation its proposals for: |
|
|
|
a) such
testing as may be necessary to demonstrate that the Digital Deliverables and
capable of fulfilling the Approved Purposes |
Schedule of Requirements for the Supply
of Digital Cameras |
October 1999 |
Information and Communications Technology
Requirements |
March 1999 |
||
Information and Communications Technology
Tender Document |
February 2000 |
||
Test plan submitted for installation of
ICT equipment |
October 2000 |
||
Data Capture Specification for Indexes |
November 1999 |
||
Website design specification |
November 1999 |
||
|
b) such
evaluation as may be necessary to demonstrate that the Digital Deliverables
are capable of fulfilling the Approved Purposes |
Evaluation and
selection criteria for ICT equipment submitted in evaluation report “SCAN ICT
Requirements Tender Report” |
April 2000 |
Book Cradle
Evaluation |
July 2000 |
||
Web Site Tender
Evaluation |
January 2000 |
||
Camera
Evaluation for HLF |
May 2000 |
||
Resolution
Requirements for Testaments |
May 2000 |
||
Data Capture
Tender Evaluation |
December 2000 |
||
|
c) the
preservation and security of all data and other material collected or
created in the course of carrying out
the Approved Purposes by the keeping of back-up copies of the Digital Deliverables and
otherwise; |
Weekly backups
and daily incremental backups take place for all SCAN information (excluding
images) |
April 2001 |
Uncompressed TIFF images are written to
DLT and stored locally |
November 2000 (and ongoing) |
||
Compressed JPEG images are written to the
Internet Server where a backup is taken weekly |
November 2000 (and ongoing) |
||
|
d) the
form of licence(s) to be used by the Grantee permitting third party
exploitation of the Intellectual Property; |
This was included as part of the contract
negotiations with the Genealogical Society of Utah. The HLF have a copy of
this document July 1999 |
|
|
e) the
form(s) of assignment(s) consent(s) waiver(s) licence(s) or permission(s) to
be used by the Grantee for the securing of third party rights in the
Intellectual Property; |
|
|
|
f) error
correction, maintenance and updating of the Digital Deliverables |
Data flow diagram of the digitisation
process available May 2001 Proposed data flow for the maintenance of
distributed data for the online catalogues available from May 2001 |
|
|
g) user
manuals or instructions and interfaces for the Digital Deliverables and its
use. |
All manuals
received for ICT equipment and standard operation of digital cameras Additional operator manual developed with
GSU for the use of the digital camera. ser manual produced in association with
the GSU for the installation, maintenance and delivery of digital imaging in
June 2000 Guidelines for capture of fonds level
descriptions produced by SCAN in September 2000 |
|
|
Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. The Grantee must obtain prior written
Approval for any changes in the proposals which are not in accordance with
the Approved reports |
|
|
11.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
12.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report on the hardware technology to be used with the Digital
Deliverables (“the Hardware”) including without limitation its proposals for: (a) such
testing as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved Purposes; (b) such
evaluation as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved
Purposes; (c) error
correction, maintenance and updating of the Hardware; and (d) user
manuals and instructions for the Hardware and its use. Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. On receipt of Approval of the said monthly
reports the Grantee shall implement the reports in carrying out the Approved
Purposes. The Grantee must obtain
prior written Approval for any changes in the proposals which are not in
accordance with the Approved reports. |
A presentation
and report covering the entire ICT requirements for the project was given |
May 2000 |
Information and
Communications Technology Requirements |
March 1999 |
||
Information and
Communications Technology Tender Document |
February 2000 |
||
Test plan
submitted for installation of ICT equipment |
October 2000 |
||
Data Capture
Specification for Indexes |
November 1999 |
||
12.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
13. |
The Grantee shall enter into a deposit
agreement with a third party Approved by NHMF for all Digital Deliverables
and any associated or necessary software and applications and shall
thereafter deposit escrow copies of the said Digital Deliverables on a basis
to be agreed with NHMF. |
Escrow discussed
for deposit of digital images. SCAN has a contract clause with GSU to provide
mutual restore and backup of digital images |
Early
discussions held with NCC Follow Up
Required |
14. |
The Grantee shall ensure that all
applications and software necessary to access use or present the digital
deliverables are transferable to a third party. |
Escrow discussed
for deposit of any software packages |
Early
discussions held with NCC Follow Up
Required |
15 |
The Grantee agrees that it shall take all
reasonable steps to mitigate to NHMF’s satisfaction the amount of VAT payable
upon, or to recover the VAT payable upon, or to recover the VAT attributable
to, the cost of fulfilling the Approved Purposes. The Grant shall be reduced by an amount
which bears the same proportion to the VAT not payable or recovered as the
Grant, prior to such decrease, bore to the original costs of the Approved
Purposes. |
SCAN has fulfilled this condition: VAT is fully recovered. |
|
16 |
At the end of Year 1 the Grantee is to produce a policy statement to support the extensibility of membership of Scottish Archive Network Limited with no financial implications. |
SCAN supports the extensibility of
membership of the Scottish Archive Network with no financial implications.
Currently there is an interest shown by the Roman Catholic Archdiocese of
Glasgow Archives for inclusion |
|
17 |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance for the Project on terms which note the interest of and
are Approved by NHMF. |
SCAN has fulfilled this condition |
|
18 |
The documents required to be submitted or
provided to NHMF under these special conditions, are required to be submitted
or provided by the Grantee only for NHMF’s own purposes in connection with
the Grant and NHMF’s approval or acceptance of such documents cannot be taken
as approval or acceptance for any other purpose. |
This is accepted by SCAN |
|
|
19. [Clause
to go in here annexing contracts between a Scottish Archive Network Ltd and
others] |
|
|
20 |
The Grantee shall take account of any
representations which NHMF may make with regard to the carrying out of the
Approved Purposes in accordance with the Programme, Design, specification,
Cost Plan, ICT Report and the contracts referred to in special conditions 1.1. In particular the Grantee shall take
account of any representations which NHMF may make prior to the issue of a
certificate of practical completion of the Works and shall pass such
representations on to the person authorised to sign a certificate of practical
completion. |
This is accepted by SCAN |
|
21 |
Without prejudice to the generality of
Clause 13.2 of this Contract NHMF may at any time appoint by notice in
writing to the Grantee a third party (“the Lead Monitor”) to monitor the
progress of the Approved Purposes and additional monitors to advise on
specialist matters arising from the implementations regarding the Approved
Purposes the Grantee shall take such reasonable steps as may be necessary to
comply with the recommendations. |
This is accepted by SCAN |
|
22 |
Prior to commencing the Works the Grantee
shall secure to the satisfaction of NHMF all the additional funding required
to complete the Approved Purposes. |
The additional funding required by the
HLF was secured. Budget projections supplied to HLF in March 2001 indicate
that the project will complete within budget and with the agreed percentage
of partnership funding |
Notes of Project Board Meeting
27 June 2001 16.00
Attendees:
Rob Mildren (Chair/Secretary), George Mackenzie, Peter Anderson
Apologies:
Stuart Low (Minute Secretary)
1 |
Minutes of Last Meeting and Matters Arising |
Action |
1.1 |
The minutes of the last meeting were approved. Progress on the following action points was reported 2.2 RM Has written to Riksarkivet on future use of Arkis and awaiting response 2.3 RM Issue of Project Manager post raised with HLF at the recent monitoring meeting. It was agreed to advertise the post externally and the project could fund the advertising costs 3.1.1 SL Workplan spreadsheet not yet complete. It will be done for the next project board 3.1.2 RM had circulated details of stock jobs currently under consideration 3.1.4 Release of the index to the search room staff was now imminent 4.1.1 SL had placed request for advance drawdown form HLF for the next cameras |
|
2 |
HLF Correspondence |
|
2.1 |
The monitoring meeting had been held on 4 June and the feeling of the project board was that it had been very positive and productive. |
|
2.2 |
During the meeting it was agreed that SCAN would respond immediately on the outstanding issues regarding digitisation policy and budget changes |
RM |
2.3 |
It was noted that HLF should have a representative on the selection panel for the Project Manager post |
|
3 |
Review of Workplans |
|
|
|
|
3.1 |
Internet Resources sub-Project |
|
3.1.1 |
Work on the Marketing report for the Scottish Enterprise course had been completed |
|
3.1.2 |
It was reported that Joanna Baird was now on the steering group for the Scottish Tourist Board on their “Genealogy Tourism Strategy” |
|
3.1.3 |
New leaflets for the project had been produced and samples were shown to the project board |
|
3.1.4 |
The sub-project work plans for both June and July were agreed and approved. |
|
3.2 |
Testaments |
|
3.2.1 |
Work on index/image linking was now well underway. It was reported that the standard of indexes for those done to date was high. It was proposed that the GSU could be used to cover the bulk of the Sheriff Court images given the high quality of the index entries. This would allow curatorial staff on the team to concentrate on older, more difficult paleographically, material. PDA offered to assist with the Orkney and Shetland material given his special local knowledge. |
|
3.2.2 |
The conservation staffing position was discussed. There were a number of issues to be resolved. RM will report on the remaining staff budget for conservation originally planned for the project HA will discuss with Linda Ramsay regarding the management of throughput to cover the shortages for sick leave GM will discuss with PSB the remaining issues for taking back into NAS the seconded SCAN staff in conservation |
RM HA GM |
3.2.3 |
The sub-project work plans for both June and July were agreed and approved. |
|
3.3 |
Online Cataloguing sub-Project |
|
3.3.1 |
RM reported that the casual students had begun work. NT had trained them and they would be working from home with AB checking the work |
|
3.3.2 |
AB and NT had devised methods to manage the update of the central SCAN database of catalogue entries to maintain consistency and integrity of data entered. |
|
3.3.2 |
The sub-project work plans for both June and July were agreed and approved. |
|
4 |
Procurement |
|
4.1 |
Digital Cameras |
|
4.1.1 |
As the Atmel cameras had now been successfully installed and integrated into the workflow, the final 2 cameras would now be ordered. |
|
4.2 |
Cataloguing Software |
|
|
|
|
4.2.1 |
RM had met with Goran Kristiansson of the Riksarkivet and discussed the SCAN requirements for ARKIS. It was agreed that these could be met with a copy of the database structure based on the data model produced by RA along with the internet asp pages to allow public access and retrieval. RM has written to RA to confirm these details meet the SCAN requirements. |
RM |
5. |
Staffing |
|
|
GM reported that the NAS Curatorial board had met and selected sufficient suitable candidates for all the vacancies currently in NAS and SCAN. AB will select the staff for SCAN requirements. |
AB |
6. |
Finance |
|
|
SL produced a written report in his absence |
|
7. |
User
Group |
|
|
|
|
8. |
Participating
Archives Working Group |
|
|
|
|
8.1 |
The next meeting will be held on 28 June. The agenda will be decided by PAWG themselves. |
|
9. |
Marketing
Events & Publicity Dissemination |
|
|
Not discussed |
|
10 |
AOCB |
|
|
There were no additional items |
|
11 |
Date
of Next Meeting |
|
|
The next Project Board meeting will be held on Tuesday 24th July at 14.30 in Thomas Thomson House, Bankhead Crossway North, Edinburgh. |
|
RM
23/06/01