|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To
be submitted by Grantee with each grant drawdown application, or at intervals
no greater than 3 months)
|
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the
Monitoring Documents referred to in your Grant Contract, you are required to
submit to NHMF a Progress Report with each grant drawdown application, or at
maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing
towards meeting the Approved Purposes. The headings and format
of the Report, addressing the principal monitoring criteria, are shown below.
These headings and format must be followed, but you may prepare your Report
using computer software incorporating spreadsheets as appropriate. All
sections (expanded in size as
necessary) are to be completed fully on each monthly report. (Use
supplementary sheets if necessary). PM forms should be returned in hardcopy and must be
completed fully. Failure to do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
29 |
|
Report Date: |
27 Sept 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
August 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general progress towards
achievement of the Approved Purposes identifying any problems or issues to
which NHMF’s attention should be drawn. Note any actions proposed in response
to problems or particular areas of risk.
The
project remains within budget and is scheduled to be completed on time. |
See
annex 1 for detailed progress. |
See
annex 2 for update on special conditions. |
The
minutes of the Project Board held in August are attached at Annex 3. |
The
Project Performance Information is now held on the accompanying spreadsheet. |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing partnership funds
Source of Funding |
Amount expected (A) |
Amount received to date (B) |
Balance to come A-B) |
Date balance expected |
NAS |
£425,967 |
£ 99,042 |
£326,925 |
Dec
2002 |
GSU |
£703,785 |
£248,554 |
£455,231 |
Dec
2002 |
|
|
|
|
|
|
£1,129,752 |
£347,596 |
£782,156 |
Dec
2002 |
Totals
|
|
|
|
|
Explain any changes to sources
of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material change to the Approved
Purposes which have been approved by
NHMF since the last Report and advise of any potential requests for such change
in the future.
Description
of Change Item |
Date
of request to NHMF |
Date
of NHMF response |
Effect
on achievement of Approved Purposes |
Effect
on Programme |
Effect
on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any
material change to the Approved Purposes
Report on any effect to delivery of the Approved
Purposes of any cost transfer between the principal cost elements stated in
your “Notification of Grant”. (Note: no such transfer is to be made between
capital and revenue elements, or between VAT and any other cost element,
without NHMF prior consent ).
Amount
of cost transfer (£’000) |
Cost
transfer from (cost element): |
Cost
transfer to (cost element): |
Effect
on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or comments received from
NHMF or its Project Monitors since your last report
Work
element for which Design/Document review has been carried out |
Date
reviewed |
NHMF/Project
Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the agreed
Timetable/Programme for key activities
Grant Expiry Date:
Key Activity or milestone |
Planned completion date |
Actual (or currently forecast) completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall
Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a) Cost Control
Enter expenditure to date against the key items
of Approved Cost (i.e. the costs on
which NHMF has agreed to pay the Payment Percentage) compared with that
detailed in the pre-commencement documentation. (VAT and Contingencies to be
separately identified).
Items of Approved Cost (Principal cost elements) |
Approved Costs to completion as agreed at award |
Out-turn Costs as currently
forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual costs to Date (C) |
Variance (C-B) |
Balance of costs (A- C) |
Staff
|
£2,170,889 |
£1,401,212 |
£1,401,212 |
£1,035,357 |
£-365,855 |
£365,855 |
Internet
Server |
£449,700 |
£ 412,225 |
£ 412,225 |
£ 139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£ 34,518 |
£ 34,518 |
£ 31,238 |
£ - 3,280 |
£ 3,280 |
Digitisation |
£349,191 |
£198,750 |
£198,750 |
£ 152,924 |
£-
45,826 |
£ 45,826 |
Other |
£543,500 |
£421,750 |
£421,750 |
£ 310,011 |
£-111,739 |
£111,739 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£112,209 |
£112,209 |
|
£-112,209 |
£112,209 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals
|
£6,196,307 |
£2,580,664 |
£2,580,664 |
£1,669,378 |
£-911,286 |
£911,286 |
Note any significant changes to the apportionment of
costs between the principal cost elements prior to their commitment. Note the
effect of any such changes and confirm that they will not affect the Approved
Purposes including expected quality.
Cost
transfer from : |
Cost
transfer to: |
Amount
(£) |
Effect
of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of expenditure of the total
Balance (A-C) calculated above and the funding sources to cover the expenditure
|
To
date |
Next Qtr |
2nd
Qtr |
3rd
Qtr |
4th
Qtr |
5th
Qtr |
Later |
Total
to Completion |
Expenditure
of Approved Cost |
Enter Total
of C above |
|
|
|
|
|
|
Enter Total of A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,669,378 |
|
|
|
|
|
|
£2,580,664 |
Other
source (1) |
|
|
|
|
|
|
|
|
Other
source (2) |
|
|
|
|
|
|
|
|
Other
source (3) |
|
|
|
|
|
|
|
|
Total
Funding (to equal Expenditure of Approved Cost) |
£1,669,378 |
|
|
|
|
|
|
£2,580,664 |
7. Procurement
Enter the current procurement status of any
significant goods, works, or services currently being procured for the project,
or awarded since the last Report.
Goods/Works/ Services : brief description |
Approx Value |
EU procurement Applies? Yes./No |
No of tenderers |
Date of tender return |
Date of award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services not awarded to the
lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note any evidence provided at
the request of NHMF or the Project Monitor.
Property Description and
evidence provided |
Date evidence provided to
NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective From Date |
Expiry Date |
Employer
Liability Insurance |
21/10/00 |
20/10/01 |
Computer
Insurance |
21/10/00 |
21/10/01 |
Office
Insurance: Including Goods In Transit & Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried Staff (Note: applicable
only to staff whose salaries are included as Eligible Costs in the Approved
project.
Position |
Date Appointed |
Job Description sent to NHMF
(Yes/No) |
Media in which advert placed |
Employment Contract to NHMF (Yes/No) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer Staff
The total number of Volunteer staff employed at present is …………11…… (Details are
provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal statutory consents
required to complete the project
Consent Required |
Granting Authority |
Actual or expected date of
consent |
Planning |
N/A |
|
Listed
Building |
|
|
Scheduled
Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement, press releases, or
other publicity issued since the last report:
Description |
Date Issued |
Approved by NHMF (Yes/No) |
Displayed
acknowledgement |
N/A |
|
Press
Releases issued |
|
|
Publicity
issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making photographic records of
the project Y
14. Special Conditions
Indicate progress towards satisfying the Special
Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Grantee: Scottish Archive Network
Address:
Thomas Thomson House, 99 Bankhead Crossway North, Edinburgh, EH11 4DX
Signed
for Grantee: …Rob Mildren……………………………………………………..
Date: 27/09/01………………………….
Work on collection description creation continued in the following archives: Glasgow City, Dundee City, Aberdeen University Library Special Collections and West Lothian Archives/Local History Library (some of which in each case was revision of existing entries).
The revision of the internal work on West Lothian Archives/Local History Library was completed by the end of the month, and the entries were despatched for local checking.
The converted older data now migrated into the WeeArkis access databases continued to arrive from our casual student employees, and mostly it was possible to review what was received to ensure that the conversion had been properly managed. The work finished at end August, and has been successful in achieving what we had set out to do.
As a result of the NAS/SCAN recruitment board in June, two suitable candidates for SCAN were identified. One was due to start on 3 September; the other one was unfortunately moved away from SCAN before he had started with us to fill a vacant post in NAS, and another candidate who would then come to SCAN instead was going through clearance procedures as the month ended. We are making arrangements to extend the contract of one of our casual curatorial home-based staff, Andrew Jackson, who would otherwise finish on 30 September.
All the staff had at least a few days’ annual leave during the month.
Alan Borthwick attended a Scottish Executive seminar on Development Appraisal under the new Scottish Executive reporting system, 10 August; Jenny Cutts attended the same seminar on 16 August; he and Jenny Cutts attended an NAS seminar on Freedom of Information, 16 August; and Jenny Cutts attended the Scottish Archive Training School week-long course, Glasgow University Archives, from 20 August.
Joanna Baird and Victoria Miller worked closely together on the market research project for Scottish Wills. A questionnaire was drafted, and then put online and tested and eventually released to interested parties. Nearly 400 responses were received during the course of August and a database was created in order to store and facilitate analysis of the results. The final report incorporating these results was presented to SCAN on 24th August – Victoria’s final day on the project. Joanna and Victoria held a meeting with the business manager, Cathy Black together with Rob Mildren and Hazel Anderson in the middle of August to discuss progress. The findings of the report will be discussed in September.
There were some problems with the website during the course of August and for some time the Forum was not functional nor was it possible to add new material to the website. This was to some extent rectified by the end of the month but it has still not been possible to activate the email side of the Forum – thus greatly inhibiting the amount of postings received. Lack of a digital camera and problems with Joanna’s PC, the server and a lack of external email all delayed progress on Exhibitions, Research Tools and the Knowledge Base.
The 600th Knowledge Base entry was added to the website. All the Knowledge Base entries so far on the website underwent some redesign to give them a more consistent look, make navigation much easier/more logical and reduce download times.
The exhibition for the Royal College of Physicians and Surgeons in Glasgow was completed at the end of August and sent to RCPSG staff for approval. They were happy with it and it is scheduled to go online in September.
A new Virtual Tour was added to the website (for the National Library of Scotland).
Material sent for data capture was received back from ADS on 29 August and will be quality controlled in September.
Most of the team had some annual leave during August.
Robin Urquhart ran a Palaeography training morning at Angus Archives on 28 August and also carried out some research whilst there. Joanna Baird gave a talk at the Scottish Archive Training School on 22 August and also attended a seminar on e-commerce on 21 August.
An archivist from Cyprus visited the project on 7 August and was given an introduction to the testaments and website by the Internet Resources team.
Joanna Baird attended a meeting of VisitScotland’s Genealogy Steering Group on Wednesday 8th August.
The continuing problems with the digital camera meant that it was sent back to Atmel at the beginning of August. A replacement camera was not received until 30 August and therefore few images were made during August. Gary Clelland produced a number of A3 printouts for the Testaments team and also took photographs of TTH staff with the handheld digital camera for use on the NAS intranet.
Digital capture of the Aberdeen Testaments (SC1/37/1-76) was completed. The post-1823 registers currently being captured are: Ayr Inventories (SC6/44/1-38), which are nearing completion. Digital capture of the Edinburgh Testaments, 1514-1829 (CC8/8/1-152) continues, and capture of the Argyll Testaments (CC2/3/1-12) and Brechin Testaments (CC3/3/1-12) has been started.
Arlene and Grant Miller joined the GSU volunteer team on 27August, when they started their training programme, including document handling conducted by Dagmar.
The following visitors came to see the project during the month:
Robin Blair, Lord Lyon of Scotland; Margaret McCollum, Beth Rainy and Richard Higgins, Durham Diocesan Archives.
Images of six Aberdeen warrants (CC1/6/4325-35, 11689-93, 14545-50, 19947-49, 20103-05, 21104-07), a total of 32 images, were captured and printed out for readers by special request. A request relating to Aberdeen wills (SC1/36 & 37) was passed on from the SCAN website and answered by Hazel.
Ann attended a 1 day SE training course on ‘Introduction to Government in Scotland’ on 24 August, and Hazel and Margaret attended a NAS seminar on Freedom of Information legislation on 16 August.
The following staff were on holiday during the month:
Hazel – 1 week, Jane – 2 weeks, Margaret - 1 week.
Annex 2
1.1 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
Fulfilled. The Scottish Archive Network
follows all Scottish Executive procurement rules. This has been verified by Mr J Grady, Chief Procurement Officer NAS. |
|
1.2 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
|
|
1.3 |
NHMF may reduce the Grant by such amount
as it thinks fit up to an amount which bears the same proportion to the
difference between the lowest tender price and the price of the tender
accepted by the Grantee as the Grant bore to the original cost of the
Approved Purposes if NHMF, in its absolute discretion, disagrees with the
reason given by the Grantee for not accepting the lowest tender. |
|
|
1.4 |
The Grantee agrees that it shall only
accept tenders that it believes in good faith will result in the Approved
Purposes being carried out to the standard prescribed by Special Conditions 2
and 9 of this Contract. |
|
|
2. |
The Grantee shall carry out the Works or
shall procure that the Works are carried out in a professional manner in
accordance with currently accepted best practice in the Information
Technology industry. The Grantee will
ensure that best practice or proven and widely adopted standards are applied
especially in the areas of project management, requirements analysis, system
or application, design, testing, documentation, installation and maintenance
and in the area of the preservation of digital materials. |
SCAN believes that it is carrying out the
Works and procuring the Works in a professional manner in accordance with
currently accepted best practice in the Information Technology industry |
|
3. |
Prior to commencing the Works the Grantee
shall secure to NHMF’s satisfaction all necessary
planning permissions building consents and statutory approvals. |
Fulfilled |
|
4. |
Prior to commencing the Works the Grantee
shall prepare a detailed cost plan for carrying out the Approved Purposes in
a format which has been agreed in advance by NHMF and shall submit the same
to NHMF for Approval. Thereafter the
Grantee shall spend the Grant and other funds provided for the Approved
Purposes only in accordance with the Approved cost plan (“the Cost
Plan”). The Grantee must obtain prior
written Approval for any changes in expenditure which are not in accordance
with the details of the Cost Plan and in particular for movement of funds
between the various elements of the Cost Plan. |
Detailed cost plan submitted and agreed with the HLF. No changes in expenditure have been made
without prior written approval. The budget has been updated following the PID
review and a report detailing the variations form the original budget
estimates has also been submitted for discussion with the HLF at our next
quarterly meeting |
|
5. |
Prior to commencing the Works the Grantee
shall prepare a draft monthly project report form and a draft monthly cash
flow report form and shall submit the same to NHME for Approval. Thereafter the Grantee shall submit signed
monthly reports in the Approved forms to NHMF until the Approved Purposes
have been fulfilled. |
Signed monthly project reports and
monthly cash flows are submitted to the HLF |
|
6. |
Prior to commencing the Works the Grantee
shall submit to NHMF for Approval a revised and updated programme
for the Project. For the avoidance of
doubt the Programme shall contain details of the
works to be carried out at the development stage. The Grantee shall only carry out the Works
in accordance with the Approved programme (“the Programme”) or any modification thereof Approved by NHMF. |
The Project Initiation Document (PID) was
submitted to the HLF as requested. The revised PID has also been submitted
and discussed with the HLF |
|
7. |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance of the project on terms which note the interest of and
are Approved by NHMF. |
Insurance has been obtained and full
details given to the HLF. Any renewal notices will automatically be dealt
with by SCAN |
|
8. |
Prior to issuing invitations to tender
the grantee shall prepare a report on the information and communication
technology to be installed at the Property pursuant to the Approved Purposes
and without prejudice to the generality of the foregoing the report shall
include:- |
An ICT report was prepared and the
tendering process undertaken as agreed. The ICT infrastructure is now in
place and has been paid in full. The next requirement will be to increase the
data storage capacity as the digital imaging workflow increases |
|
8.1 |
a feasibility report |
|
|
8.2 |
the specification for the Digital
Deliverables |
|
|
8.3 |
the design of the system which shall in
particular include details of all interactives |
|
|
8.4 |
the proposals for the purchase of network
infrastructure. |
|
|
|
On receipt of Approval for the report
(“the ICT Report”) the Grantee shall prepare invitations to tender and tender
evaluation criteria for such works and shall submit the same to NHMF for
Approval. Thereafter the Grantee shall
issue invitations to tender in accordance with the Approved tender
invitations and evaluation criteria. |
|
|
9. |
The Grantee shall carry out the
information and communication technology works in accordance with currently
accepted best practice in the Information Technology industry. The Grantee will ensure that best practice
or proven and widely adopted standards are applied especially in the areas of
project management, requirements analysis, system or application
specification, design testing, user and system documentation, installation
and maintenance and in the areas of the preservation of digital materials. |
SCAN believes it has fulfilled and is
fulfilling this condition |
|
10. |
The Grantee shall submit to NHMF for
Approval details of the standards that the Grantee intends to implement. |
SCAN has submitted to the HLF its draft
cataloguing standards |
|
11.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report for the safeguarding and enhancement of, and public
access to, the Property including without limitation its proposals for: |
|
|
|
a) such
testing as may be necessary to demonstrate that the Digital Deliverables and
capable of fulfilling the Approved Purposes |
Schedule of Requirements for the Supply
of Digital Cameras |
October 1999 |
Information and Communications Technology
Requirements |
March 1999 |
||
Information and Communications Technology
Tender Document |
February 2000 |
||
Test plan submitted for installation of
ICT equipment |
October 2000 |
||
Data Capture Specification for Indexes |
November 1999 |
||
Website design specification |
November 1999 |
||
|
b) such
evaluation as may be necessary to demonstrate that the Digital Deliverables
are capable of fulfilling the Approved Purposes |
Evaluation and
selection criteria for ICT equipment submitted in evaluation report “SCAN ICT
Requirements Tender Report” |
April 2000 |
Book Cradle
Evaluation |
July 2000 |
||
Web Site Tender
Evaluation |
January 2000 |
||
Camera
Evaluation for HLF |
May 2000 |
||
Resolution
Requirements for Testaments |
May 2000 |
||
Data Capture
Tender Evaluation |
December 2000 |
||
|
c) the
preservation and security of all data and other material collected or
created in the course of carrying out
the Approved Purposes by the keeping of back-up copies of the Digital Deliverables and
otherwise; |
Weekly backups
and daily incremental backups take place for all SCAN information (excluding
images) |
April 2001 |
Uncompressed TIFF images are written to
DLT and stored locally |
November 2000 (and ongoing) |
||
Compressed JPEG images are written to the
Internet Server where a backup is taken weekly |
November 2000 (and ongoing) |
||
|
d) the
form of licence(s) to be used by the Grantee
permitting third party exploitation of the Intellectual Property; |
This was included as part of the contract
negotiations with the Genealogical Society of Utah. The HLF have a copy of
this document July 1999 |
|
|
e) the
form(s) of assignment(s) consent(s) waiver(s) licence(s)
or permission(s) to be used by the Grantee for the securing of third party
rights in the Intellectual Property; |
|
|
|
f) error
correction, maintenance and updating of the Digital Deliverables |
Data flow diagram of the digitisation process available May 2001 Proposed data flow for the maintenance of
distributed data for the online catalogues available from May 2001 |
|
|
g) user
manuals or instructions and interfaces for the Digital Deliverables and its
use. |
All manuals
received for ICT equipment and standard operation of digital cameras Additional operator manual developed with
GSU for the use of the digital camera. ser manual produced in association
with the GSU for the installation, maintenance and delivery of digital imaging
in June 2000 Guidelines for capture of fonds level descriptions produced by SCAN in September
2000 |
|
|
Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. The Grantee must obtain prior written
Approval for any changes in the proposals which are not in accordance with
the Approved reports |
|
|
11.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
12.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report on the hardware technology to be used with the Digital
Deliverables (“the Hardware”) including without limitation its proposals for: (a) such
testing as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved Purposes; (b) such
evaluation as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved
Purposes; (c) error
correction, maintenance and updating of the Hardware; and (d) user
manuals and instructions for the Hardware and its use. Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. On receipt of Approval of the said monthly
reports the Grantee shall implement the reports in carrying out the Approved
Purposes. The Grantee must obtain
prior written Approval for any changes in the proposals which are not in
accordance with the Approved reports. |
A presentation
and report covering the entire ICT requirements for the project was given |
May 2000 |
Information and
Communications Technology Requirements |
March 1999 |
||
Information and
Communications Technology Tender Document |
February 2000 |
||
Test plan
submitted for installation of ICT equipment |
October 2000 |
||
Data Capture
Specification for Indexes |
November 1999 |
||
12.2 |
On receipt of Approval of such proposals or
monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
13. |
The Grantee shall enter into a deposit
agreement with a third party Approved by NHMF for all Digital Deliverables
and any associated or necessary software and applications and shall
thereafter deposit escrow copies of the said Digital Deliverables on a basis
to be agreed with NHMF. |
Escrow discussed
for deposit of digital images. SCAN has a contract clause with GSU to provide
mutual restore and backup of digital images |
Early
discussions held with NCC Follow Up
Required |
14. |
The Grantee shall ensure that all
applications and software necessary to access use or present the digital
deliverables are transferable to a third party. |
Escrow discussed
for deposit of any software packages |
Early
discussions held with NCC Follow Up
Required |
15 |
The Grantee agrees that it shall take all
reasonable steps to mitigate to NHMF’s satisfaction
the amount of VAT payable upon, or to recover the VAT payable upon, or to recover
the VAT attributable to, the cost of fulfilling the Approved Purposes. The Grant shall be reduced by an amount
which bears the same proportion to the VAT not payable or recovered as the
Grant, prior to such decrease, bore to the original costs of the Approved
Purposes. |
SCAN has fulfilled this condition: VAT is fully recovered. |
|
16 |
At the end of Year 1 the Grantee is to produce a policy statement to support the extensibility of membership of Scottish Archive Network Limited with no financial implications. |
SCAN supports the extensibility of
membership of the Scottish Archive Network with no financial implications.
Currently there is an interest shown by the Roman Catholic Archdiocese of
Glasgow Archives for inclusion |
|
17 |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance for the Project on terms which note the interest of and
are Approved by NHMF. |
SCAN has fulfilled this condition |
|
18 |
The documents required to be submitted or
provided to NHMF under these special conditions, are required to be submitted
or provided by the Grantee only for NHMF’s own
purposes in connection with the Grant and NHMF’s
approval or acceptance of such documents cannot be taken as approval or
acceptance for any other purpose. |
This is accepted by SCAN |
|
|
19. [Clause
to go in here annexing contracts between a Scottish Archive Network Ltd and
others] |
|
|
20 |
The Grantee shall take account of any
representations which NHMF may make with regard to the carrying out of the
Approved Purposes in accordance with the Programme,
Design, specification, Cost Plan, ICT Report and the contracts referred to in
special conditions 1.1. In particular
the Grantee shall take account of any representations which NHMF may make
prior to the issue of a certificate of practical completion of the Works and
shall pass such representations on to the person authorised
to sign a certificate of practical completion. |
This is accepted by SCAN |
|
21 |
Without prejudice to the generality of
Clause 13.2 of this Contract NHMF may at any time appoint by notice in
writing to the Grantee a third party (“the Lead Monitor”) to monitor the
progress of the Approved Purposes and additional monitors to advise on
specialist matters arising from the implementations regarding the Approved
Purposes the Grantee shall take such reasonable steps as may be necessary to
comply with the recommendations. |
This is accepted by SCAN |
|
22 |
Prior to commencing the Works the Grantee
shall secure to the satisfaction of NHMF all the additional funding required
to complete the Approved Purposes. |
The additional funding required by the
HLF was secured. Budget projections supplied to HLF in March 2001 indicate
that the project will complete within budget and with the agreed percentage
of partnership funding |
Notes of Project Board Meeting
22 August 2001 14.30
Attendees:
Rob Mildren (Chair), George Mackenzie, Peter Anderson
Stuart
Low (Minute Secretary)
1 |
Minutes of Last Meeting and Review of Action Points |
Action
|
1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 1.11 1.12 |
The
minutes of the last meeting were approved. Progress on the following action
points was reported: Noted
that Conservation already operate a time sheet system. In order to prevent
duplication RM will discuss SCAN’s requirements
with LR. Noted that RM had spoken to GK and agreed that Arkis payments would be structured within the following framework. Consultancy
· Database · Application · Search Screens Intellectual
Property Rights
· Applications ·
Search Screens It
was noted that the overall cost would lie between £10,000 - £15,000. Further
noted that NT was drawing up a contract of conditions of service for the Swedish
Archives to sign. It was noted that the Swedish National Archives were the
only organisation able to supply this system. Noted that the B2 curatorial would join the project in September, although the B1 curatorial was still to be selected. Noted that over 300 replies had been received in response to VM’s market research questionnaire. Noted that 85% of respondents would be prepared to pay £7.00 for a digital image of a will. RM to discuss a charging structure with JG that would equate to the current charging structure in place in the search room. Noted that JB was in agreement with seeking wider distribution channels for the proposed SCAN poster. Also noted that this would be discussed further at the next PAWG meeting. Noted that RM would follow up on quality control checks for the index linking of images. Noted that RM had met with Ann Laird (New User Group Chair) on 13th August. Noted that AL would attend next HLF meeting on 19th September. Further noted that AL intended to establish topic groups to improve communications both within the User Group and between the User Group and SCAN. Also in her capacity as a teacher, AL suggested that her more mature pupils could evaluate certain aspects of the website. Noted that the next joint meeting of the User Group and the PAWG would take place in mid November in Glasgow. Agreed that the second phase of IT provision for the Participating Archives should be conducted on a first come, first served basis. Proposed that those archives that had signed off completion of their cataloguing work should be given priority. SL to discuss final drafting of bid invitation with AB. Noted that SCAN should be clearly associated with the provision of any SoA delivered training, funded through the SCAN project and that all training should be SoA certified. Noted that HA should discuss the issues surrounding the use of NAS repro staff on SCAN projects with Hugh Hagan. Proposed that a series of familiarisation visits be set up. Agreed that RM would discuss the Stairs project with JB in more detail. |
RM NT RM/JG RM RM SL/AB HA/HHRM/JB
|
2 |
Review of Workplans |
|
2.1 |
Internet Resources sub-Project |
|
2.1.1 2.1.2 2.1.3 |
Agreed
that the findings of VM’s market research report
would be discussed at the next HLF monitoring meeting on 19th September.
Stuart to add to Agenda. Noted
that the new forum software had been installed and initiated. Noted that work had begun on 5 new on-line exhibitions. |
SL |
2.2 |
Testaments |
|
2.2.1 2.2.2 2.2.3 2.2.4 2.2.5 |
Confirmed that the problem with the Atmel cameras had been resolved by inserting faster disk controllers in the PC’s. Noted that RM had proposed a new system to expedite the clearance of the digital tapes sent to the GSU in SLC in order to optimise the storage capacity of the server. Noted that all indexing and pagination was now complete and that resources could now be concentrated on image linking. Noted that NT had completed the union index for the sheriff court records and was now working on a similar index for the commissariats. It was agreed that due to PD’s continuing absence SL would review the budget to assess the viability of employing another conservator (B1) on a short-term basis. |
NT SL |
2.3 |
On-Line Catalogues |
|
2.3.1 2.3.2 2.3.3 |
Noted that AB had completed the Local Authority fonds project. Noted that Arkis now had the facility to draw groups of records together. Agreed that RM would discuss with AB and IO the options for completing the On-Line catalogues commitment of the project within budget. The options as proposed were: (a). Use agreed budget to fund existing staff, but protracted over a longer time frame than initially envisaged. (b). Employ additional staff, from within agreed budget, and complete the project on time. |
RM |
3.0 |
Procurement |
|
3.1 3.2 |
Noted that the next 2 digital cameras should arrive in early September. Noted that a quote for additional data storage servers had been requested from Morse. |
|
4.0 |
Staffing |
|
4.1 |
Nothing further to add over and above review of action points. |
|
5.0 |
Finance |
|
5.1 |
Written Report
Attached
|
|
6.0 |
User Group/PAWG |
|
6.1 |
Nothing further to add over and above review of action points. |
|
7.0 |
National Council of Archives |
|
7.1 |
Noted that the first meeting of the National Archives Network User Research Group will be held in London on 20th September. SL to attend and also to copy Sarah Flynn e-mail to PA. |
SL |
8.0 |
Marketing & Publicity
|
|
8.1 |
Nothing further to add over and above review of action points. |
|
9.0 |
AOCB |
|
9.1 |
Agreed that GM would ask Alison Lindsay to contact JB with regard to the Millenium Canal Link. |
GM |
10.0 |
Date
of Next Meeting |
|
|
The next Project Board meeting will be held on Thursday 27th September at 14.30 in Thomas Thomson House, Bankhead Crossway North, Edinburgh. |
|
SL
30/08/01
Scottish Archive Network
Finance Report – 30th August 2001
1.
HLF Drawdowns
1.1 The July
drawdown (26) of £47,283.56 is currently being assessed.
1.2 The August drawdown (27) was submitted on 24th
August.