|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To
be submitted by Grantee with each grant drawdown application, or at intervals
no greater than 3 months)
|
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the
Monitoring Documents referred to in your Grant Contract, you are required to
submit to NHMF a Progress Report with each grant drawdown application, or at
maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing
towards meeting the Approved Purposes. The headings and format
of the Report, addressing the principal monitoring criteria, are shown below.
These headings and format must be followed, but you may prepare your Report
using computer software incorporating spreadsheets as appropriate. All
sections (expanded in size as
necessary) are to be completed fully on each monthly report. (Use
supplementary sheets if necessary). PM forms should be returned in hardcopy and must be
completed fully. Failure to do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
30 |
|
Report Date: |
25 Oct 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Sept 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general progress towards
achievement of the Approved Purposes identifying any problems or issues to
which NHMF’s attention should be drawn. Note any actions proposed in response
to problems or particular areas of risk.
The
project remains within budget and is scheduled to be completed on time. |
See
annex 1 for detailed progress. |
See
annex 2 for update on special conditions. |
The
minutes of the Project Board held in September are attached at Annex 3. |
The
Project Performance Information is now held on the accompanying spreadsheet. |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing partnership funds
Source of Funding |
Amount expected (A) |
Amount received to date (B) |
Balance to come A-B) |
Date balance expected |
NAS |
£425,967 |
£102,686 |
£323,281 |
Dec
2002 |
GSU |
£703,785 |
£268,507 |
£435,278 |
Dec
2002 |
|
|
|
|
|
|
£1,129,752 |
£371,193 |
£758,559 |
Dec
2002 |
Totals
|
|
|
|
|
Explain any changes to sources
of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material change to the Approved
Purposes which have been approved by
NHMF since the last Report and advise of any potential requests for such change
in the future.
Description
of Change Item |
Date
of request to NHMF |
Date
of NHMF response |
Effect
on achievement of Approved Purposes |
Effect
on Programme |
Effect
on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any
material change to the Approved Purposes
Report on any effect to delivery of the Approved
Purposes of any cost transfer between the principal cost elements stated in
your “Notification of Grant”. (Note: no such transfer is to be made between
capital and revenue elements, or between VAT and any other cost element,
without NHMF prior consent ).
Amount
of cost transfer (£’000) |
Cost
transfer from (cost element): |
Cost
transfer to (cost element): |
Effect
on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or comments received from
NHMF or its Project Monitors since your last report
Work
element for which Design/Document review has been carried out |
Date
reviewed |
NHMF/Project
Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the agreed
Timetable/Programme for key activities
Grant Expiry Date:
Key Activity or milestone |
Planned completion date |
Actual (or currently forecast) completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall
Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a) Cost Control
Enter expenditure to date against the key items
of Approved Cost (i.e. the costs on
which NHMF has agreed to pay the Payment Percentage) compared with that
detailed in the pre-commencement documentation. (VAT and Contingencies to be
separately identified).
Items of Approved Cost (Principal cost elements) |
Approved Costs to completion as agreed at award |
Out-turn Costs as currently
forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual costs to Date (C) |
Variance (C-B) |
Balance of costs (A- C) |
Staff
|
£2,170,889 |
£1,593,632 |
£1,593,632 |
£1,087,487 |
£-506,145 |
£506,145 |
Internet
Server |
£449,700 |
£ 412,225 |
£ 412,225 |
£ 139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£ 37,768 |
£ 37,768 |
£ 31,388 |
£ - 6,380 |
£ 6,380 |
Digitisation |
£349,191 |
£217,500 |
£217,500 |
£ 160,495 |
£-
57,005 |
£ 57,005 |
Other |
£543,500 |
£453,425 |
£453,425 |
£ 329,799 |
£-123,626 |
£123,626 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£124,514 |
£124,514 |
|
£-124,514 |
£124,514 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals
|
£6,196,307 |
£2,839,064 |
£2,839,064 |
£1,749,017 |
£-1,090,047 |
£1,090,047 |
Note any significant changes to the apportionment of
costs between the principal cost elements prior to their commitment. Note the
effect of any such changes and confirm that they will not affect the Approved
Purposes including expected quality.
Cost
transfer from : |
Cost
transfer to: |
Amount
(£) |
Effect
of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of expenditure of the total
Balance (A-C) calculated above and the funding sources to cover the expenditure
|
To
date |
Next Qtr |
2nd
Qtr |
3rd
Qtr |
4th
Qtr |
5th
Qtr |
Later |
Total
to Completion |
Expenditure
of Approved Cost |
Enter Total
of C above |
|
|
|
|
|
|
Enter Total of A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,749,017 |
|
|
|
|
|
|
£2,839,064 |
Other
source (1) |
|
|
|
|
|
|
|
|
Other
source (2) |
|
|
|
|
|
|
|
|
Other
source (3) |
|
|
|
|
|
|
|
|
Total
Funding (to equal Expenditure of Approved Cost) |
£1,749,017 |
|
|
|
|
|
|
£2,839,064 |
7. Procurement
Enter the current procurement status of any
significant goods, works, or services currently being procured for the project,
or awarded since the last Report.
Goods/Works/ Services : brief description |
Approx Value |
EU procurement Applies? Yes./No |
No of tenderers |
Date of tender return |
Date of award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services not awarded to the
lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note any evidence provided at
the request of NHMF or the Project Monitor.
Property Description and
evidence provided |
Date evidence provided to
NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective From Date |
Expiry Date |
Employer
Liability Insurance |
21/10/00 |
20/10/01 |
Computer
Insurance |
21/10/00 |
21/10/01 |
Office
Insurance: Including Goods In Transit & Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried Staff (Note: applicable
only to staff whose salaries are included as Eligible Costs in the Approved
project.
Position |
Date Appointed |
Job Description sent to NHMF
(Yes/No) |
Media in which advert placed |
Employment Contract to NHMF (Yes/No) |
Curatorial
(Online
Catalogues) |
03/09/01 |
See
original PID |
SoA
Newsletter |
No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer Staff
The total number of Volunteer staff employed at present is …………11…… (Details are
provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal statutory consents
required to complete the project
Consent Required |
Granting Authority |
Actual or expected date of
consent |
Planning |
N/A |
|
Listed
Building |
|
|
Scheduled
Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement, press releases, or
other publicity issued since the last report:
Description |
Date Issued |
Approved by NHMF (Yes/No) |
Displayed
acknowledgement |
N/A |
|
Press
Releases issued |
|
|
Publicity
issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making photographic records of
the project Y
14. Special Conditions
Indicate progress towards satisfying the Special
Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Grantee: Scottish Archive Network
Address:
Thomas Thomson House, 99 Bankhead Crossway North, Edinburgh, EH11 4DX
Signed
for Grantee: …Rob Mildren……………………………………………………..
Date: 25/10/01………………………….
Work on collection description creation continued in the following archives: Glasgow City, Dundee City, Aberdeen University Library Special Collections, Edinburgh University Library Special Collections/Archives and Aberdeenshire Archives (the last two being new starts this month). By the end of the month work on Dundee City was nearing completion in initial draft form, and Aberdeen University Library Special Collections initial draft was finished.
Caroline Brown (B2) joined the staff on 3 September as a result of the summer recruitment campaign. Caroline’s principal role will be as data editor, a role which would have been taken on increasingly by one of the staff appointed originally had she not left a year ago. In this guise Caroline worked on the initial draft of Northern Health Services Archive collection descriptions, the editorial work on which was completed; and also on Jordanhill College (Strathclyde University), which was nearing completion.
There is still one more recruit from the summer campaign due to start, on 29 October. The casual contract of Andrew Jackson was concluded by mutual agreement at the end of September to allow him to work unimpeded on another task, and he will rejoin the staff, again as a casual member of staff, in early November.
A team meeting for all the staff (casual and permanent) was held in Edinburgh on 26 September. The meeting considered current progress, and discussed issues which might arise at the Participating Archives meeting due to be held on 5 October; and was a useful chance for us all to meet, especially as we had one new member of staff.
Caroline Brown was given a number of days of local induction training, and she attended a course about the new Scottish Executive appraisal system on 10 September.
Alan Borthwick gave an introduction to the work of SCAN to Bob Anger, a Canadian archivist on a secondment exercise to Scottish archives, and he then did about 6 days’ work on creation of collection descriptions for some kirk sessions in Borders’ presbyteries for us.
Jenny Cutts and Alan Borthwick attended the “Doors Open Day” event at GRH, 29 September, both representing SCAN. The event was well attended, and many people were given an introduction to the SCAN web-site.
Jenny Cutts and Niall Taylor attended a meeting in Glasgow, 11 September, at which a library-based collection description system was launched and discussions were held as to the continuation of work on this with a view to future co-operation with Scottish Archives, including SCAN.
Approximately 20 new pages/images were added to the Scottish Wills part of the website in September and many existing pages were edited to take into consideration these new additions. This was partly in preparation for ‘Doors Open Day’ to be held on Saturday 29th September.
The exhibition for the Royal College of Physicians and Surgeons in Glasgow was put online at the end of September. A list of suggested docs for imaging for the ‘Scots in…’ highlights exhibitions from the National Archives of Scotland was submitted to Rosemary Gibson, head of Outreach and Education branch for discussion. The list was summarily agreed and Gary will image the suggested items in October.
Research Tools on Lighthouse and Tax Records were added to the Virtual Strongroom in September. Continued problems with Joanna’s PC meant that new additions to the website proved much more time-consuming than normal.
Work was begun on editing the list of emigrants from which the data had been captured by ADS. Work will continue on this in October with a view to adding it to the website in November. Other data captured by ADS began to be received back in late September. This will also require quality controlling prior to putting it online.
In-year reviews were held in September. Most of the team had some annual leave during September.
Robin Urquhart gave a talk to the Highland Railway Heritage Society in Glasgow on Saturday 15th September. He also visited Perth & Kinross Council Archive on 21 September.
Joanna Baird attended a meeting of VisitScotland’s Genealogy Steering Group on Wednesday 5th September. Rob Mildren and Joanna Baird held a meeting with Ian Galbraith from Scots Origins on Wednesday 5th September.
Gary Clelland attended a 2-day course in Project Support organised by the Scottish Executive. This course formed part of Gary’s mentoring scheme. Gary also attended a lunchtime seminar on Technology and Innovation – Risk Management. All of the team attended an introduction to the new Development appraisal system in General Register House
Robin demonstrated the SCAN website to Bob Anger, a Canadian archivist, on 5th September.
The replacement digital camera arrived and functioned well during September and it was therefore possible to achieve the predicted amount of digital images. Gary produced images for the Scottish Wills microsite. He also produced some test images of seals and some images from UCS albums for Ian Johnston. Gary completed the imaging of the glass plate negatives of ‘City of New York’.
Digitising of the following series has now been completed: Aberdeen (SC1/36/1-77, SC1/37/1-76); Alloa (SC64/42/1-15); Ayr (SC6/1-38, SC6/46/1-11); Banff (SC2/40/1-28); Dingwall (SC25/44/1-11); Kinross (SC22/44/3-7); St Andrews (CC20/4/1-31, CC20/7/1-16); Edinburgh (CC8/11/1-6/2), Kirkwall (SC11/38/1-8, SC11/41/1); Lerwick (SC12/36/1-6).
Most 19th century CC volumes have also been completed.
Digitising of the following series is ongoing: Cupar (SC20/50/1-48); Kirkcudbright (SC16/41/4-32); Peebles (SC42/20/1-9);
Aberdeen warrants (CC1/6/bundles 1-86);
Edinburgh (CC8/8/1-152); Argyll (CC2/3/1-12); Brechin (CC3/3/1-12); Caithness
(CC4/3/1-3); Dumfries (CC5/6/1-21). Speed of capture of the foregoing CC series
is governed by Conservation production rates.
The pressure on server capacity caused by storage of copies of the GSU greyscale images has eased, but has not been eliminated. The tendering process for purchasing increased capacity is in hand.
In the last week of the month the two new cameras and book cradles were delivered and installed. One camera could not be operated due to a problem with fitting the shutter and lens. It is hoped to have this problem sorted out early next month. The latest update of the dCam software, designed to cope with A B C etc suffixes to page numbers, is operating well.
Although a higher number of volumes were captured than in August the actual number of images appeared to be fewer. This statistic is attributable to a number of factors:
- the August figures included a number of retakes, which had not been recorded
as such;
- 40% of the images captured were single page from relatively small volumes, which involved a higher ratio of handling to digitising time;
- 9% of the images captured were from loose documents, requiring individual positioning and cropping on screen;
- holiday leave by the volunteers.
Dagmar was closely involved in advising on the capture of the loose documents and making supports to facilitate the work.
During the month quality control levels were increased to 100% for one week in order to find out if significant numbers of sub-standard images were being missed at the 30% QC level. However, no significant increase was observed, and operators have reverted to the previous level. One of the more difficult judgements for the operators to make is the detection of minute degrees of colour shift. Rob Mildren has devised a programme to automate this detection, and the operators are currently experimenting with it.
Work continued on the registers of Edinburgh testaments (CC8/8) and the Aberdeen warrants (CC1/6), as well as the registers of Argyll (CC2/3), Brechin (CC3/3), Caithness (CC4/3) and Dumfries (CC5/6). The GSU team completed pagination of the 19th century Commissary Court registers.
Peter Dickson, who had been on continuous sick leave for three months, finally decided to resign from SCAN/NAS, with effect from 30 September. Though his departure is much regretted it enables SCAN and NAS to formulate more settled procedures for maintaining a satisfactory workflow.
Work on index/image linking of the Aberdeen Inventories registers (SC1/36) by the GSU volunteers continued satisfactorily, and was almost complete by the end of the month. Their next task will be the Aberdeen Wills (SC1/37)
Niall Taylor added the Glasgow entries to the union index of the 19th century registers, and continued work on putting together the index for the pre-1800 registers.
Jane continued the linking of images and index entries (and recording variants of surname and forename spellings) for the St Andrews Testaments registers (CC20/4). She also began work on the selection of warrants of Brechin testaments (CC3/4) for capture.
Margaret began entering volume and page numbers of the Dunblane registers (CC6/5) into the index database. Due to technical problems she was unable to access the index/image linking software on her computer, but she checked 1½ volumes of the St Andrews Testaments registers (CC20/4/27 & 28), inputting data on surname variants and page numbers to the index database. After consultation with Joanna, she also re-commenced work on the Wills microsite and prepared SCAN display boards for ‘Doors Open Day’.on 29th September.
Hazel quality controlled the 19th century Glasgow index, making a number of amendments, before passing it on to Niall for inclusion in the union index. She then started work on the Edinburgh index.
The following visitors came to see the project during the month:
Deborah Hunter and Joni McArthur, National Gallery of Scotland;
Bob Anger, archivist of the Presbyterian Church of Canada;
David Chinn, Production Manager for Record Copying, Public Record Office.
Ann Gibson attended a ½ day Scottish Executive training course on ‘Filing and Records Management’.
Margaret and Hazel took part in Edinburgh Doors Open Day on Saturday 29th September in the Historical Search Room at General Register House, demonstrating the SCAN website and answering general enquiries.
All testaments staff attended performance management appraisal training sessions during the month, and Hazel conducted in-year reviews with them.
The following staff member was on holiday during the month:
Dagmar – 2 weeks.
Annex 2
1.1 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
Fulfilled. The Scottish Archive Network
follows all Scottish Executive procurement rules. This has been verified by
Mr J Grady, Chief Procurement Officer NAS. |
|
1.2 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
|
|
1.3 |
NHMF may reduce the Grant by such amount
as it thinks fit up to an amount which bears the same proportion to the difference
between the lowest tender price and the price of the tender accepted by the
Grantee as the Grant bore to the original cost of the Approved Purposes if
NHMF, in its absolute discretion, disagrees with the reason given by the
Grantee for not accepting the lowest tender. |
|
|
1.4 |
The Grantee agrees that it shall only
accept tenders that it believes in good faith will result in the Approved
Purposes being carried out to the standard prescribed by Special Conditions 2
and 9 of this Contract. |
|
|
2. |
The Grantee shall carry out the Works or
shall procure that the Works are carried out in a professional manner in
accordance with currently accepted best practice in the Information
Technology industry. The Grantee will
ensure that best practice or proven and widely adopted standards are applied
especially in the areas of project management, requirements analysis, system
or application, design, testing, documentation, installation and maintenance
and in the area of the preservation of digital materials. |
SCAN believes that it is carrying out the
Works and procuring the Works in a professional manner in accordance with
currently accepted best practice in the Information Technology industry |
|
3. |
Prior to commencing the Works the Grantee
shall secure to NHMF’s satisfaction all necessary planning permissions
building consents and statutory approvals. |
Fulfilled |
|
4. |
Prior to commencing the Works the Grantee
shall prepare a detailed cost plan for carrying out the Approved Purposes in
a format which has been agreed in advance by NHMF and shall submit the same
to NHMF for Approval. Thereafter the
Grantee shall spend the Grant and other funds provided for the Approved
Purposes only in accordance with the Approved cost plan (“the Cost Plan”). The Grantee must obtain prior written Approval
for any changes in expenditure which are not in accordance with the details
of the Cost Plan and in particular for movement of funds between the various
elements of the Cost Plan. |
Detailed cost plan submitted and agreed with the HLF. No changes in expenditure have been made
without prior written approval. The budget has been updated following the PID
review and a report detailing the variations form the original budget
estimates has also been submitted for discussion with the HLF at our next
quarterly meeting |
|
5. |
Prior to commencing the Works the Grantee
shall prepare a draft monthly project report form and a draft monthly cash
flow report form and shall submit the same to NHME for Approval. Thereafter the Grantee shall submit signed
monthly reports in the Approved forms to NHMF until the Approved Purposes
have been fulfilled. |
Signed monthly project reports and
monthly cash flows are submitted to the HLF |
|
6. |
Prior to commencing the Works the Grantee
shall submit to NHMF for Approval a revised and updated programme for the
Project. For the avoidance of doubt
the Programme shall contain details of the works to be carried out at the
development stage. The Grantee shall
only carry out the Works in accordance with the Approved programme (“the
Programme”) or any modification thereof Approved by NHMF. |
The Project Initiation Document (PID) was
submitted to the HLF as requested. The revised PID has also been submitted
and discussed with the HLF |
|
7. |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance of the project on terms which note the interest of and
are Approved by NHMF. |
Insurance has been obtained and full
details given to the HLF. Any renewal notices will automatically be dealt
with by SCAN |
|
8. |
Prior to issuing invitations to tender
the grantee shall prepare a report on the information and communication
technology to be installed at the Property pursuant to the Approved Purposes
and without prejudice to the generality of the foregoing the report shall
include:- |
An ICT report was prepared and the
tendering process undertaken as agreed. The ICT infrastructure is now in
place and has been paid in full. The next requirement will be to increase the
data storage capacity as the digital imaging workflow increases |
|
8.1 |
a feasibility report |
|
|
8.2 |
the specification for the Digital
Deliverables |
|
|
8.3 |
the design of the system which shall in
particular include details of all interactives |
|
|
8.4 |
the proposals for the purchase of network
infrastructure. |
|
|
|
On receipt of Approval for the report
(“the ICT Report”) the Grantee shall prepare invitations to tender and tender
evaluation criteria for such works and shall submit the same to NHMF for
Approval. Thereafter the Grantee shall
issue invitations to tender in accordance with the Approved tender
invitations and evaluation criteria. |
|
|
9. |
The Grantee shall carry out the
information and communication technology works in accordance with currently
accepted best practice in the Information Technology industry. The Grantee will ensure that best practice
or proven and widely adopted standards are applied especially in the areas of
project management, requirements analysis, system or application specification,
design testing, user and system documentation, installation and maintenance
and in the areas of the preservation of digital materials. |
SCAN believes it has fulfilled and is
fulfilling this condition |
|
10. |
The Grantee shall submit to NHMF for
Approval details of the standards that the Grantee intends to implement. |
SCAN has submitted to the HLF its draft
cataloguing standards |
|
11.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report for the safeguarding and enhancement of, and public
access to, the Property including without limitation its proposals for: |
|
|
|
a) such
testing as may be necessary to demonstrate that the Digital Deliverables and
capable of fulfilling the Approved Purposes |
Schedule of Requirements for the Supply
of Digital Cameras |
October 1999 |
Information and Communications Technology
Requirements |
March 1999 |
||
Information and Communications Technology
Tender Document |
February 2000 |
||
Test plan submitted for installation of
ICT equipment |
October 2000 |
||
Data Capture Specification for Indexes |
November 1999 |
||
Website design specification |
November 1999 |
||
|
b) such
evaluation as may be necessary to demonstrate that the Digital Deliverables
are capable of fulfilling the Approved Purposes |
Evaluation and
selection criteria for ICT equipment submitted in evaluation report “SCAN ICT
Requirements Tender Report” |
April 2000 |
Book Cradle
Evaluation |
July 2000 |
||
Web Site Tender
Evaluation |
January 2000 |
||
Camera
Evaluation for HLF |
May 2000 |
||
Resolution
Requirements for Testaments |
May 2000 |
||
Data Capture
Tender Evaluation |
December 2000 |
||
|
c) the
preservation and security of all data and other material collected or
created in the course of carrying out
the Approved Purposes by the keeping of back-up copies of the Digital Deliverables and
otherwise; |
Weekly backups
and daily incremental backups take place for all SCAN information (excluding
images) |
April 2001 |
Uncompressed TIFF images are written to
DLT and stored locally |
November 2000 (and ongoing) |
||
Compressed JPEG images are written to the
Internet Server where a backup is taken weekly |
November 2000 (and ongoing) |
||
|
d) the
form of licence(s) to be used by the Grantee permitting third party
exploitation of the Intellectual Property; |
This was included as part of the contract
negotiations with the Genealogical Society of Utah. The HLF have a copy of
this document July 1999 |
|
|
e) the
form(s) of assignment(s) consent(s) waiver(s) licence(s) or permission(s) to
be used by the Grantee for the securing of third party rights in the
Intellectual Property; |
|
|
|
f) error
correction, maintenance and updating of the Digital Deliverables |
Data flow diagram of the digitisation
process available May 2001 Proposed data flow for the maintenance of
distributed data for the online catalogues available from May 2001 |
|
|
g) user
manuals or instructions and interfaces for the Digital Deliverables and its
use. |
All manuals
received for ICT equipment and standard operation of digital cameras Additional operator manual developed with
GSU for the use of the digital camera. ser manual produced in association
with the GSU for the installation, maintenance and delivery of digital
imaging in June 2000 Guidelines for capture of fonds level
descriptions produced by SCAN in September 2000 |
|
|
Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. The Grantee must obtain prior written
Approval for any changes in the proposals which are not in accordance with
the Approved reports |
|
|
11.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
12.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report on the hardware technology to be used with the Digital
Deliverables (“the Hardware”) including without limitation its proposals for: (a) such
testing as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved Purposes; (b) such
evaluation as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved
Purposes; (c) error
correction, maintenance and updating of the Hardware; and (d) user
manuals and instructions for the Hardware and its use. Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. On receipt of Approval of the said monthly
reports the Grantee shall implement the reports in carrying out the Approved
Purposes. The Grantee must obtain
prior written Approval for any changes in the proposals which are not in
accordance with the Approved reports. |
A presentation
and report covering the entire ICT requirements for the project was given |
May 2000 |
Information and
Communications Technology Requirements |
March 1999 |
||
Information and
Communications Technology Tender Document |
February 2000 |
||
Test plan
submitted for installation of ICT equipment |
October 2000 |
||
Data Capture
Specification for Indexes |
November 1999 |
||
12.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
13. |
The Grantee shall enter into a deposit
agreement with a third party Approved by NHMF for all Digital Deliverables
and any associated or necessary software and applications and shall
thereafter deposit escrow copies of the said Digital Deliverables on a basis
to be agreed with NHMF. |
Escrow discussed
for deposit of digital images. SCAN has a contract clause with GSU to provide
mutual restore and backup of digital images |
Early
discussions held with NCC Follow Up
Required |
14. |
The Grantee shall ensure that all
applications and software necessary to access use or present the digital
deliverables are transferable to a third party. |
Escrow discussed
for deposit of any software packages |
Early
discussions held with NCC Follow Up
Required |
15 |
The Grantee agrees that it shall take all
reasonable steps to mitigate to NHMF’s satisfaction the amount of VAT payable
upon, or to recover the VAT payable upon, or to recover the VAT attributable
to, the cost of fulfilling the Approved Purposes. The Grant shall be reduced by an amount
which bears the same proportion to the VAT not payable or recovered as the
Grant, prior to such decrease, bore to the original costs of the Approved
Purposes. |
SCAN has fulfilled this condition: VAT is fully recovered. |
|
16 |
At the end of Year 1 the Grantee is to produce a policy statement to support the extensibility of membership of Scottish Archive Network Limited with no financial implications. |
SCAN supports the extensibility of
membership of the Scottish Archive Network with no financial implications.
Currently there is an interest shown by the Roman Catholic Archdiocese of
Glasgow Archives for inclusion |
|
17 |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance for the Project on terms which note the interest of and
are Approved by NHMF. |
SCAN has fulfilled this condition |
|
18 |
The documents required to be submitted or
provided to NHMF under these special conditions, are required to be submitted
or provided by the Grantee only for NHMF’s own purposes in connection with
the Grant and NHMF’s approval or acceptance of such documents cannot be taken
as approval or acceptance for any other purpose. |
This is accepted by SCAN |
|
|
19. [Clause
to go in here annexing contracts between a Scottish Archive Network Ltd and
others] |
|
|
20 |
The Grantee shall take account of any
representations which NHMF may make with regard to the carrying out of the
Approved Purposes in accordance with the Programme, Design, specification,
Cost Plan, ICT Report and the contracts referred to in special conditions
1.1. In particular the Grantee shall
take account of any representations which NHMF may make prior to the issue of
a certificate of practical completion of the Works and shall pass such
representations on to the person authorised to sign a certificate of
practical completion. |
This is accepted by SCAN |
|
21 |
Without prejudice to the generality of
Clause 13.2 of this Contract NHMF may at any time appoint by notice in
writing to the Grantee a third party (“the Lead Monitor”) to monitor the
progress of the Approved Purposes and additional monitors to advise on
specialist matters arising from the implementations regarding the Approved
Purposes the Grantee shall take such reasonable steps as may be necessary to
comply with the recommendations. |
This is accepted by SCAN |
|
22 |
Prior to commencing the Works the Grantee
shall secure to the satisfaction of NHMF all the additional funding required
to complete the Approved Purposes. |
The additional funding required by the
HLF was secured. Budget projections supplied to HLF in March 2001 indicate
that the project will complete within budget and with the agreed percentage
of partnership funding |
Notes of Project Board Meeting
27 September 2001 16.00
Attendees:
Rob Mildren (Chair), George Mackenzie, Peter Anderson, Stuart Low (Minute
Secretary).
1. Minutes of Last Meeting Review of
Action Points
1.1 It was noted that Rob was still to discuss the issue of
conservation time sheets with Linda Ramsay. Action:
RM
1.2 It was agreed that the implications of the Arkis software
solution would be discussed at the participating archives meeting on 5th
October.
1.3 It was noted that Rob was intending to discuss the issue of
user charges in detail with Jim Grady. It was agreed that access to grey scale
images of the testaments should be made available in the search rooms at a
different charge on a self serve basis Action:
RM
1.4 Following on from the HLF Monitoring meeting it was clarified
that SCAN had never intended to provide access to images as an entirely free
service. It was also suggested that material for educational use could be
contextually packaged and made widely available at minimal cost.
1.5 It was noted that consideration needed to be given to the way
in which any income generated by SCAN could be used within the wider NAS after
post-project integration. It was suggested that it might be able to fund
further digitisation projects of various classes of records.
1.6 It was confirmed that Hazel was carrying out selective quality
assurance on the index linking.
1.7 It was noted that the next user group meeting would take place
on Saturday 1st December at TTH.
1.8 It was agreed that Stuart would contact David Brown and Ian
Hill to confirm their attendance at the participating archives meeting on 5th
October. Action:
SL
1.9 It was confirmed that the bid form for the second phase of IT
equipment provision had been distributed to the participating archives. It was
agreed to discuss this with the participating archives at the meeting on 5th
October.
1.10 It was confirmed that Hazel and Rob had met with Hugh Hagan to
discuss the use of NAS reprographic staff on (after-hours) commercial
digitisation projects. It was also confirmed that this arrangement was
acceptable.
1.11 It was noted that a price had been agreed for the STAIR Society
digitisation project. It was agreed that Rob would inform the NAS that the
STAIR Society information would be available on the SCAN web-site. Action:
RM
1.12 It was noted that Niall was
continuing with work on the Union Index.
1.13 It was confirmed that Stuart had assessed the financial
implications of employing a further conservator.
1.14 It was noted that Alan would produce a timetable detailing the
completion schedule for the online catalogues for the October HLF report.
Action:
AB
1.15 It was noted that discussions with Personnel were underway
regarding the extension/re-employment of staff on casual contracts.
1.16 It was agreed to check with Joanna, whether Alison Lindsay had
been in contact with her regarding the British Waterways, Millennium Canal
Link. Action:
SL
2.0 Review of Workplans
2.1 Online Catalogues
2.1.1 It was confirmed that wee Arkis had now been completed.
2.1.2 It was noted that the further curatorial staff member for the
online catalogues team would be unlikely to start until late October.
2.2 Internet Resources
2.2.1 It was noted that the Marketing Report compiled by Victoria
Miller had been passed to the HLF for comment and review.
2.2.2 It was confirmed that a bid was being prepared for submission to
the Lord Lyon for the proposed Heraldic Crests digitisation project.
2.3 Testaments
2.3.1 It was confirmed that Ralf Ihrig from IKM was currently setting
up the final 2 digital cameras.
2.3.2 It was noted that it was now unlikely that there would be any
overlap between GSU volunteers who had finished their contracts and the arrival
of their replacements.
2.3.3 It was confirmed that financial analysis had shown that the
project would remain within viable limits, given current and projected levels
of GSU partnership funding.
2.3.4 It was noted that the delays in clearing the data tapes in SLC
now seemed to have been resolved.
2.3.5 It was noted that Morse had supplied a quote for an additional
200GB of storage capacity. As the figure was over the £10,000 tender threshold
it was agreed that Rob would discuss the tendering process with Jim Grady. Action:
RM
3.0 Procurement
3.1 It was confirmed that Rob was following up on the procurement
of cataloguing software, which would interface with the wee Arkis system. Action:
RM
4.0 Staffing
4.1 It was agreed that, given the current situation, conservation
should be run as an integrated SCAN/NAS function.
5.0 Finance
5.1 It was noted that the HLF drawdown request No. 26 had been
delayed, due to the request being misplaced. It was further noted that the HLF
had apologised for this and that steps had been taken to ensure that this would
not happen again. Drawdown No 27 had been processed as normal.
5.2 It was confirmed that an audit of the company’s financial
affairs had been undertaken by McCabe’s between 4th-7th
September. It was noted that the nature of the SCAN/NAS financial relationship
still required to be fully resolved. It was agreed that George would speak to
Jim Grady to clarify this. Action:
GM
6.0 Participating
Archives
6.1 It was noted that a training bid form had been distributed to
all participating archives. It was noted that SCAN had agreed to fund all or
part of the training needs as identified by participating archives. It was also
agreed to discuss this issue at the meeting on 5th October.
7.0 NANURG
Meeting
7.1 It was noted that the NCA had set up a committee (National
Archives Network User Research Group) to gather and evaluate feedback data from
users of online digital archive services. It was noted that the projects to be
evaluated included SCAN, A2A, AIM 25, Re:source and the Archives Hub.
7.2 It was confirmed that 3 evaluation sessions would take place
between the 3-14 December 2001 and would be held in 3 locations; London,
Manchester and Edinburgh. It was also noted that each session would aim for a
different user group, including academics, educationalists, professional users
and family historians.
7.3 It was noted that SCAN had been asked to identify specific
issues it may want the evaluation sessions to address, for inclusion in the
design of the evaluation study.
7.4 It was noted that the next meeting of this group would take
place on 22 October in Manchester. Stuart to attend. Action: SL
8.0 Indexing
8.1 Stair Society as per
Action Points
8.2 It was noted that there had been for further contact with the
Royal College of Nursing regarding their proposed digitisation project since
they had been sent an initial quote.
9.0 Marketing/Publicity
9.1 It was noted that after the events of the 11th
September, no further contact had been made with the American Scottish
Foundation. It was also suggested that New York/Tartan Day 2002 might no longer
be an appropriate location for the launch of the Testaments project. It was
agreed that a rethink of the launch strategy was required. It was agreed that
the launch of the online catalogues should proceed as planned and that a
Scottish venue should be identified as soon as possible.
9.2 It was noted that Eddie Friel (Glasgow & Clyde Tourist
Board) had contacted George with regard to promoting SCAN through his
organisation. Agreed that George would follow this up.
Action:
GM
10.0 A.O.C.B
10.1 It was agreed that arrangements should now be made for the
Orkney and Shetland volumes, brought back by Alan for digitisation, to be
returned.
11.0 Date
of Next Meeting
The next project board will be held on Tuesday
23rd October at 10.00am in TTH.