|
Form PM3 ( Interim
Report2:
|
|
|
FORMAT OF PROGRESS REPORT |
|
|
|
||||||
|
(To
be submitted by Grantee with each grant drawdown application, or at intervals
no greater than 3 months)
|
|
||||||||||
|
Form PM3(Part 2-Capital)
|
|
||||||||||
|
|
|
||||||||||
|
Project Title: |
Scottish Archive
Network |
|
Project Ref No: |
DG-95-05231 |
|
||||||
|
|
|
|
|
|
|
||||||
|
Name of Grantee: |
Scottish Archive
Network |
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
|
|
|
||||||
|
As stated in the
Monitoring Documents referred to in your Grant Contract, you are required to
submit to NHMF a Progress Report with each grant drawdown application, or at
maximum intervals of 3 months in the absence of an application, reporting on how the project is progressing
towards meeting the Approved Purposes. The headings and format
of the Report, addressing the principal monitoring criteria, are shown below.
These headings and format must be followed, but you may prepare your Report
using computer software incorporating spreadsheets as appropriate. All
sections (expanded in size as
necessary) are to be completed fully on each monthly report. (Use
supplementary sheets if necessary). PM forms should be returned in hardcopy and must be
completed fully. Failure to do so will delay processing your Grant |
|
||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
|
|||||||||||
|
Report No: |
31 |
|
Report Date: |
23 Nov 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
|
|
|
|
Covering Period: |
Oct 2001 |
|
||||||
|
|
|
|
|
|
|
||||||
1.
General Progress/ Programme and Project Objectives
Enter summary report on general progress towards
achievement of the Approved Purposes identifying any problems or issues to
which NHMF’s attention should be drawn. Note any actions proposed in response
to problems or particular areas of risk.
The
project remains within budget and is scheduled to be completed on time. |
See
annex 1 for detailed progress. |
See
annex 2 for update on special conditions. |
The
minutes of the Project Board held in September are attached at Annex 3. |
The
Project Performance Information is now held on the accompanying spreadsheet. |
|
|
|
|
|
2. Partnership Funding
Enter progress towards securing partnership funds
Source of Funding |
Amount expected (A) |
Amount received to date (B) |
Balance to come A-B) |
Date balance expected |
NAS |
£425,967 |
£106,330 |
£319,637 |
Dec
2002 |
GSU |
£703,785 |
£288,460 |
£415,325 |
Dec
2002 |
|
|
|
|
|
|
£1,129,752 |
£394,790 |
£734,962 |
Dec
2002 |
Totals
|
|
|
|
|
Explain any changes to sources
of Partnership Funding since the last Progress Report
|
|
|
3. Change Control
Enter requests for any material change to the Approved
Purposes which have been approved by
NHMF since the last Report and advise of any potential requests for such change
in the future.
Description
of Change Item |
Date
of request to NHMF |
Date
of NHMF response |
Effect
on achievement of Approved Purposes |
Effect
on Programme |
Effect
on Costs |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note: NHMF Approval is required for any
material change to the Approved Purposes
Report on any effect to delivery of the Approved
Purposes of any cost transfer between the principal cost elements stated in
your “Notification of Grant”. (Note: no such transfer is to be made between
capital and revenue elements, or between VAT and any other cost element,
without NHMF prior consent ).
Amount
of cost transfer (£’000) |
Cost
transfer from (cost element): |
Cost
transfer to (cost element): |
Effect
on delivery of Approved Purposes |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4. Review of Design Drawings and
Documentation
Enter any design reviews or comments received from
NHMF or its Project Monitors since your last report
Work
element for which Design/Document review has been carried out |
Date
reviewed |
NHMF/Project
Monitor’s comments (if any) |
N/A |
|
|
|
|
|
|
|
|
|
|
|
5. Timetable/Programme
Enter progress compared with the agreed
Timetable/Programme for key activities
Grant Expiry Date:
Key Activity or milestone |
Planned completion date |
Actual (or currently forecast) completion date |
Variance |
Comment |
See Annex 1 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Overall
Project Completion |
|
|
|
|
6. Expenditure on Approved Costs
a) Cost Control
Enter expenditure to date against the key items
of Approved Cost (i.e. the costs on
which NHMF has agreed to pay the Payment Percentage) compared with that
detailed in the pre-commencement documentation. (VAT and Contingencies to be
separately identified).
Items of Approved Cost (Principal cost elements) |
Approved Costs to completion as agreed at award |
Out-turn Costs as currently
forecast (A) |
Planned costs to date - as submitted with Form PM1 (B) |
Actual costs to Date (C) |
Variance (C-B) |
Balance of costs (A- C) |
Staff
|
£2,170,889 |
£1,593,632 |
£1,593,632 |
£1,108,761 |
£-484,871 |
£484,871 |
Internet
Server |
£449,700 |
£ 412,225 |
£ 412,225 |
£ 139,848 |
£-272,377 |
£272,377 |
Communication |
£51,222 |
£ 37,768 |
£ 37,768 |
£ 36,250 |
£ - 1,518 |
£ 1,518 |
Digitisation |
£349,191 |
£217,500 |
£217,500 |
£ 249,231 |
£-
31,821 |
£ 31,821 |
Other |
£543,500 |
£453,425 |
£453,425 |
£ 333,043 |
£-120,382 |
£120,382 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contingency |
£2,631,805 |
£124,514 |
£124,514 |
|
£-124,514 |
£124,514 |
VAT |
N/A |
|
|
|
|
|
|
|
|
|
|
|
|
Totals
|
£6,196,307 |
£2,839,064 |
£2,839,064 |
£1,867,133 |
£-1,035,483 |
£1,035,483 |
Note any significant changes to the apportionment of
costs between the principal cost elements prior to their commitment. Note the
effect of any such changes and confirm that they will not affect the Approved
Purposes including expected quality.
Cost
transfer from : |
Cost
transfer to: |
Amount
(£) |
Effect
of Transfer |
N/A |
|
|
|
|
|
|
|
|
|
|
|
b) Cash Flow
Enter the expected timing of expenditure of the total
Balance (A-C) calculated above and the funding sources to cover the expenditure
|
To
date |
Next Qtr |
2nd
Qtr |
3rd
Qtr |
4th
Qtr |
5th
Qtr |
Later |
Total
to Completion |
Expenditure
of Approved Cost |
Enter Total
of C above |
|
|
|
|
|
|
Enter Total of A above |
Funded
by: |
|
|
|
|
|
|
|
|
NHMF |
£1,867,133 |
|
|
|
|
|
|
£2,839,064 |
Other
source (1) |
|
|
|
|
|
|
|
|
Other
source (2) |
|
|
|
|
|
|
|
|
Other
source (3) |
|
|
|
|
|
|
|
|
Total
Funding (to equal Expenditure of Approved Cost) |
£1,867,133 |
|
|
|
|
|
|
£2,839,064 |
7. Procurement
Enter the current procurement status of any
significant goods, works, or services currently being procured for the project,
or awarded since the last Report.
Goods/Works/ Services : brief description |
Approx Value |
EU procurement Applies? Yes./No |
No of tenderers |
Date of tender return |
Date of award |
Selected
Contractor/supplier/ consultant |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Identify any goods/works/services not awarded to the
lowest tenderer and provide reasons why the selected
supplier/consultant/contractor offered best value for money.
8. Property Ownership and Possession
Note any evidence provided at
the request of NHMF or the Project Monitor.
Property Description and
evidence provided |
Date evidence provided to
NHMF |
N/A |
|
|
|
9. Insurance
Enter the insurances you have effected:
Cover |
Effective From Date |
Expiry Date |
Employer
Liability Insurance |
21/10/00 |
20/10/01 |
Computer
Insurance |
21/10/00 |
21/10/01 |
Office
Insurance: Including Goods In Transit & Officers Liability Insurance. |
21/10/00 |
21/10/01 |
10. Appointment of
Staff (Revenue Elements only, if
any)
List the salaried staff appointed (applicable to “Revenue” elements
of project only) since your last Report and the total number of volunteers
currently employed (if any).
a) Salaried Staff (Note: applicable
only to staff whose salaries are included as Eligible Costs in the Approved
project.
Position |
Date Appointed |
Job Description sent to NHMF
(Yes/No) |
Media in which advert placed |
Employment Contract to NHMF (Yes/No) |
Curatorial
(Online
Catalogues) |
29/10/01 |
See
original PID |
SoA
Newsletter |
No |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
b) Volunteer Staff
The total number of Volunteer staff employed at present is …………11…… (Details are
provided with PM3 (Part1)
11. Statutory Consents
Enter the status of the principal statutory consents
required to complete the project
Consent Required |
Granting Authority |
Actual or expected date of
consent |
Planning |
N/A |
|
Listed
Building |
|
|
Scheduled
Monument |
|
|
Others |
|
|
12. Publicity and Grant Acknowledgement
Enter displayed acknowledgement, press releases, or
other publicity issued since the last report:
Description |
Date Issued |
Approved by NHMF (Yes/No) |
Displayed
acknowledgement |
N/A |
|
Press
Releases issued |
|
|
Publicity
issued |
|
|
|
|
|
13. Photographic Records
Y
Confirm that you are making photographic records of
the project Y
14. Special Conditions
Indicate progress towards satisfying the Special
Conditions (if any) noted in the Contract:
No |
Special Condition |
Target Date for compliance |
Current Status |
|
See Annex 2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Name
of Grantee: Scottish Archive Network
Address:
Thomas Thomson House, 99 Bankhead Crossway North, Edinburgh, EH11 4DX
Signed
for Grantee: …Rob Mildren……………………………………………………..
Date: 23/11/01………………………….
Work on collection description creation continued in the following archives: Dundee City, Orkney Archives, Aberdeenshire Archives, Stirling Council Archives, Highland Council Archives, and Stirling University Library Special Collections (the last being a new start this month). A little work was also done for National Archives of Scotland collections. By the end of the month work on Dundee City was nearing completion in initial draft form. Editing work took place on Aberdeen University Library Spec. Coll./Archives and Lothian Health Services Archive data.
Approximately 1,000 basic name authority records were made available to participating archive staff only on a restricted access part of the website in mid-October, to allow them to see at last a little of what we have been doing.
A meeting (15 October) was held with the archivist of the Glasgow consortium led by Glasgow University Archives (GUA) contributing data to the Archives Hub project. The consortium includes five SCAN participating archives: GUA, Glasgow University Library Special Collections, Strathclyde University Archives, Glasgow School of Art, and Glasgow Caledonian University Archives. As there is nothing to be gained from duplication of effort, we agreed to co-operate as much as we can in the provision of collection-level descriptions, so that entries created for one project will be made available to the other. Something of this nature has worked well with Aberdeen University Library Special Collections/Archives. Alan Borthwick attended a Steering Group meeting of the Archives Hub project; and will be one of the evaluators of bids submitted for the next round of Archives Hub money, due to be awarded in December.
The final new recruit from the summer recruitment round, Helen Kemp (graded B1), joined the staff on 29 October. For the first time since June 2000 the team within TTH is complete, although with our two “out-workers” in Glasgow and Aberdeen we are in fact able to make inroads into the backlog of work that has built up since we were last at full strength.
Jenny Cutts completed her probationary period of employment at the start of the month.
Helen Kemp was given a number of days of local induction training, to be continued in November.
Alan Borthwick gave an update on current work to the meeting of the Participating Archives, 5 October. He and Jenny Cutts attended Scottish Executive “Development Appraisal” training courses during the month. He, Jenny and Caroline Brown attended NAS meetings involving demonstrations of possible new cataloguing systems for NAS, which may prove very relevant to SCAN in the short term.
Alan Borthwick gave a lecture, “Digitising our Past for our Future”, to the annual conference of the Scottish Local History Forum, Edinburgh, 13 October.
Alan visited Clackmannanshire Archives, Alloa, on 18 October with a view to their potential participation in the SCAN project, and agreed with the archivist there in general how they might become a participating archive.
Mr Scanlin, a
volunteer worker on the Knowledge Base finished his creation of entries on
Scottish burghs and this work was handed over to SCAN staff for editing.
Preparatory work began
on the creation of the Stair Society manuscripts pages in preparation for their
AGM on 10th November.
Work continued on
editing Highlands and Islands Emigration data and it is hoped to finish this in
November and make it available online together with some complementary sources.
The IT staff were
finally able to activate the email functionality of the website towards the end
of October. This made it possible for Joanna to set up a Forum for
Participating Archives and to send out passwords to all the Participating
Archives as well as the Users Group.
Development appraisals
for team staff were held in October. Robin and Gary both had some annual leave
in October.
Gary Clelland
continued on his Leadership Development Training and this included a meeting
with his mentor and with the NAS Development Adviser. He also carried out some
training at the Learning Resource Centre – namely on Project Teams and Project
Management.
Robin Urquhart gave a talk to Renfrewshire Family History Society on 18th October and conducted two
research visits to participating archives – NAS and Glasgow City Archives. Robin
Urquhart also attended the Participating Archives meeting on 5th
October where he gave an update on the progress of the Knowledge Base, asking for contributions and assistance with
quality checking.
Joanna Baird attended
a meeting of the VisitScotland Steering Group on 5th October. Joanna
also gave two presentations to Postgraduate Students during the PGTVER
(Postgraduate Training Visits to Edinburgh Repositories) week of 22nd – 26th October.
The digital camera had
to be returned to IKM on 3 October because of technical problems. During transit,
the CCD array was damaged and this therefore meant further delay. It was not
returned to SCAN in October and therefore few images for the website could be
produced during October. Gary Clelland was allowed some time on the GSU’s Kodak
camera and this enabled him to carry out some imaging work of NAS Parliamentary
material on behalf of the Stair Society.
Digitising of the following series with the Atmel cameras has now been completed
· Dingwall (SC25/44/1-11)
· Dornoch (SC9/36/1-6)
· Dumbarton (SC65/34/1-20)
· Dumfries (SC15/41/1-16)
· Dunblane (SC44/44/1-22)
· Cupar (SC20/50/1-48) is almost complete
· Edinburgh Inventories (SC70/1/1-176) has begun.
· Aberdeen Inventories (SC1/36) Re-takes of a number of volumes of Aberdeen Inventories were carried out as a result of errors (mainly pages missed) identified at the index linking stage.
Digitising of the following series with the Kodak cameras continues:
· Aberdeen warrants (CC1/6/bundles 1-86)
· Edinburgh Testaments (CC8/8/1-152)
· Dumfries (CC5/6)
· Dunblane (CC6/5)
· Dunkeld (CC7/7)
·
Peebles (CC18/4)
The new cameras delivered in September were fully operational by the end of the second week in October and this is reflected in a 63% increase in the capture of images over the September figures. This increase was achieved despite problems with one of the Kodak book cradles, caused by malfunction of the compressor. This problem was finally fixed by the end of the month.
Digitised registers of Kirkwall (SC11/38/1-8 & SC11/41/1) and Lerwick testaments (SC12/36/1-6) were collected by the archivists of Orkney and Shetland respectively for return to the archives.
Dagmar and Ann concentrated on preparation of the registers of Edinburgh testaments (CC8/8) and the Aberdeen warrants (CC1/6). Dagmar also refined operating procedures for capture of the warrants, to increase both efficiency in throughput and protection of the documents.
At a meeting with NAS Preservation Branch on 29th October procedures were defined for NAS Conservation to assist in the work of preparing testaments for digitising. It is hoped that this will maintain the workflow of the two Kodak cameras
Editorial
Work on index/image linking by the GSU volunteers of the Aberdeen Inventories registers (SC1/36/1-77), including the recaptured volumes, was completed during the month. Linking of the Aberdeen Wills (SC1/37/1-76) was nearing completion by the end of the month
Niall Taylor completed the union index for the pre-1800 registers.
Jane continued the linking of images and index entries (and recording variants of surname and forename spellings) for the St Andrews Testaments registers (CC20/4).
Margaret continued entering volume and page numbers of the Dunblane registers (CC6/5) into the index database. She was also able to recommence work on linking the St Andrews registers after problems with the software were sorted out.
Hazel continued quality control of the 19th century Edinburgh index.
A party of staff from NAS Court and Legal Records branch visited the project on 17th October. Several SCAN staff had the dCam software demonstrated to them by Jim Oakley during the month.
On request, Hazel produced digital image
quality control guidelines for the Wiltshire Wills Project and sent a copy of
the SCAN document handling guidelines to the Waterways Trust. She took part in
a meeting about the ‘Seals Online’ project, chaired by the Keeper, on 9th
October and gave a brief presentation about progress in the Testaments project
at a meeting of the Participating Archives on 5th October at GRH.
Ann and Dagmar attended a 1 day training course on photographic preservation organised by the Library Association Local Studies Group on 31st October in Perth and took part in training arranged by NAS conservation on edge-gilding on 1st and 2nd November at TTH.
Hazel attended Development Appraisal
training at GRH on 18th October and conducted interviews with
Testaments staff in the final week of the month. The Keeper conducted an
in-year Performance Management review with Hazel on 26th October.
Annex
2
1.1 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
Fulfilled. The Scottish Archive Network
follows all Scottish Executive procurement rules. This has been verified by Mr
J Grady, Chief Procurement Officer NAS. |
|
1.2 |
Prior to commencing the Works the Grantee
will sign and complete all contracts required to enable the Grantee to
fulfill the Approved Purposes including all contracts with contractors and
professional advisers before the work to which such contracts relate is due
to commence. Each such contract shall
provide for the provision of the work or services contracted for on terms
which do not differ to a material extent (save as provided by this Contract)
from the terms (including appropriate provisions for a retention on practical
completion) that would be entered into by a reasonably experienced relevant
employer engaging parties to provide similar work or services for projects of
the size, value, complexity and prominence of the Approved Purposes. Any material divergence from such terms
requires the Approval of NHMF. |
|
|
1.3 |
NHMF may reduce the Grant by such amount
as it thinks fit up to an amount which bears the same proportion to the
difference between the lowest tender price and the price of the tender
accepted by the Grantee as the Grant bore to the original cost of the
Approved Purposes if NHMF, in its absolute discretion, disagrees with the
reason given by the Grantee for not accepting the lowest tender. |
|
|
1.4 |
The Grantee agrees that it shall only
accept tenders that it believes in good faith will result in the Approved
Purposes being carried out to the standard prescribed by Special Conditions 2
and 9 of this Contract. |
|
|
2. |
The Grantee shall carry out the Works or
shall procure that the Works are carried out in a professional manner in
accordance with currently accepted best practice in the Information
Technology industry. The Grantee will
ensure that best practice or proven and widely adopted standards are applied
especially in the areas of project management, requirements analysis, system
or application, design, testing, documentation, installation and maintenance
and in the area of the preservation of digital materials. |
SCAN believes that it is carrying out the
Works and procuring the Works in a professional manner in accordance with
currently accepted best practice in the Information Technology industry |
|
3. |
Prior to commencing the Works the Grantee
shall secure to NHMF’s satisfaction all necessary planning permissions
building consents and statutory approvals. |
Fulfilled |
|
4. |
Prior to commencing the Works the Grantee
shall prepare a detailed cost plan for carrying out the Approved Purposes in
a format which has been agreed in advance by NHMF and shall submit the same
to NHMF for Approval. Thereafter the
Grantee shall spend the Grant and other funds provided for the Approved
Purposes only in accordance with the Approved cost plan (“the Cost Plan”). The Grantee must obtain prior written
Approval for any changes in expenditure which are not in accordance with the
details of the Cost Plan and in particular for movement of funds between the
various elements of the Cost Plan. |
Detailed cost plan submitted and agreed with the HLF. No changes in expenditure have been made
without prior written approval. The budget has been updated following the PID
review and a report detailing the variations form the original budget
estimates has also been submitted for discussion with the HLF at our next
quarterly meeting |
|
5. |
Prior to commencing the Works the Grantee
shall prepare a draft monthly project report form and a draft monthly cash
flow report form and shall submit the same to NHME for Approval. Thereafter the Grantee shall submit signed
monthly reports in the Approved forms to NHMF until the Approved Purposes
have been fulfilled. |
Signed monthly project reports and
monthly cash flows are submitted to the HLF |
|
6. |
Prior to commencing the Works the Grantee
shall submit to NHMF for Approval a revised and updated programme for the Project. For the avoidance of doubt the Programme
shall contain details of the works to be carried out at the development
stage. The Grantee shall only carry
out the Works in accordance with the Approved programme (“the Programme”) or
any modification thereof Approved by NHMF. |
The Project Initiation Document (PID) was
submitted to the HLF as requested. The revised PID has also been submitted
and discussed with the HLF |
|
7. |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance of the project on terms which note the interest of and
are Approved by NHMF. |
Insurance has been obtained and full
details given to the HLF. Any renewal notices will automatically be dealt
with by SCAN |
|
8. |
Prior to issuing invitations to tender
the grantee shall prepare a report on the information and communication
technology to be installed at the Property pursuant to the Approved Purposes
and without prejudice to the generality of the foregoing the report shall
include:- |
An ICT report was prepared and the
tendering process undertaken as agreed. The ICT infrastructure is now in
place and has been paid in full. The next requirement will be to increase the
data storage capacity as the digital imaging workflow increases |
|
8.1 |
a feasibility report |
|
|
8.2 |
the specification for the Digital
Deliverables |
|
|
8.3 |
the design of the system which shall in
particular include details of all interactives |
|
|
8.4 |
the proposals for the purchase of network
infrastructure. |
|
|
|
On receipt of Approval for the report
(“the ICT Report”) the Grantee shall prepare invitations to tender and tender
evaluation criteria for such works and shall submit the same to NHMF for
Approval. Thereafter the Grantee shall
issue invitations to tender in accordance with the Approved tender
invitations and evaluation criteria. |
|
|
9. |
The Grantee shall carry out the
information and communication technology works in accordance with currently
accepted best practice in the Information Technology industry. The Grantee will ensure that best practice
or proven and widely adopted standards are applied especially in the areas of
project management, requirements analysis, system or application
specification, design testing, user and system documentation, installation
and maintenance and in the areas of the preservation of digital materials. |
SCAN believes it has fulfilled and is
fulfilling this condition |
|
10. |
The Grantee shall submit to NHMF for
Approval details of the standards that the Grantee intends to implement. |
SCAN has submitted to the HLF its draft
cataloguing standards |
|
11.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report for the safeguarding and enhancement of, and public
access to, the Property including without limitation its proposals for: |
|
|
|
a) such
testing as may be necessary to demonstrate that the Digital Deliverables and
capable of fulfilling the Approved Purposes |
Schedule of Requirements for the Supply of
Digital Cameras |
October 1999 |
Information and Communications Technology
Requirements |
March 1999 |
||
Information and Communications Technology
Tender Document |
February 2000 |
||
Test plan submitted for installation of
ICT equipment |
October 2000 |
||
Data Capture Specification for Indexes |
November 1999 |
||
Website design specification |
November 1999 |
||
|
b) such
evaluation as may be necessary to demonstrate that the Digital Deliverables
are capable of fulfilling the Approved Purposes |
Evaluation and
selection criteria for ICT equipment submitted in evaluation report “SCAN ICT
Requirements Tender Report” |
April 2000 |
Book Cradle
Evaluation |
July 2000 |
||
Web Site Tender
Evaluation |
January 2000 |
||
Camera
Evaluation for HLF |
May 2000 |
||
Resolution
Requirements for Testaments |
May 2000 |
||
Data Capture
Tender Evaluation |
December 2000 |
||
|
c) the
preservation and security of all data and other material collected or
created in the course of carrying out
the Approved Purposes by the keeping of back-up copies of the Digital Deliverables and
otherwise; |
Weekly backups
and daily incremental backups take place for all SCAN information (excluding
images) |
April 2001 |
Uncompressed TIFF images are written to
DLT and stored locally |
November 2000 (and ongoing) |
||
Compressed JPEG images are written to the
Internet Server where a backup is taken weekly |
November 2000 (and ongoing) |
||
|
d) the
form of licence(s) to be used by the Grantee permitting third party
exploitation of the Intellectual Property; |
This was included as part of the contract
negotiations with the Genealogical Society of Utah. The HLF have a copy of
this document July 1999 |
|
|
e) the
form(s) of assignment(s) consent(s) waiver(s) licence(s) or permission(s) to
be used by the Grantee for the securing of third party rights in the
Intellectual Property; |
|
|
|
f) error
correction, maintenance and updating of the Digital Deliverables |
Data flow diagram of the digitisation
process available May 2001 Proposed data flow for the maintenance of
distributed data for the online catalogues available from May 2001 |
|
|
g) user
manuals or instructions and interfaces for the Digital Deliverables and its
use. |
All manuals
received for ICT equipment and standard operation of digital cameras Additional operator manual developed with
GSU for the use of the digital camera. ser manual produced in association
with the GSU for the installation, maintenance and delivery of digital
imaging in June 2000 Guidelines for capture of fonds level
descriptions produced by SCAN in September 2000 |
|
|
Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. The Grantee must obtain prior written
Approval for any changes in the proposals which are not in accordance with the
Approved reports |
|
|
11.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
12.1 |
Prior to commencing the Works relating to
the information communication and technology the Grantee shall submit to NHMF
for Approval a report on the hardware technology to be used with the Digital
Deliverables (“the Hardware”) including without limitation its proposals for: (a) such
testing as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved Purposes; (b) such
evaluation as may be necessary to demonstrate that the Hardware is capable of fulfilling the Approved
Purposes; (c) error
correction, maintenance and updating of the Hardware; and (d) user
manuals and instructions for the Hardware and its use. Thereafter the Grantee shall submit
signed monthly written reports in the form agreed with NHMF and show the
progress made in relation to the above matters. On receipt of Approval of the said monthly
reports the Grantee shall implement the reports in carrying out the Approved
Purposes. The Grantee must obtain
prior written Approval for any changes in the proposals which are not in
accordance with the Approved reports. |
A presentation
and report covering the entire ICT requirements for the project was given |
May 2000 |
Information and
Communications Technology Requirements |
March 1999 |
||
Information and
Communications Technology Tender Document |
February 2000 |
||
Test plan
submitted for installation of ICT equipment |
October 2000 |
||
Data Capture
Specification for Indexes |
November 1999 |
||
12.2 |
On receipt of Approval of such proposals
or monthly reports the Grantee shall implement such proposals in carrying out
the Approved Purposes. |
|
|
13. |
The Grantee shall enter into a deposit
agreement with a third party Approved by NHMF for all Digital Deliverables
and any associated or necessary software and applications and shall
thereafter deposit escrow copies of the said Digital Deliverables on a basis
to be agreed with NHMF. |
Escrow discussed
for deposit of digital images. SCAN has a contract clause with GSU to provide
mutual restore and backup of digital images |
Early
discussions held with NCC Follow Up
Required |
14. |
The Grantee shall ensure that all
applications and software necessary to access use or present the digital
deliverables are transferable to a third party. |
Escrow discussed
for deposit of any software packages |
Early
discussions held with NCC Follow Up
Required |
15 |
The Grantee agrees that it shall take all
reasonable steps to mitigate to NHMF’s satisfaction the amount of VAT payable
upon, or to recover the VAT payable upon, or to recover the VAT attributable
to, the cost of fulfilling the Approved Purposes. The Grant shall be reduced by an amount which
bears the same proportion to the VAT not payable or recovered as the Grant,
prior to such decrease, bore to the original costs of the Approved Purposes. |
SCAN has fulfilled this condition: VAT is fully recovered. |
|
16 |
At the end of Year 1 the Grantee is to produce a policy statement to support the extensibility of membership of Scottish Archive Network Limited with no financial implications. |
SCAN supports the extensibility of
membership of the Scottish Archive Network with no financial implications. Currently
there is an interest shown by the Roman Catholic Archdiocese of Glasgow
Archives for inclusion |
|
17 |
The Grantee will effect and maintain (or
will procure the effecting and maintenance of) during the Works construction
and project insurance for the Project on terms which note the interest of and
are Approved by NHMF. |
SCAN has fulfilled this condition |
|
18 |
The documents required to be submitted or
provided to NHMF under these special conditions, are required to be submitted
or provided by the Grantee only for NHMF’s own purposes in connection with
the Grant and NHMF’s approval or acceptance of such documents cannot be taken
as approval or acceptance for any other purpose. |
This is accepted by SCAN |
|
|
19. [Clause
to go in here annexing contracts between a Scottish Archive Network Ltd and
others] |
|
|
20 |
The Grantee shall take account of any
representations which NHMF may make with regard to the carrying out of the
Approved Purposes in accordance with the Programme, Design, specification,
Cost Plan, ICT Report and the contracts referred to in special conditions
1.1. In particular the Grantee shall
take account of any representations which NHMF may make prior to the issue of
a certificate of practical completion of the Works and shall pass such
representations on to the person authorised to sign a certificate of
practical completion. |
This is accepted by SCAN |
|
21 |
Without prejudice to the generality of
Clause 13.2 of this Contract NHMF may at any time appoint by notice in
writing to the Grantee a third party (“the Lead Monitor”) to monitor the
progress of the Approved Purposes and additional monitors to advise on
specialist matters arising from the implementations regarding the Approved
Purposes the Grantee shall take such reasonable steps as may be necessary to
comply with the recommendations. |
This is accepted by SCAN |
|
22 |
Prior to commencing the Works the Grantee
shall secure to the satisfaction of NHMF all the additional funding required
to complete the Approved Purposes. |
The additional funding required by the
HLF was secured. Budget projections supplied to HLF in March 2001 indicate
that the project will complete within budget and with the agreed percentage
of partnership funding |
Notes of Project Board Meeting
23 October 2001 14.00
Attendees:
Rob Mildren (Chair), George Mackenzie, Stuart Low (Minute Secretary).
Apologies:
Peter Anderson
1. Minutes
of Last Meeting Review of Action Points
1.1 It was noted a meeting had been planned between George and
Linda Ramsay to discuss the integration of SCAN/NAS conservation services. Action:
GM
1.2 It was confirmed that both Ian Hill and David Brown had
attended the participating archives meeting on 5th October on behalf
of the NAS.
1.3 It was noted that the tendering process for the additional
server storage had been delayed due to a change in procurement procedures.
1.4 It was noted that the distributors for both CALM and Adlib had
been contacted with a view to providing bids to supply proprietary cataloguing
software to the NAS and SCAN. It was further noted that over 20 participating
archives had expressed an interest in obtaining copies of this software through
SCAN, subject to HLF approval. It was noted that this would be largely funded
from within the IT for Participating Archives budget heading.
1.5 It was agreed that George would confirm with Jim Grady that
any outstanding audit issues between the NAS and SCAN had been resolved. Action:
GM
1.6 It was confirmed that Stuart had attended the last NANURG
meeting in Manchester on 22nd October.
1.7 It was agreed that Rob and George would meet with Eddie Friel
(Glasgow & Clyde Tourist Board) on 1st November to discuss how
he might be able to assist with marketing SCAN’s services. It was agreed to
reschedule the team meeting on 1st November to 2.30pm.
Action:
RM/GM/SL
2.0 Review of Workplans
2.1 Online Catalogues
2.1.1 It was agreed that Alan should liase with Ian Hill over his
proposed schedule of visitations to participating archives. Rob to discuss with
Alan. Action:RM
2.1.3 It was agreed that Rob and George should arrange to revisit
participating archives that had been visited early on in the project where it
could help Alan’s programme for completing finding aid work. It was suggested
that this might help to reaffirm their commitment to the project and would be a
useful way of demonstrating SCAN’s policy of inclusion. Action:
RM/GM
2.2 Internet Resources
2.2.1 It was noted that this strand of the project was progressing
satisfactorily and that the data capture of the Sasine records was now
complete.
2.2.2 It was noted that the NAS should be kept aware of any other data
capture projects, which might be planned. It was further noted that a meeting
had been planned with the NAS to discuss possible future digitising projects.
2.3 Testaments
2.3.1 It was noted that it was intended to keep back-up tape copies of
the last 10 tapes sent to the GSU in Salt Lake City, on a rotational basis.
This will keep enough space free on the server to resolve any operational problems.
2.3.2 It was noted that correspondence had been received from the
Association of Scottish Genealogists and Record Agents suggesting that proposed
charges for obtaining copies of testaments from the NAS search rooms were too
high. It was agreed that two pricing structures might need to be introduced to
reflect the differing needs of users and different service delivery mechanisms,
which were envisaged, and that SCAN should have an input to the price fixing
process. It was clarified that access to a virtual image would be provided free
of charge and that charges would only be incurred when an actual copy was
requested. It was agreed that George would draft a reply to ASGRA to address
their concerns. It was also agreed that representatives of ASGRA be invited to
visit the project around the end of January 02.
Action:
GM/RM
2.3.3 It was noted that a letter had been received from Mr Chin (PRO)
expressing his appreciation for the time granted him during his recent visit to
the project.
3.0 Procurement
3.1 It was confirmed that the final two cameras had been now been
installed in the GSU camera room.
4.0 Staffing
4.1 It was noted that the online catalogues team would be back up
to full strength by 29th October. This will allow SCAN to plan the
future programme for completing participating archives work Action : AB
4.2 It was noted that the project’s Head Conservator had resigned
in September. It was further noted that the conservation service would now
proceed as an integrated SCAN/NAS function. It was noted, however, that a
mechanism still required to be established, which would allow the NAS to
recover the costs of providing a conservation service to the project and meet
the conservation requirements of the project.
5.0 Finance
5.1 It was noted that the next Drawdown would be submitted w/c 29
October.
5.2 It was noted that the McCabe Partnership had now been given
all the information they required to prepare the financial statement for SCAN
for 2000/2001, and that this should be available by the end of November.
5.3 It was noted that the VAT Return for the period July to Sept
01 had been submitted. The total amount of VAT reclaim was £4,238.81.
5.4 It was noted that SCAN’s office and computer engineering
insurance was due to be renewed from 21st October 2001. Noted that
Stuart was in the process of obtaining quotes, and that temporary cover had
been arranged. Action:
SL
6.0 Participating Archives
6.1 It was noted that the meeting held on 5th October
had been a well attended and successful event and that 17 of those archives
represented had expressed an interest in procuring proprietary cataloguing
software, through SCAN funding.
6.2 It was agreed that a licensing arrangement, which would allow
participating archives to have images available in their search rooms, should
be discussed and developed. Action: RM
6.3 It was noted that a further full meeting of the participating
archives would be arranged for sometime next year.
6.4 It was agreed to send out an amended version of the HLF
narrative report to participating archives on a monthly basis and to also make
this available on the NAS Intranet. Action:
SL/RM
6.5 It was noted that SCAN had agreed to fund staff members from
participating archives who wished to attend the SoA’s EAD Edinburgh workshop in
November. It was further noted that the HLF were very supportive of this
initiative.
7.0 NANURG Meeting
7.1 It was noted that Stuart had attended the last meeting of the
NANURG group on 22nd October in Manchester.
7.2 It was noted that it had been decided to approach the existing
user group/participating archives working group with the intention of using
them as a focus group for the Scottish evaluation session. It was also noted
that Joanna would speak to the post-graduate student’s visit to repositories
group regarding their potential participation.
7.3 It was noted that arrangements were now in place to run all
three evaluation sessions and that steady progress was being made with
recruiting participants for each venue.
7.4 It was noted that a draft questionnaire would be distributed
w/c 5th November.
7.5 It was noted that a total of £4,000 would be requested from
Re:source to fund the evaluation sessions and the completion of the report. It
was noted that SCAN had confirmed that it might be able to contribute towards
some of the costs associated with the Scottish evaluation session.
7.6 It was noted that the final report would be completed by
mid-February and that Re:source would retain the copyright to this. It was also
noted that the final report would be circulated to Re:source members and other
interested parties as well as being posted on the NCA website.
8.0 Indexing
8.1 It was noted that work on the Stair Society project was
progressing satisfactorily.
9.0 Marketing/Publicity
9.1 It was noted that the participating archives were supportive
of a launch event and were happy to go along with whatever SCAN decided to
arrange.
9.2 It was proposed that Argyll’s Lodging, in Stirling, be used as
a venue for the launch event for the online catalogues. It was noted that a
timeframe within which to host this event would need to be identified
reasonably quickly in order to confirm the availability of this venue.
9.3 It was noted that no real feedback had been obtained from the
participating archives regarding the design or size of a SCAN poster. It was
agreed to follow this up at the next PAWG meeting. Stuart to put on Agenda. Action:
SL
9.4 It was noted that Hazel and Joanna would be attending the
“From Saltmarket to Salt Lake” SAFHS annual conference organised by Glasgow
& West of Scotland FHS to be held on Saturday 27th April, 2002
in Glasgow.
10.0 Date of Next Project Board
The next project board will be
held on Friday 23rd November at 14.00 in TTH.