At the Pass of Killicrankie the banks were so precipitous
and steep at that point that the line had to be supported by breast of
retaining walls to the extent of 690 lineal yards, and to the average
height of 26 feet, the extreme height of one being 55 feet; and in order
to carry the railway at the narrowest point in the Pass where the precipices
close in, as it were, on either side, and afford scarcely any additional
space beyond that occupied by the channel of the river, instead of supporting
the line by breastwalls, it was deemed prudent to construct a viaduct
of 10 arches, 60 feet above the river, which with a tunnel at the north
end carried it successively through the Pass. At two other points in the
line, in running up the sides of the Garry, breastwalls had to be formed,
respectively 94 and 35 yards in length, and 15 feet in average height.
All these breastwalls, extending to 1650 lineal yards, are built with
lime, and set on a solid foundation of dry gravel or rock, at right angles
to the face of the wall, which batters at the rate of 1½ inch to the foot.
The writer prefers the curves to the straight batter, as it gives more
effectual resistance if well built; but breastwalls are to be avoided
wherever earth embankments can be substituted, as, in his experience,
there are subtle influences in the Scottish Climate of alternate frost
and wet in winter, which operate imperceptibly to their destruction, and
they require careful and constant inspection.
In running through so large an extent of mountainous
country the line, as might be expected, had to pass over some lengths
of soft ground and morass. The principal of these were for two miles near
the town of Nairn, also for about two miles near Keith, one mile near
Dava Moor, and about a mile in crossing through a hollow at Drumochter
on the summit of the Grampians. In all places where the ground was particularly
soft, a uniform mode of treatment was adopted. Two parallel drains were
first cut outside the fences, about 50 feet apart, from4 to 6 feet deep,
and with slopes of 1 to 1. This drained off the surface-water; and, after
making up the holes and other irregularities of the surface with turf,
the space for the railway to a breadth of about 15 feet was covered with
two or three layers of swarded or heather turf, having the sward side
of the lower layer undermost, and that of the top layer up, the joints
breaking band. In this way a good sustaining surface has uniformly been
obtained.* On this bed of turf the ballast
was laid for 2 or 3 feet in depth. This was quite sufficient to support
the traffic, but as in some cases the bed of moss was from 20 to 30 feet
in depth, the railway merely floated on the surface, and was in the first
instance undulating, and yielded in some parts from 3 to 4 inches under
the weight of the engines passing over. To obviate this undulation longitudinal
beams of timber were tried at one place, 20 to 40 feet long, below the
sleepers, but his was found objectionable, as rendering it more difficult
to raise or repair this surface of the road; and an additional sleeper
(making the sleepers 2 foot 6 inches from centre to centre, instead of
3 feet) was found preferable. There was nothing for it, at the worst,
but to lift the road every other week as it sunk, until it had acquired
a solid bearing. In many places we had to lay on 4, 5, or 6 feet in depth
of additional gravel, and in one place no les than 27 feet, before the
road became solid. In the course of two or three years, however, with
the attention, the tails being fished, the lines through these mosses
were all that could be desired for solidity and performance.
As the writer has said, in crossing so many mountain-rivers,
bridges of magnitude had to be constructed, involving considerable varieties
of execution. The principal of these bridges may now be described, and
any peculiarity will be noticed which may have arisen during the progress
of the works. It will be observed that the beds of the rivers in the north
of Scotland differ in many respects from what is common in England, consisting
frequently of depths of 10 or 12 feet of gravel and boulders, the solid
and compact debris of successive floods, below which, if the country is
of rocky formation, there is usually hard clay and then rock, or, as in
the case of the mouth of the River Ness, after penetrating 12 feet of
shingle and boulders, a sort of admixture of whitish clay and sand was
obtained. In some cases we had to deal with soft clay and mud of great
depth, but these were exceptions. Nor was it possible in general to ascertain,
by boring, the precise nature of the foundations, because many of the
boulders in the gravel were of large size, and were often mistaken for
rock. The only way in which an approximate knowledge of the foundations
could be obtained was by driving iron rods at various places, and when
the bed of the river admitted of it, wooden piles. Still we worked very
much in the dark; but the writer's long experience of these rivers, and
of the nature of their floods, was of great advantage in enabling him
to fix the depth of the foundations and the precise description of works
to secure the necessary stability of construction. In only two of three
cases was there any fear of sinking. What had chiefly to be guarded against
was sudden and impetuous floods, sometimes accompanied with floating ice
and trees, undermining the foundations and damaging the piers; it was
therefore important to provide ample waterway. The construction of these
bridges [lasted?]** over twelve years, and
during that time there has been considerable changes in bridge building,
by the adoption of iron cylinders for piers, and lattice girders in spanning
the waterways, so that, as the works progressed, these improvements were
adopted where found suitable.
*Author's note: "Had
this plan, which the writer has found to answer to well both for roads
and railway, been adopted in the clayey ground at Balaklava in the Crimea,
a good road might have been formed, 1867".
**Transcriber's note: this
word is illegible
TOP
|